A flood risk assessment in Hampton Bishop is an assessment of a village inside its own flood banks. The parish lies on the floodplain where the River Lugg meets the River Wye at Mordiford Bridge, east of Hereford, and about six miles of earth embankments, known locally as the Stanks, run almost all the way round it. Whether the report is for a planning application, a house purchase, a mortgage or an insurer, we prepare flood risk assessments in Hampton Bishop, together with sequential and exception tests and surface water drainage strategies.

Here Hampton Bishop means the civil parish, which takes in the village along the B4224, the farmland between the two rivers, ground at the edge of the Lugg Meadows and a north-western corner on the Tupsley edge of Hereford, all in the HR1 4 postcode sector. Most of the parish's 178 homes are in the village itself, in one group south of Court Farm and another around St Andrew's Church. Herefordshire Council decides planning applications and is the lead local flood authority; the wider county is on our Herefordshire page.

In February 2020 the River Lugg overtopped the 3 km bank on its side of the village. The Environment Agency estimated that the defences still protected about 150 homes and businesses, and Herefordshire Council's investigation recorded 50 properties in the parish flooded inside, among them Hampton House residential care home.

Call 01293 214444 or email enquiries@unda.co.uk to go through a Hampton Bishop address with one of our flood risk consultants. Reports for sites in Hampton Bishop come from Unda Consulting Limited, a CIWEM Business Partner.

The Stanks: six miles of earth bank between the village and two rivers

The parish's Neighbourhood Development Plan sets out how the banks came about and how well they protect the village. The figures below come from it, from the Environment Agency and from the council:

  • The oldest bank. The first Stank is understood to have been raised for the Bishops of Hereford around 1630 to protect their farmland. The 1890 Ordnance Survey map shows it beside the Bunch of Carrots inn.
  • The Wye side. The Stank along the Wye runs from the eastern edge of Hereford to Mordiford Bridge. It was raised by 12 inches and widened after the flood of December 1960. After the Environment Agency judged it unstable following the floods of 2000, about 900 yards were rebuilt from June 2003, between a point 250 yards upstream of the Bunch of Carrots and Colcombe House.
  • The Lugg side. From Mordiford Bridge the bank follows the Lugg round towards Tupsley. The plan records that the Wye Stank is believed to be built to overtop about once in 100 years, against about once in 25 years for the Lugg embankment.
  • Little to spare. A 2006 engineering study quoted in the plan put the average height of the banks above the 1% annual probability flood at 0.48 m, falling to 0.04 m in places.
  • Repairs after 2020. The Environment Agency's £90,000 repair programme covered the overtopped Lugg bank, the Wye bank damaged by prolonged high water, and erosion at Mordiford Bridge and its flood wall.

The planning map still shows most of the parish in Flood Zone 3. That is because the Environment Agency draws its flood zones as if the defences were not there. The county's 2008 Strategic Flood Risk Assessment, quoted in the plan, singled out the defended ground at Leominster, Hereford and Hampton Bishop as carrying a relatively high residual risk. Core Strategy Policy SD3 keeps new development out of areas that would fill rapidly if a defence breached. Our guides to below-standard flood defences and why defended land stays in a flood zone explain what that means for a planning application.

When the flap valves close at Mordiford Bridge

The banks that keep the rivers out also keep rain in. The village ditches drain through culverts to Mordiford Bridge, and when the Wye and the Lugg are high the flap valves there shut, so water that falls on the village has nowhere to go. The plan records three long spells of this kind of flooding since 2000:

  1. November 2000. Rectory Road, Whitehall Road, Church Lane and the stretch from Layton's Drive to Mordiford Bridge became impassable to anything but commercial vehicles and four-by-fours.
  2. Christmas 2012 to New Year 2013. Flooding through the village lasted about ten days at worst, between Rectory Road and the entrance to Court Farm, and the Christmas Eve service at St Andrew's was cancelled.
  3. Winter 2013 to February 2014. Water stood up to 3 ft (900 mm) deep on Rectory Road and Church Lane, the Army delivered sandbags, and the B4224 was closed. Pumps were set up on Mordiford Bridge on 10 February 2014, and the roads were passable again on 19 February.

