Horsham Policy 38: Flood Risk & Drainage Requirements
Contact Us
Horsham Policy 38 (Flooding), in the Horsham District Planning Framework adopted in November 2015, is the flood policy Horsham District Council applies to every application, with West Sussex County Council advising on surface water as the Lead Local Flood Authority. The requirement most often missed is local: Horsham asks for a Surface Water Drainage Statement with any application that adds a building, an extension or hard surfacing, however small. A replacement Local Plan is at examination: the hearings have closed, and the Inspector expects to report no later than January 2027.
This page sets out what Horsham District Council, West Sussex County Council and the Environment Agency each need to see on flood risk and drainage, policy by policy, and what our reports contain to satisfy each one. To talk a Horsham application through, call 01293 214444 or email enquiries@unda.co.uk.
Where Horsham's Local Plan stands in November 2026
Two plans matter on a Horsham application today. The adopted Horsham District Planning Framework (HDPF, November 2015) is the development plan, and Policy 38 is its flood policy. Behind it, the emerging Horsham District Local Plan 2023-2040 is at examination: it was submitted on 26 July 2024, hearings were held in December 2024 and, after a new Inspector was appointed in January 2026, resumed in April 2026, and the council consulted on its proposed main modifications from 13 July to 24 August 2026.
The October 2026 examination hearings were held from 13 to 22 October 2026 (hearing sessions page), and the Inspector does not expect any further sittings. No Inspector's report had been published by 2 November 2026. The Inspector's post-hearing letter of 30 October 2026 (IDJB14) says a small number of changes to the main modifications will be published for further consultation, and that he expects to submit his report no later than January 2027. The council's June 2026 provisional timetable (HDCJB11) gives adoption as January 2027, date to be confirmed. Until adoption, the main modifications carry weight in decisions but Policy 38 remains the policy an application is tested against.
MM61 is the flood modification. It replaces the submitted text of proposed Strategic Policy 10 (Flooding) in full. MM59 deletes the water neutrality policy and renames proposed Strategic Policy 9 "Water Efficiency". A third plan, Horsham District 2045, has only reached its scoping consultation (30 June to 28 July 2026) under the new plan-making system and has no flood policies yet.
District, county or Environment Agency: who decides what on a Horsham application?
| Body | Role | What it decides or is consulted on |
|---|---|---|
| Horsham District Council | Local planning authority (outside the South Downs National Park) | Validates and determines the application against the HDPF; consents works to ordinary watercourses under a local designation agreement |
| West Sussex County Council | Lead Local Flood Authority | Statutory consultee on surface water for major development; applies its August 2026 SuDS guidance |
| Environment Agency | Statutory consultee | Development in Flood Zones 2 and 3 near Main Rivers such as the Arun and the Adur; flood warnings; permits for works near a Main River |
| Southern Water | Sewerage undertaker | Capacity and connections where surface or foul water goes to a public sewer |
| South Downs National Park Authority | Local planning authority inside the park | Applications in the south of the district that fall inside the National Park |
Horsham decides. West Sussex County Council, as the Lead Local Flood Authority, reviews the drainage on major schemes, and an unanswered county objection is something the district has to weigh before it can grant permission. On minor schemes the district's own officers read the Surface Water Drainage Statement. Ordinary watercourse consent is unusual here: Horsham District Council, not the county, determines it.
