Flood Risk & Drainage Requirements for City of Doncaster Council
Contact Us
City of Doncaster Council judges flood risk against Doncaster Local Plan Policy 57 and drainage against Policy 56 of the Local Plan adopted on 23 September 2021. Both are read with its Flood Risk SPD of August 2023 and a Level 1 strategic flood risk assessment published in February 2026. The requirement with most bearing on a windfall site is in Policy 57 itself: in Flood Zones 2 and 3a, windfall housing and some commercial, business and industrial uses (E(c), E(g) other than offices, and B2) at Tiers 1 to 3 of the settlement hierarchy must pass a sequential test normally searched across the rest of the same settlement, and the SFRA's residual flood risk areas can then push floor levels well above the existing ground.
The council is also the Lead Local Flood Authority for the borough, so the officer who reads a major scheme's drainage strategy works for the same authority as the case officer. This page sets out Policies 56, 57 and 60, the documents behind them, the bodies the council consults and what our reports contain to meet each one. To talk through a site, call 01293 214444 or email enquiries@unda.co.uk.
Which plan a Doncaster application is judged against in November 2026
The adopted development plan is the Doncaster Local Plan 2015 to 2035, adopted after examination by Full Council on 23 September 2021. The Barnsley, Doncaster and Rotherham Joint Waste Plan and any made neighbourhood plans sit alongside it (council Local Plan page). The 2021 plan replaced both the Core Strategy and the saved policies of the Unitary Development Plan (Local Plan paragraph 1.10), so an old UDP environment policy that still turns up in search results no longer decides anything.
A replacement is under way. Cabinet agreed on 20 May 2026 to start a new Doncaster Local Plan under the 2026 plan-making regulations. The notice of intention followed on 30 June 2026 and the scoping consultation ran from 19 August to 21 September 2026; the council reports that it passed Gateway 1 on 30 October 2026 (new Doncaster Local Plan page). Its timetable puts the Plan Content and Evidence consultation at 30 April to 11 June 2027 and adoption at 30 April 2029. No draft flood or drainage policy has been published yet, so until then Policies 56 and 57 decide applications and nothing in the new plan carries weight on a current scheme.
Two supplementary planning documents adopted on 4 August 2023 sit under the policies (council SPD page). The Flood Risk SPD explains how the council applies Policy 57, including its own table of when a sequential test is not needed, and the Technical and Developer Requirements SPD sets out the drainage rules at section 7. Neither is part of the development plan, but both are material considerations that case officers and the drainage team quote back in their responses.
Which bodies rule on flooding and drainage in a Doncaster planning application
| Body | Role | What it decides or is consulted on |
|---|---|---|
| City of Doncaster Council (planning) | Local planning authority | Determines the application against Policies 56, 57 and 60 and Chapter 18 of the NPPF; the case officer judges whether the sequential test is passed (Flood Risk SPD 6.2.5) |
| City of Doncaster Council (flood risk team) | Lead Local Flood Authority | Statutory consultee on surface water for major development; consents works to ordinary watercourses outside drainage board districts, including culverting (Technical and Developer Requirements SPD 7.4.14 and 7.10.5) |
| Environment Agency | Flood risk from main rivers and the sea | Advises on development in Flood Zones 2 and 3 and beside main rivers such as the Don, Dearne, Torne, Went and Ea Beck; works on a main river need its permission |
| Yorkshire Water, Severn Trent Water and, for a very small area, Anglian Water | Sewerage undertakers | Confirm capacity for any surface water or foul connection to the public sewer; can adopt sewers and some SuDS |
| Doncaster East IDB, Danvm Drainage Commissioners and Black Drain Drainage Board | Internal drainage boards | Byelaw consent for structures near board watercourses and for any increase in flow into their districts; separate from planning permission |
| Canal & River Trust | Navigation authority | Prior approval as navigation authority where surface water would go to the Sheffield and South Yorkshire Navigation, as Policy 56 F2 expects for any watercourse outfall |
Doncaster has three drainage boards, according to the council's flooding contacts page, and they no longer share one administrator. Doncaster East Internal Drainage Board was formed in 2012 from seven older boards, Armthorpe, Finningley and Potteric Carr among them. It is now one of four boards run by the Water Management Consortium from Louth, and its byelaws were confirmed on 24 January 2025. Danvm Drainage Commissioners are administered by Yorkshire & Humber Drainage Boards. Our guide to why internal drainage boards matter for planning covers the consent process in general.