That changes the questions. Floor levels have to clear the water held behind the banks as well as the river, the access has to be tested against roads that have been shut for days at a time, and any surface water drainage has to work when the outfall is closed. A survey for the River Lugg Internal Drainage Board in 2001 identified drainage problems in the village, but no work followed for lack of money. Our guide to surface water flooding and planning covers the flow-route evidence the council asks for.

The Lugwardine and Mordiford gauges and the village's warning areas

Either river can flood the village, so the Environment Agency runs a separate warning area for each side of it. The nearest gauges, Lugwardine upstream on the Lugg and Mordiford on the Wye below the confluence, give a measure of each:

Environment Agency gauges and warning areas for Hampton Bishop
Gauge or warning areaRiverWhat it records
Lugwardine gaugeRiver Lugg, north of the parishNormal range 0.15 m to 2.40 m; property flooding possible above 3.10 m; highest level 3.00 m, on 22 July 2007
Mordiford gaugeRiver Wye, below the confluenceNormal range 0.47 m to 3.60 m; property flooding possible above 4.90 m; highest level 5.50 m, on 17 February 2020
River Wye at Hampton BishopRiver WyeFlood warning area for the village's Wye side
River Lugg at Hampton BishopRiver LuggFlood warning area for the village's Lugg side
River Wye in Herefordshire, River Lugg south of Leominster and River Frome in HerefordshireAll three riversThe wider flood alert areas for the three rivers

In February 2020 both village warning areas were at severe warning, and the Environment Agency said the Wye at Hampton Bishop reached its highest recorded level. It also said the Lugg bank was overtopped when that river reached its highest level, although its Lugwardine gauge, upstream of the village, still has July 2007 as its record. The two do not agree. Our live river levels map shows the current readings, and our page on the River Wye and its floods follows the river past the confluence.

Screening an HR1 4 postcode in the parish

The map below checks a Hampton Bishop postcode against the Environment Agency's river, surface water and reservoir data; for addresses elsewhere in England, our flood risk map does the same. The coral line is the parish boundary. The Office for National Statistics' built-up area for Hampton Bishop is only 0.22 km² and leaves out most of the village, the Stanks and the Lugg Meadows, so the parish is drawn instead. Its north-western corner takes in houses on the Tupsley edge of Hereford, which our Hereford page also covers; Mordiford, across the bridge, lies outside it.

Hampton Bishop parish, from the Lugg Meadows to Mordiford Bridge, is outlined in coral. Results are an indicative screening based on Environment Agency open data — not a Flood Risk Assessment.
Loading flood map…
Rivers & Sea
—
Surface Water
—
Reservoirs
—
Flood Zone (for planning)
—
Climate change (2070–2125)
—
Historic flooding
—
Flood warning area
—
Live flood warnings (nearby)
—
Important: This tool gives an indicative screening only, based on modelled Environment Agency datasets (Flood Map for Planning Flood Zones 2 & 3, Flood Zones plus Climate Change 2070–2125, Risk of Flooding from Rivers and Sea, Risk of Flooding from Surface Water, reservoir, historic, flood warning area, flood storage area, flood defence and main river data) under the Open Government Licence. It reflects the area around the postcode, not the exact property, and does not account for finished floor levels, ground levels or groundwater. It is not a Flood Risk Assessment and must not be relied on for planning, conveyancing, insurance or design decisions. Data © Environment Agency copyright and/or database right; contains Ordnance Survey data © Crown copyright and database right. The Hampton Bishop boundary shown is the civil parish from the Office for National Statistics (Parishes and Non-Civil Parished Areas, December 2024, parish ‘Hampton Bishop’; Open Government Licence; contains OS data © Crown copyright and database right).