Horsham's flood and drainage policies, and how we meet each one
| Policy | Title | What it requires | Your obligation | How Unda meets it | Source and date |
|---|---|---|---|---|---|
| Policy 38 | Flooding | A sequential approach to flood risk; a site-specific flood risk assessment for all development over 1 ha in Flood Zone 1 and all proposals in Flood Zones 2 and 3; where there is the potential to increase flood risk, SuDS where technically feasible | Show the site is safe for its lifetime and does not raise flood risk elsewhere | A site-specific flood risk assessment covering every source, with the sequential test where it applies | HDPF, adopted 27 November 2015 |
| Policy 24 | Environmental Protection | Protection of the environment, including water, from the effects of development | Deal with pollution risk to watercourses from runoff | Water quality treatment set out in the drainage strategy | HDPF, adopted 27 November 2015 |
| Policy 35 | Climate Change | Development that adapts to a changing climate | Allow for climate change in flood and drainage evidence | Current Environment Agency allowances applied in the FRA and the drainage calculations | HDPF, adopted 27 November 2015 |
| Strategic Policy 10 (proposed, main modifications) | Flooding | No flood risk to occupiers, users or visitors; FRA in Flood Zones 2, 3a and 3b, and in Flood Zone 1 on sites of 1 ha or more, critical drainage problem land, land at increased future risk, or land at risk from any source where a more vulnerable use is introduced; sequential test; where there is the potential to increase flood risk, SuDS unless technically unfeasible and no surface water to the foul sewer | Prepare evidence that will meet the modified policy if the plan is adopted before determination | Reports written to Policy 38 and to MM61 together | Main modifications MM61, consulted July 2026 |
| Strategic Policy 9 (proposed, main modifications) | Water Efficiency | New homes to use no more than 110 litres of mains water per person per day; non-domestic buildings BREEAM Excellent in the Water category | Design to the water efficiency standard; no water neutrality case | Drainage strategy kept consistent with any rainwater reuse proposed | Main modifications MM59, consulted July 2026 |
Requirements checked November 2026.
Horsham Policy 38 (Flooding): what it asks of an application
Policy 38 steers development away from flood risk and asks for a site-specific flood risk assessment wherever a site is in Flood Zone 2 or 3, or is over a hectare in Flood Zone 1. Horsham's validation list widens the trigger: an FRA is also needed on Flood Zone 1 land the Environment Agency has flagged for critical drainage problems, land the SFRA shows at increased future risk, and land at risk from other sources where a more vulnerable use is proposed.
Officers look for three things: every source assessed (river, surface water, groundwater, sewer and reservoir), climate change applied to the design flood, and a layout that keeps the vulnerable parts of the scheme out of the wetter ground. An FRA that reads the national flood map and stops meets none of the three. Our assessment works from the SFRA's climate change extents, sets floor levels and safe access against them, and includes the sequential test where Policy 38 and the validation list call for one.
Horsham Policy 24 (Environmental Protection) and Policy 35 (Climate Change)
Both sit beside Policy 38 in the HDPF, and neither is a flood policy in its own right. A drainage submission still meets each of them: Policy 24 by treating runoff before it leaves the site, Policy 35 through the climate change allowances in the flood and drainage figures. Our drainage strategies show a treatment train for runoff from roads and parking, and every storm in the calculations uses the current allowance.
Proposed Strategic Policy 10 (Flooding): what changes on adoption
Strategic Policy 10, as modified by MM61 in the July 2026 main modifications, is broader than Policy 38. It opens with "Development proposals should not present a risk from flooding to potential occupiers, users, or visitors", and states "In Flood Risk Zones 2, 3a and 3b, a site-specific flood risk assessment should accompany all development proposals." Where there is the potential to increase flood risk, it requires SuDS "unless technically unfeasible" and says surface water must "not be allowed to drain to the foul sewer" (Schedule of Proposed Main Modifications).
Policy 38 already requires SuDS where technically feasible on schemes with the potential to increase flood risk. MM61 keeps that test, now worded "unless technically unfeasible", and adds that surface water must "not be allowed to drain to the foul sewer", that there must be no net loss of flood storage capacity, and that a management plan must maintain the flood water assets in perpetuity. A scheme that will be determined in 2027 should be designed to the modified wording now. We write reports against both texts while the plan is at examination.
Proposed Strategic Policy 9 (Water Efficiency) and the end of water neutrality
Natural England withdrew its water neutrality position for the Sussex North supply zone on 31 October 2025, and the council's water neutrality page says water neutrality no longer needs to be considered in planning assessment. Under the main modifications, Strategic Policy 9 becomes a water efficiency policy at 110 litres per person per day. The background is in our article on water neutrality in planning.
Applying to Horsham before the new plan is adopted?