Policies 56, 57 and 60: the Doncaster flood and drainage policies in force
Three policies in the 2021 Local Plan carry the flood and drainage tests. Policy 57 deals with where development goes and how it is kept safe, Policy 56 with what happens to the water, and Policy 60 with water quality and groundwater.
| Policy | Title | What it requires | Your obligation | How Unda meets it | Source and date |
|---|---|---|---|---|---|
| Policy 57 | Flood Risk Management | Every proposal assessed against the NPPF, with the sequential test and, if needed, the exception test; windfall sites in Flood Zones 2 and 3a searched within set areas; the SFRA's development advice for residual flood risk areas to be considered | Show the flood zone and every other source; supply a sequential test over the right area of search; show the SFRA's residual-area advice has been considered; pass the exception test where Annex F requires it | A site-specific assessment covering all sources and the residual flood risk zone, plus a separate sequential test report scoped to Policy 57 C and the catchment limit in F5 | Doncaster Local Plan, p.155-157, adopted 23 September 2021 |
| Policy 56 | Drainage | A workable foul drainage route; no increase in flood risk; less runoff from brownfield sites and none extra from greenfield; no new culverting and a 10 metre buffer from watercourses; SuDS unless technically unfeasible; infiltration first | Prove the discharge route down the hierarchy, the brownfield reduction (30% looked for) or greenfield rate, and the foul solution | A surface water drainage strategy with runoff calculations, the hierarchy evidence, infiltration testing and the buffer drawn on the layout | Doncaster Local Plan, p.154-155, adopted 23 September 2021 |
| Policy 60 | Protecting and Enhancing Doncaster's Soil and Water Resources | Support for progress towards good Water Framework Directive status; no harm to rivers or flood storage areas, no deterioration of surface or ground water and no fall in groundwater levels | Show how runoff is treated before it reaches a watercourse or the ground, and that infiltration will not pollute or lower groundwater | Water quality treatment steps in the drainage strategy and a groundwater check alongside the infiltration design | Doncaster Local Plan, p.165, adopted 23 September 2021 |
Requirements checked November 2026.
Doncaster Local Plan Policy 57 (Flood Risk Management): the settlement-based sequential test
Policy 57 starts from national policy: "All development proposals will be considered against the NPPF, including application of the sequential test and, if necessary, the exception test" (Local Plan Policy 57 A). Part B leaves the extent of Flood Zone 3b to the council's strategic flood risk assessment, agreed with the Environment Agency, and Part D points applicants to the SFRA's development advice for its residual flood risk areas, which should be considered when developing in them.
Part C is the local rule. For windfall housing, some commercial uses and business, service and general industrial uses (E(c), E(g) other than offices, and B2) at Tiers 1 to 3 of the settlement hierarchy in Flood Zones 2 and 3a, the sequential test has "an area of search normally confined to elsewhere within the same settlement". Offices search the town centre in which they are proposed, retail searches the settlement's town, district or local centre, mixed-use schemes must justify being treated as one proposal or split into their parts, and "All other proposals: will normally require a borough-wide area of search unless a case can be made to narrow the search area due to certain locational needs of the development or specific catchment requirements".
The supporting text adds three points that decide many cases. Sites allocated for the use proposed are deemed to have passed, but more vulnerable uses on employment and mixed-use allocations still need a test, and Potential Development Sites generally failed it at plan stage (paragraph 14.7). Paragraph 14.8 extends the search to sites at risk from other significant sources such as surface water. It asks applicants to compare sites in the same zone by speed of onset, duration, velocity and depth, and lets sites with planning permission be discounted. It also says proposals that cannot pass the sequential test should normally be refused, without going on to the exception test.
Two things have moved since 2021. Policy F5 of the August 2026 NPPF now caps every search: "The area to which the test is applied should not be greater than the anticipated catchment of the development in terms of its likely occupiers or users." A borough-wide search for an "all other proposals" scheme is therefore the outer limit, not the starting point, and under Annex A any part of Policy 57 that would push a search beyond the catchment gets very limited weight. F5 also reaches land at risk from any source, beyond Flood Zones 2 and 3a, much as paragraph 14.8 already does.
Our sequential test starts with the catchment the use serves. It then works through the Policy 57 C area, the council's land availability and housing supply evidence and at least two online sources, as the Flood Risk SPD asks in its Table 4. Where nothing turns up, the nil return is written down. The sequential and exception test explainer covers the national method.