Floods the parish has recorded, from 1947 to 2020

The plan lists the times the banks have failed or been overtopped; the Environment Agency and the council recorded 2020:

  1. 1947. The Stank was breached and the village flooded severely before the bank was repaired.
  2. December 1960. The Stank was overtopped and people were rescued by helicopter. The plan records it as the highest flood the village has seen.
  3. 1998 to 2002. Significant floods came in October 1998, October 2000 and February 2002. In 2000 water seeped through the base of the Stank near the Bunch of Carrots, and steel piling went in along the bank in 2002.
  4. July 2007. The Lugg bank was overtopped behind Court Farm and 26 homes in the village flooded.
  5. February 2020. Storms Ciara and Dennis brought severe warnings on both rivers. The Lugg bank was overtopped and damaged; the council's investigation recorded 50 properties flooded inside and the B4224 closed, and the Environment Agency said about 150 more were protected.

The council's Section 19 report on the 2019-20 floods also lists repairs to the Lugg Meadows banks after repeated overtopping, and a Hampton Bishop Flood Mitigation Group working with the agencies.

Policy HB1 and the other rules for building in Hampton Bishop

Herefordshire Council decides applications in the parish against its Core Strategy and the neighbourhood plan, which has flood policies of its own:

Neighbourhood plan, Core Strategy and national policy for sites in Hampton Bishop
Policy or documentWhat it asks of a site in the parish
Hampton Bishop Neighbourhood Development Plan 2011-2031, Policy HB1 Development in Areas of Flood RiskNew development in Flood Zone 1 wherever possible, with the sequential and exception tests for Zones 2 and 3; new homes in Flood Zone 3 resisted, and until better surface water drainage is in place, new homes acceptable only in Flood Zone 1
Policy HB2 Design for Flood Resilience and ResistanceAll new development built to be flood resilient and to recover quickly
Policy HB3 Design to Reduce Surface Water Run OffRain kept on site, sustainable drainage wherever possible, and buildings laid out to steer flow away from property
Policy HB6 Settlement BoundaryNew housing supported within the boundary drawn round the village, subject to its criteria
Herefordshire Local Plan Core Strategy 2011-2031, Policy SD3The sequential and exception tests, floor levels and safe access, a flood evacuation management plan where needed, compensation for lost flood storage, no new culverts, and no increase in runoff
Core Strategy Policy SD4Foul drainage that adds no phosphate to the River Wye Special Area of Conservation, which includes the Lugg below Hampton Court Bridge
NPPF chapter 18, policies F4 to F8The trigger for a site-specific assessment (F4), the sequential and exception tests (F5 and F6), and sustainable drainage to the 2025 National Standards (F8)

With so little of the parish in Flood Zone 1, new homes usually face the sequential test before anything else. The Core Strategy remains the council's adopted plan while it works on a new Local Plan for 2025 to 2045. Because the parish sits on both rivers, the council's sub-catchment map decides whether a site falls in the River Lugg catchment, where Natural England's advice since July 2019 has required new homes to show they add no phosphate; our guide to nutrient neutrality explains the method.

Planning a barn conversion or a new house behind the Stanks?

Send us the address and what you want to build. One of our experienced flood risk consultants will reply within 60 minutes with a fixed fee, free and with no obligation.

Start a Quote

Septic tanks and no public sewer

The plan records that every house in Hampton Bishop has a septic tank or similar private system. There is no public sewer. In the winter of 2013-14, with the ground saturated and the ditches full, septic tanks and biodisc units stopped working and several overflowed; some residents left the village for a time. A new home here needs a foul drainage route that keeps working when the water table is high, and that meets the council's rules on phosphate where the site drains to the Lugg.

The same ground affects surface water. The fields are low floodplain beside two rivers, the water table rose through the 2013-14 winter, and a soakaway may not drain when it is most needed. A BRE 365 infiltration test shows whether it can, and our ground conditions and soakaway map gives a first view. Owning land beside the rivers and the ditches brings duties as well as rights, as our guide to riparian ownership sets out.

The Lugg Meadows and the Hereford edge of the parish

In the north-west the parish reaches the Lugg Meadows, Lammas meadows on the eastern edge of Hereford that lie under water through much of the winter. With Hampton Meadow they form a Site of Special Scientific Interest notified in December 2011, and the Lugg Rhea, a ditch along their edge, returns water to the Lugg at Hampton Bishop. In 2024 the Herefordshire Wildlife Trust recorded the meadows still flooded on 19 March after being under water since late November. All of that water passes Hampton Bishop on its way out.