Our consultants write each report to Policy 38 and to the modified wording of proposed Strategic Policy 10, so a decision in 2027 finds nothing out of date. Get a no-obligation, free quote. One of our experienced flood risk consultants will get back to you within 60 minutes. Call 01293 214444 or email enquiries@unda.co.uk.
Start a QuoteWhich reports a Horsham application needs, trigger by trigger
| Trigger | Flood risk assessment | Sequential test | Surface Water Drainage Statement or drainage strategy |
|---|---|---|---|
| Any part of the site in Flood Zone 2 or 3 | Required | Required unless exempt under NPPF policy F5 (householder development, non-residential extensions under 250 m², changes of use other than to caravan, camping, chalet, mobile home or park home sites, or where an FRA shows no built development would be at risk) or the site was allocated after a sequential test | Required where buildings or hard surfacing are added |
| Flood Zone 1, site of 1 ha or more | Required | Not required on flood zone grounds | Required; a full drainage strategy on major schemes |
| Flood Zone 1 with EA critical drainage problems, SFRA future risk, or other sources and a more vulnerable use | Required | Required where surface water or other flood risk is medium or high | Required |
| Major development (10+ homes, 0.5 ha+ for unknown numbers, 1,000 m²+ floorspace or 1 ha+) | As above by flood zone | As above | Drainage strategy reviewed by West Sussex County Council as LLFA |
| Minor scheme adding any building, extension or hard surfacing | By flood zone | By flood zone | Surface Water Drainage Statement, proportionate to the scheme |
| Works in or next to an ordinary watercourse | Not triggered by the works alone | Not triggered | Ordinary watercourse consent from Horsham District Council |
These triggers come from the council's Local Information Requirements for Validation, which is undated on its web page and still cites the superseded 2024 Framework; where its wording differs from the August 2026 NPPF (its 250 m² exemption covers all small non-residential development, F5's covers extensions only), the NPPF prevails. A missing statement is a validation failure rather than a reason for refusal, so the application simply does not start. Our note on why applications are invalidated for flood risk and drainage covers the usual gaps.
The sequential test is a separate report from the FRA. It asks whether a reasonably available site at lower risk exists, and on a Horsham application the area of search is set by the scheme's catchment. Our explainer on the sequential and exception tests sets out how the two tests fit together.
The Horsham SFRA and the Surface Water Drainage Statement
The current evidence is the Level 1 Strategic Flood Risk Assessment prepared by AECOM for the Local Plan, final revision P03 dated 5 September 2024. It uses the Environment Agency's Upper Arun model for Horsham and treats the climate change extent conservatively. When the validation list asks whether the SFRA shows a site at increased future risk, this is the report to read. The council's older SFRA web page still lists only the 2007 study and its 2010 revision; the 2024 report sits in the Local Plan evidence. Our guide to Strategic Flood Risk Assessments explains the Level 1 and Level 2 split.
Horsham's Surface Water Drainage Statement guidance sets its own tests. On a major application the statement must be signed by a competent drainage engineer recognised by the Engineering Council, the Institution of Civil Engineers or an equivalent body. Soakaways must be designed from BRE Digest 365 percolation tests with a minimum factor of safety of 2, infiltration units must half-empty within 24 hours for storms up to 1 in 10 years, and "House or rubble soakaways are not acceptable". Discharge to a sewer or highway drain needs evidence of spare capacity downstream.
West Sussex County Council's drainage standards for Horsham schemes
West Sussex County Council's Complying with the National Standards for SuDS (August 2026) is the standard the LLFA applies to major Horsham applications, and its SuDS page (updated 28 August 2026) says the county "will not accept high density housing or lack of space as reasons to exclude source control SuDS". The guidance follows the 2025 National Standards for SuDS and adds firm numbers of its own.