Doncaster Local Plan Policy 56 (Drainage): runoff, culverts and the 10 metre buffer
Policy 56 asks that schemes "achieve a reduction in surface water run off on brownfield sites, and no increase on existing rates for greenfield sites" (Local Plan Policy 56 C), and its explanation puts a number on the first half: "The Council will look for a reduction of 30% on brownfield sites, but will consider each case on its merits having regard to what is practical" (paragraph 14.5). Part D asks schemes to remove culverts, avoid building over one and leave "a 10 metre buffer zone" free from development from the water's edge. Part E requires SuDS unless shown to be technically unfeasible.
Part F sets the order for getting rid of surface water: infiltration such as soakaways wherever possible, then a watercourse "with the prior approval of the landowner and navigation authority", then a public sewer or highway drain. The explanation expects all major schemes to use SuDS and the council to see water discharged as high up that list as possible, with no harm to existing users of any sewer used. Our SuDS hierarchy guide sets out the national version of the same order.
Drainage officers look for evidence behind each step down the list: infiltration tests rather than an assumption about clay, a topographical survey proving a gravity outfall, and the water company's capacity response before a sewer is named. Our drainage strategy contains that evidence, shows the brownfield betterment as a calculated figure against the existing connected area, and draws the 10 metre strip on the layout so it is settled before the scheme is fixed. Where a culvert is involved, our note on what a culvert is explains why the policy resists them.
Doncaster Local Plan Policy 60 (Protecting and Enhancing Doncaster's Soil and Water Resources): groundwater and water quality
Policy 60 is mostly about farmland and soils, but parts E and F reach drainage. Proposals should support progress towards good status under the Water Framework Directive, and will not be supported where they would "have an adverse impact on the ecological status or recreational value of rivers and other water bodies such as flood storage areas", lead to deterioration of surface or ground waters, or "lead to a reduction in ground water levels (or reduced flows in water courses)" (Local Plan Policy 60). Part D also protects peat and other soils that help to alleviate flooding.
In practice it matters most for infiltration. The SFRA shows the greatest risk of groundwater emergence at Bentley, Adwick-le-Street and Tickhill, and the council's drainage guidance wants a treatment train before runoff reaches the soil. Our strategy states the treatment stages for each catchment and checks infiltration against groundwater level and contamination before relying on it.
Windfall site in Flood Zone 2 or 3a in Doncaster?
Send us the address and the use, and we will tell you whether Policy 57 needs a sequential test, what area it should search and which residual flood risk advice applies. Get a no-obligation, free quote. One of our experienced flood risk consultants will get back to you within 60 minutes, with a fixed quote within the hour.
Start a QuoteHow the Flood Risk SPD applies Policy 57, and where it now differs from F5
The Flood Risk SPD sets out a five-stage route: assess the risk, run the sequential test, run the exception test where needed, apply a sequential layout within the site, then prepare the site-specific assessment. Its Table 3 lists cases where the council does not expect a sequential test, and its Table 4 sets out the area of search and the evidence for each use. For a housing site of fewer than five homes or under 0.1 ha, for example, the search covers the rest of the same settlement using at least two online sources such as Rightmove or Zoopla.
Table 3 was written in 2023 against an earlier Framework. Several entries track the exemptions now in F5: allocated sites, householder development, small non-residential extensions under 250 m² and changes of use other than to a caravan, camping or chalet site or a mobile home or park home site. Some go further, among them redevelopment of existing industrial, leisure and commercial sites for similar uses where the scheme significantly improves flood resilience and makes the most of the lower-risk parts of the site, and replacement dwellings with no increase in numbers or significant increase in footprint. The SPD is guidance, not development plan policy, and F5 does not list those cases. For a scheme that relies on one of them, we prepare the evidence for an F5 test anyway and agree the position with the case officer before the application goes in.
The SPD also tightens one national exemption. A subdivision that creates ground floor or basement self-contained rooms, or involves significant alterations, still needs a test in Doncaster. And it sets the bar for Part A of the exception test: applicants fill in the Local Plan's sustainability appraisal framework, and the council expects most relevant criteria to score positive or significantly positive (SPD 7.2.4). Our exception test work completes that appraisal with evidence for each score, not a block of general benefits.