Policy HB10 guards the parish's urban fringe, where 110 homes east of Hampton Dene Road had permission when the plan was written. The plan worries that more drainage to the Lugg from new building on the edge of Hereford could worsen flooding for the village downstream, behind a bank of about 1 in 25 year protection. A site there needs a drainage strategy that keeps runoff to greenfield rates, and evidence that the outfall still works while the meadows are flooded.

From an outbuilding to a new house: the reports a Hampton Bishop proposal triggers

Most proposals in the parish meet at least one flood trigger. The usual combinations are these:

Typical proposals in Hampton Bishop and the reports they lead to
ProposalWhere in the parishUsually needed
Extension or outbuildingThe village behind the Stanks, Rectory Road, Whitehall Road, Church LaneA flood risk assessment with floor levels set above the water held behind the banks, and flood resistance under HB2
A new house or a barn converted to a homeWithin the settlement boundary or among the farmsteadsA flood risk assessment, the sequential test (and exception test where it applies), a surface water drainage strategy, and a foul drainage strategy for an off-mains site
Housing on the Hereford fringeThe north-west of the parish, near Hampton Dene Road and the Lugg MeadowsA flood risk assessment and a drainage strategy that keeps runoff to the Lugg at greenfield rates
Buying a house in the villageAnywhere behind the banksA pre-purchase flood report, which a buyer's lender or insurer may also ask to see
A care home, holiday let or other businessThe village and the B4224 corridorA flood risk assessment and a plan for warning and evacuation

A minor proposal on one of the small patches of Flood Zone 1 may need less, but the village roads and the drainage still have to be considered.

Reports for homes, farmsteads and plots between the Wye and the Lugg

Each report is matched to which bank protects the site and how the water reaches it:

  • Planning in Flood Zone 3. Almost every application in the parish needs a flood risk assessment for planning that meets Policy HB1 and the Core Strategy, with levels and access tested against an overtopped or breached bank.
  • Both rivers and the ditches. A flood risk assessment for a Hampton Bishop site considers the Wye and the Lugg together, the water trapped when the Mordiford valves shut, surface water and groundwater.
  • Buying behind the banks. A flood risk survey for property purchase looks at one house's floor level, the bank in front of it and its record in 2007 and 2020.
  • Is there a drier site? With only small patches of Flood Zone 1 in the parish, the sequential and exception test shows whether a new home could go somewhere at lower risk instead.
  • Rain that cannot leave. Our drainage strategy work deals with surface water and foul flows for sites where the outfall can be shut for days.
  • Storage behind the banks. A surface water drainage strategy follows Policy HB3, sizing storage on the plot and testing whether a soakaway will drain on the floodplain.
  • After the decision. The discharge of drainage conditions puts together the calculations and maintenance plan the council wants before building starts.
  • Off the mains. With no public sewer in Hampton Bishop and septic tanks that failed on Rectory Road and Church Lane in 2013-14, a foul drainage strategy shows how a septic tank or treatment plant will cope with a high water table.
  • Two rivers at once. Where national mapping cannot show how the Wye holds the Lugg back at the confluence, flood modelling can set the level for one site, including a bank failure.
  • Getting out in time. With two warning areas, a care home in the village and the B4224 closed in 2014 and 2020, a flood warning and evacuation plan sets out when to leave and by which route.
  • Cover after 2007 and 2020. For homes behind the Lugg bank at Court Farm and elsewhere in Hampton Bishop that flooded in either year, a flood risk assessment for insurance gives an insurer evidence about one address and the banks protecting it.