| Requirement | West Sussex County Council standard (August 2026) |
|---|---|
| Discharge rate | Restricted to greenfield runoff rates, calculated without climate change or urban creep |
| Everyday rainfall | First 5 mm of frequent rainfall intercepted on site |
| Design events checked | 1 in 1, 1 in 30 plus climate change and 1 in 100 plus climate change, with 10% urban creep |
| Climate change | Peak rainfall allowances from the Environment Agency climate change allowances |
| Infiltration testing | BRE 365 or an approved method, three tests per pit, lowest rate used in design |
| Groundwater | Maximum groundwater level established; winter groundwater and infiltration results at outline stage |
| Drain-down | The 3.33% AEP plus climate change event half-empties within 24 hours |
| Exceedance | Plan for the 1% AEP plus climate change event: no off-site, property or critical infrastructure flooding, safe access kept |
| Outline applications | At least one viable drainage method, a layout showing attenuation and outfalls, and a catchment plan |
Of these, the outline-stage groundwater evidence costs most time, because winter monitoring cannot be compressed into a dry month. Where the ground is Weald Clay, infiltration is often limited. Our geology and soakaway checker and BRE 365 infiltration rate calculator give an early read before trial pits are dug. The county also runs a paid pre-application advice service for major schemes, and says its SuDS proforma and validation checklist are under review against the national standards; until the review ends, applicants use the current versions and note where the newer standards were followed instead.
National policy behind Horsham's requirements
The National Planning Policy Framework published on 17 August 2026 moved flood risk into Chapter 18, Managing flood risk and coastal change, with policies F1 to F9. F4 sets when a site-specific assessment is needed, F5 and F6 the sequential and exception tests, and F8 the expectation that development meets the National Standards for sustainable drainage. The flood risk and coastal change guidance was last updated on 17 September 2025. Our summary of what the August 2026 NPPF changed and our NPPF guidance service cover the detail.
Climate change allowances come from the Environment Agency's guidance, last updated on 27 May 2022, by management catchment: the 2024 SFRA places Horsham District in two, the Arun and Western Streams and the Adur and Ouse management catchments. Our article on climate change allowances for planning explains which epoch applies to which development.
Flood risk in Horsham District in brief
Two river systems drain the district. The River Arun rises in St Leonard's Forest, runs along the south side of Horsham town before turning south past Pulborough, while the River Adur rises at Slinfold and gathers its branches near Henfield. Small ordinary watercourses such as Parson's Brook near Barns Green sit with the council and the county, not the Environment Agency.
Surface water is the most frequently recorded source of flooding in the district, according to the West Sussex Local Flood Risk Management Strategy (July 2025). The county's only internal drainage district, the Arun Internal Drainage District, is run by the Environment Agency acting as the drainage board; a site on the Arun floodplain should check whether it falls inside it. For the town's flood history see our page on flood risk assessment in Horsham, and screen a postcode on our flood risk map.
Reports for a Horsham District Council application
A flood risk assessment asks whether the site is safe, the sequential test asks whether it should be there at all, and a drainage strategy shows where the surface water goes. Horsham can ask for any of the three, and each row below gives the requirement that brings it in.
- Assessment of every source. Policy 38 and the validation list decide when Horsham needs one, and our flood risk assessment service covers every type.
- For the application. A Horsham submission in Flood Zone 2 or 3, or over a hectare in Flood Zone 1, needs a flood risk assessment for planning.
- Buying in the district. Where a search flags the Arun or Adur floodplain, a flood risk survey for property purchase looks at the building itself.
- Locational tests. Horsham's validation list asks for a sequential and exception test (the exception test where applicable) wherever any part of the site is in Flood Zone 2 or 3 or at medium or high risk from surface water or other sources, unless an exemption applies.
- Drainage evidence. The Surface Water Drainage Statement on every scheme adding hard surfacing is a drainage strategy scaled to the site.
- Major schemes. West Sussex County Council's greenfield-rate and 5 mm interception rules are met in a surface water drainage strategy.
- After permission. Pre-commencement drainage conditions on Horsham consents are cleared through discharge of drainage conditions.
- Groundwater. The county's requirement to establish maximum groundwater levels, with winter monitoring at outline, is met through a groundwater flood risk assessment.
Horsham sits in the West Sussex group of councils that share the county as LLFA; see our pages for Crawley, Mid Sussex, Arun and Adur & Worthing, or the full list of local authorities.