The February 2026 SFRA: Flood Zone 3b and the six residual flood risk areas
The council's Level 1 Strategic Flood Risk Assessment was prepared by JBA Consulting and issued on 6 February 2026. It replaces the 2015 study, uses the Flood Map for Planning issued in January 2026, and comes with six appendices and an interactive SFRA map. There is no Level 2 SFRA yet: Policy 57 D committed the council to one, but its flood risk and drainage page says it chose to update the Level 1 first. Our explainer on what strategic flood risk assessments are covers the two levels.
- Flood Zone 3b. The functional floodplain starts from recent EA-approved detailed models of the Don, Dearne, Ea Beck, Torne, Idle and the Humber. Where there is none, the SFRA uses the 3.3% annual probability defended outlines from the Flood Map for Planning, then the Bentley Flood Corridor, flood storage areas and an 8 metre buffer either side of main rivers (SFRA 5.2.2). Our note on Flood Zone 3b explains what the zone rules out.
- 1947 and 2007 flood area. Floor levels set above the recorded flood level and no lower than 5 m AOD, advice first given by the Environment Agency's predecessors (SFRA 6.5.5).
- Isle of Axholme. A critical flood level of 3.8 m AOD with finished floors aimed at 4.1 m AOD, subject to a site-specific assessment and agreement with the council and the Environment Agency.
- Bentley Flood Corridor. Development on previously developed land only, no increase in footprint, no effect on the corridor's operation, and contributions towards its upkeep sought.
- Bentley Ings Pumping Station. Floors above the modelled defended 1% annual probability level plus climate change, with resilience above the undefended level.
- Lower Don defences. On the tidally influenced left bank, land kept undeveloped; from Doncaster to Sykehouse, a breach analysis, nothing within the rapid inundation zone (under 20 m from a defence or as assessed) and floors 600 mm above existing ground.
Where these areas overlap, the highest floor level applies, and the SFRA says new bungalows and basements are not permitted in the zone. The Flood Risk SPD admits the consequence: where flood depths reach nearly 2 metres and existing ground is low, the land raising needed can threaten viability and leave new buildings sitting well above their neighbours. Our assessment reads the site against the residual zone layer first, because that is often what sets the building's height. Our article on residual flood risk covers why defended land is treated this way.
The SFRA also maps the sources the national maps leave thin: surface water hotspots in the Don floodplain and the low land east of Doncaster, groundwater emergence from JBA's 5 m map, and reservoir risk on the Don floodplain. Habitable basements are not to be permitted in Flood Zone 3 or in high or medium surface water risk areas, and basement dwellings in Flood Zone 2 need the exception test (SFRA 6.7.4). Its Appendix E sets out JBA's method for using these sources in a sequential test.
What Doncaster's drainage team looks for in a surface water strategy
Doncaster has no single up-to-date drainage manual. The figures come from the South Yorkshire Interim Local Guidance for Sustainable Drainage Systems (June 2015, final version 1.0), written jointly by the South Yorkshire councils, and section 7 of the Technical and Developer Requirements SPD (August 2023). The council's flood risk and drainage page also points applicants to the 2025 National Standards.
| Requirement | Doncaster position and source |
|---|---|
| Greenfield sites | Peak runoff no greater than the greenfield rate for the 1 in 1 year and 1 in 100 year events (South Yorkshire guidance 6.10 and 6.12, June 2015); Policy 56 C: no increase on existing rates |
| Brownfield sites | Policy 56 explanation: a 30% reduction looked for, case by case (Local Plan 14.5); for previously developed land out of use for more than 10 years, the South Yorkshire guidance asks for greenfield rates where possible and otherwise at least 30% betterment on the existing 1 in 1 year rate |
| Runoff volume | 1 in 100 year, 6 hour runoff volume no greater than greenfield; where that is not reasonably practicable, the designer must show the storage would make the scheme unviable or could not fit on site, and that the extra volume is discharged at a rate the LLFA accepts will not increase flood risk (South Yorkshire guidance 6.11) |
| Design events | Tested for the 1 in 1, 1 in 2, 1 in 30, 1 in 100 and 1 in 100 plus climate change events; the system accommodating the 1 in 30 year storm; the 1 in 100 plus climate change stored on site without risk to people or property (South Yorkshire guidance 6.10 to 6.12) |
| Climate change | The 2015 guidance uses 30% on peak rainfall; the current Environment Agency allowances for the Don and Rother and Idle and Torne catchments are 35% (3.3% event) and 40% (1% event) at the upper end for the 2070s, the levels the SFRA says the Environment Agency expects assessments to test |
| Urban creep | An extra 10% impermeable area on housing; if left out the LLFA may ask for permitted development rights to be removed (Technical and Developer Requirements SPD 7.4.27) |
| Infiltration | BRE Digest 365 tests at the location and depth of the feature; rates below 1 x 10-6 m/s ruled out; base at least 1 m above peak groundwater; half drain within 24 hours after the 1 in 30 plus climate change event; factor of safety at least 2; more than 5 m from buildings, other soakaways and highway (Technical and Developer Requirements SPD 7.4.6 to 7.4.8) |