Banks, valves and drains: who to contact in Hampton Bishop

In an emergency where floodwater is a danger to anyone, dial 999, and dial 105 to report a power cut. The rest of the work is divided between these organisations:

Flood risk and emergency bodies for Hampton Bishop
OrganisationRole in the parishContact
Environment Agency (West Midlands)The Wye and Lugg banks, the Mordiford flood wall, and the two village warning areasFloodline 0345 988 1188; flood warning sign-up
Herefordshire CouncilLead local flood authority and planning authority: ordinary watercourses, surface water, groundwater, highway drainage on the B4224, and flood investigationsFlooding; flood management
River Lugg Internal Drainage BoardDrainage board for the Lugg, Arrow, Frome and Monnow catchments, which lists Hampton Bishop among its flood-prone settlementsRiver Lugg IDB
English Severn and Wye RFCCThe Regional Flood and Coastal Committee that agrees flood investment across the Wye and the Severn; Herefordshire Council is a memberCommittee page
West Mercia Local Resilience ForumMulti-agency emergency planning for Herefordshire and its neighbours, and flood preparation adviceFlooding advice
Dŵr Cymru Welsh WaterPublic sewers in the surrounding area; the village itself is off the mainsdwrcymru.com

Upstream, Hereford has its own page covering the Wye through the city and its brooks. Every other area we cover is listed in our areas.

Hampton Bishop: questions about floods, banks and planning

Is Hampton Bishop at risk of flooding?

Yes. Most of the parish lies in Flood Zone 3 on the Environment Agency's planning map, the village has flooded from the rivers in 1947, 1960, 2007 and 2020, and its roads flood from trapped rainwater when the valves at Mordiford Bridge close. The banks lower the chance of river flooding but do not remove it.

Why does Hampton Bishop flood so often?

It sits where the Lugg, fed by the Frome and the Arrow, meets the Wye at what the neighbourhood plan calls the Mordiford Bridge bottleneck. The Lugg bank has the lower standard of the two. And rain falling inside the banks cannot drain away until the rivers drop and the flap valves open.

Is a flood risk assessment needed for almost every application in Hampton Bishop?

Almost always. A site-specific assessment is needed in Flood Zones 2 and 3, which cover nearly all the parish, and Policy HB1 sends new homes to Flood Zone 1 wherever possible. On a small Zone 1 plot an assessment may still be asked for because of the trapped surface water and the flooded access roads.

Do the Stanks mean a Hampton Bishop site needs no flood risk assessment?

No. The planning map ignores the banks, and Policy SD3 asks applicants to plan for a breach. The Lugg bank overtopped in 2007 and 2020, and a 2006 study found as little as 0.04 m of spare height in places, so an assessment tests what happens when a bank is overtopped or fails.

What flood zone is Hampton Bishop in?

Nearly all of it is in Flood Zone 3, with some ground around the village in Flood Zone 2 and only a couple of small areas in Flood Zone 1, as the neighbourhood plan describes. The map above gives the zone for a postcode, and a flood risk assessment then sets the levels for the building itself.

Can a new house in the village use a septic tank?

There is no public sewer in Hampton Bishop, so a private system is usually the only option, but it has to work when the ground is waterlogged, as tanks failed in the 2013-14 winter. Where the site drains to the Lugg, the council will also want evidence that the discharge adds no phosphate.

Who looks after the flood banks and ditches at Hampton Bishop?

The Environment Agency maintains the banks along the Wye and the Lugg and repaired them after the 2020 floods. Ditches and culverts in the village are ordinary watercourses, regulated by Herefordshire Council or, inside its drainage district, the River Lugg Internal Drainage Board, and the landowner beside each one is responsible for keeping it clear.

How quickly can I get a quote for a flood risk assessment in Hampton Bishop?

One of our experienced flood risk consultants replies within 60 minutes with a fixed fee, free and with no obligation. Send the address and a short description of the house, conversion or plot, and say whether the report is for a planning application, a purchase or an insurer.

A completion date or a planning deadline for a Hampton Bishop house?

Give us the address and the date. We send a fixed-fee quote, free and without obligation, within 60 minutes.

Start a Quote

For a cottage on Rectory Road, a farmstead by the Lugg or a plot on the Hereford fringe, call 01293 214444 or email enquiries@unda.co.uk. One of the chartered consultants at Unda Consulting Limited will set out which reports the site needs; a senior consultant checks and signs each one before it goes out.

Get a no-obligation, free quote

If you need a quote or to discuss your requirements in more detail contact one of our experienced Flood Risk and Drainage Consultants.

Call +44 (0) 1293 214444, email enquiries@unda.co.uk or fill in the form below

  • This field is for validation purposes and should be left unchanged.