Horsham District flood risk and drainage: frequently asked questions
Does Horsham District Council require a flood risk assessment for planning?
Yes, where any part of the site is in Flood Zone 2 or 3, where a Flood Zone 1 site is a hectare or more, where the Environment Agency has identified critical drainage problems, where the SFRA shows increased future risk, or where another source of flooding would affect a more vulnerable use. Those triggers come from the council's validation list.
What should a flood risk assessment for a Horsham District Council application include?
Every source of flooding (river, surface water, groundwater, sewer and reservoir), climate change applied to the design flood, the site read against the climate change extents in the 2024 Level 1 SFRA, and floor levels and safe access set against them. Where any part of the site is in Flood Zone 2 or 3, or at medium or high risk from surface water or other sources, Horsham's validation list also asks for a sequential test, a separate report, unless the scheme is exempt (for example householder development).
Which council is the Lead Local Flood Authority on a Horsham District Council application?
West Sussex County Council. It is the statutory consultee on surface water for major applications. Horsham District Council remains the planning authority and also determines ordinary watercourse consents, and the Environment Agency advises on Main Rivers such as the Arun and the Adur.
What does Policy 38 of the Horsham District Planning Framework require?
Policy 38 (Flooding) takes a sequential, risk-based approach to flood risk and asks for a site-specific flood risk assessment in Flood Zones 2 and 3 and on sites over a hectare in Flood Zone 1. It is the adopted flood policy until the Horsham District Local Plan 2023-2040 is adopted, when proposed Strategic Policy 10 (Flooding), as modified by MM61, is due to replace it.
What discharge rate or drainage standard does West Sussex County Council expect?
Greenfield runoff rates, calculated without climate change or urban creep, under its August 2026 guidance on the National Standards for SuDS. The first 5 mm of everyday rainfall must be intercepted on site, infiltration is tested to BRE 365 with three tests per pit, and the 3.33% AEP plus climate change event must half-empty within 24 hours.
Is water neutrality still required for development in Horsham District?
No. Natural England withdrew its Sussex North position on 31 October 2025, and the council says water neutrality no longer needs to be considered in planning assessment. New homes are instead held to 110 litres of water per person per day, the figure in proposed Strategic Policy 9 (Water Efficiency) in the main modifications.
What will change under Horsham's emerging Local Plan?
Proposed Strategic Policy 10 (Flooding), rewritten by main modification MM61 in July 2026, will replace Policy 38. Where a scheme has the potential to increase flood risk, it requires SuDS unless technically unfeasible and bars surface water from the foul sewer. The October 2026 hearings closed on 22 October, and the Inspector's post-hearing letter of 30 October 2026 expects his report no later than January 2027.
Does a site in Flood Zone 1 in Horsham District still need an assessment?
It can. Horsham asks for an FRA on Flood Zone 1 sites of a hectare or more, on land with critical drainage problems, on land the SFRA shows at increased future risk, and where another source of flooding affects a more vulnerable use. A Surface Water Drainage Statement is needed whatever the flood zone if buildings or hard surfacing are added.
How long does a flood risk assessment or drainage strategy for a Horsham District Council application take?
It depends on the site: a Flood Zone 1 householder scheme is quicker than a Flood Zone 3 site that needs infiltration testing or winter groundwater monitoring. Every enquiry gets a fixed quote within the hour that sets out the timescale, so you know both before you commit.
Need a Surface Water Drainage Statement for Horsham?
Send the address and the drawings, and we will tell you which reports Horsham will validate against. Get a no-obligation, free quote. One of our experienced flood risk consultants will get back to you within 60 minutes. Call 01293 214444 or email enquiries@unda.co.uk.
Start a QuoteUnda Consulting Limited's chartered consultants prepare flood risk assessments, sequential tests and drainage strategies for applications to councils across England. Reports for applications to Horsham District Council come from Unda Consulting Limited, a CIWEM Business Partner. Call 01293 214444 or email enquiries@unda.co.uk for a fixed quote within the hour.