| Storage location | No attenuation below adoptable highway or site parking areas (Technical and Developer Requirements SPD 7.8.3) |
| Watercourses | A 10 m easement to any watercourse in the layout unless access and bank stability can be shown with less (Technical and Developer Requirements SPD 7.9.9) |
| Sewer connections | The sewerage undertaker's confirmation of capacity at planning; a developer enquiry at outline and a signed Section 104 agreement at conditions stage (Technical and Developer Requirements SPD 7.4.19) |
| Maintenance | A lifetime management and maintenance plan with funding, access and responsibilities; the council prefers adoption by a statutory undertaker (Technical and Developer Requirements SPD 7.7 and 7.9) |
The SPD's Table 2 lists the documents expected at each stage, from a flood risk assessment and drainage strategy at the start to detailed drawings, ground investigation with infiltration results, discharge agreements and a construction phase plan later on. The LLFA may recommend refusal where the information is not enough to show the site can drain without raising flood risk (SPD 7.3.2). Our drainage calculators, including the climate change and urban creep calculator and the BRE 365 infiltration rate calculator, show how those figures are reached, and the ground conditions and soakaway map gives a first read on the soils.
Policy F8 of Chapter 18 now expects SuDS to be designed to the National Standards for Sustainable Drainage Systems, published in June 2025. The council's own drainage figures predate them, and no council statement adopting or adapting them was found on its planning, flooding or validation pages; the validation list does ask for a plan showing the SuDS "in compliance with national standards". Our strategy is written to the National Standards and to the Doncaster figures together, and says where they differ. The 2025 National Standards guide sets out the seven standards.
Inside a drainage board district the board's rules come on top. Doncaster East IDB's surface water advice note AN06 recognises an agricultural runoff rate of 1.4 litres per second per hectare, with 3.0 l/s as the practical minimum controlled rate. Anything higher costs more in surface water development charges, and the board does not promise to accept it. Its byelaws require consent for any building, structure or planting within nine metres of a board-maintained watercourse and for any increase in flow, and the consortium's planning and consenting page holds the forms. Works on other ordinary watercourses need ordinary watercourse consent from the council.
Triggers for an assessment, the tests, a drainage strategy and board consent in Doncaster
| Requirement | Trigger in Doncaster | Source |
|---|---|---|
| Site-specific flood risk assessment | All development in Flood Zones 2, 3a and 3b; in Flood Zone 1, sites of 1 ha or more, land with critical drainage problems, and land shown in the SFRA or the Flood Map for Planning at risk from any source now or in future, householder schemes included | NPPF F4; validation list, 1 October 2025 |
| Sequential test | Development in areas at risk from any source, unless allocated for that use and tested at plan stage, or a householder scheme, a non-residential extension under 250 m² or a change of use (not to caravans, camping, chalets, mobile or park homes); also not needed where a site-specific assessment clearly shows that no built development, access or escape route, land raising or other potentially vulnerable element would sit on land at risk from any source now or in the future, or, where the only risk is surface water, that occupiers and users stay safe for the lifetime of the development without increasing flood risk elsewhere | NPPF F5; Local Plan Policy 57 C, 23 September 2021 |
| Exception test | After the sequential test, where Annex F table 3 requires it in Flood Zones 2, 3a or 3b, such as more vulnerable uses in Flood Zone 3a; never in Flood Zone 1; not needed where no sequential test is required | NPPF F6; Flood Risk SPD section 7, August 2023 |
| Drainage assessment and SuDS strategy | All major development, outline included (10 or more homes, housing sites of 0.5 ha or more where numbers are unknown, 1,000 m² of floorspace or a site of 1 ha); smaller schemes still meet Policy 56 | Validation list, 1 October 2025; Local Plan Policy 56 |
| Foul drainage details | Any scheme with new or altered non-mains drainage (package plant, septic tank, cesspool) | Validation list; Technical and Developer Requirements SPD 7.5 |
| Residual flood risk measures | Any site inside one of the SFRA's six residual flood risk areas, where Policy 57 D says the SFRA's development advice should be considered | Local Plan Policy 57 D; SFRA 6.5.5, February 2026 |
| Emergency or evacuation plan | Wherever emergency response is part of keeping the site safe; essential for holiday caravans, camping and transient uses such as hostels and hotels | Flood Risk SPD 9.1.5, August 2023 |
| IDB consent | Any structure within nine metres of a board watercourse, or any increase in flow into a board district | Doncaster East IDB byelaws, confirmed 24 January 2025 |
The council describes major development more briefly than the law does: 10 or more homes, or 0.5 ha for commercial schemes, in the Local Plan, and 10 dwellings or 0.5 ha in the Technical SPD. The statutory definition in the Development Management Procedure Order also covers 1,000 m² of new floorspace and any site of 1 ha or more. The LLFA's statutory consultation follows the statutory definition. Our note on flood risk vulnerability classification explains how the use decides the exception test.
Doncaster's October 2025 validation lists on flood risk and drainage
The council's Local Validation Requirements and Householder Local Validation Requirements are both dated 1 October 2025, so they are inside the two-year window the council itself quotes for a local list. The main list asks for a "Flood Risk Assessment & Sequential & Exceptions Tests (where applicable)" for all proposals, minor development and changes of use included, in Flood Zones 2, 3 or 3b, on Flood Zone 1 sites of 1 ha or more, in areas with critical drainage problems, in Flood Zone 1 where the SFRA shows increased future risk, and where a change raises the vulnerability of a site exposed to other sources.
Major schemes also need a Drainage Assessment and a SuDS Strategy. The first covers site surveys, infiltration results, the outline system, SuDS locations, a maintenance plan, easements, calculations including greenfield rates, evidence of agreement to cross third party land where that is needed to drain the site and, where it discharges to the sewer network, at least a pre-planning enquiry to the water company. The second answers nine set questions, from the existing drainage to adoption. The householder list asks for an assessment only in Flood Zone 2 or 3 or in Flood Zone 1 with critical drainage problems. That is narrower than F4, which also reaches Flood Zone 1 land at risk from other sources, so we check a householder site against the SFRA's surface water and groundwater layers before saying none is needed.
The council gives an applicant eight weeks to supply what is missing from an invalid application before it disposes of the papers and returns the fee (council planning application page). Our article on applications invalidated over flood risk and drainage lists the usual gaps.
Chapter 18 of the NPPF alongside Doncaster's 2021 policies
The August 2026 Framework moved flood risk into Chapter 18: F4 sets when an assessment is needed, F5 and F6 the sequential and exception tests, F7 the safety tests and F8 sustainable drainage to the National Standards. Policies 56 and 57 were adopted in 2021, and Annex A says plan policies should not lose weight simply because they predate the Framework; only the parts materially inconsistent with its decision-making policies get very limited weight. Local content that is not inconsistent with the Framework, such as the 10 metre watercourse buffer in Policy 56 and Policy 57 D's requirement to consider the SFRA's residual-area advice, keeps its weight.
The Planning Practice Guidance on flood risk and coastal change, last revised on 17 September 2025, explains how to run these tests in practice. Our summary of the August 2026 NPPF flood risk and drainage changes sets out what moved.
The Don, the Torne and the drains behind Doncaster's flood record
Most of Doncaster's fluvial risk comes from the River Don and its tributaries, with more from the Torne and the drains east of the town and tidal risk from the Humber (SFRA 5.1). The borough is largely flat and partly below sea level, so it relies on pumps and engineered channels, and it splits between the Don and Trent catchments (council flood risk management page).
Two events shape the current evidence. In June 2007 surface water flooding reached 3,286 households in 48 parts of the borough. In November 2019 the Don, smaller watercourses such as Kearsley Brook at Conisbrough and Paper Mill Dyke at Tickhill, and local surface water between them affected 773 properties (SFRA 5.10). The council's Local Flood Risk Management Strategy 2023 to 2029 sets out its response. Our page on flood risk assessment in Doncaster covers the town's history in more detail, the flood risk map shows the national flood zones for any address, and the live river levels map tracks the Don gauges.
Reports we prepare for applications to City of Doncaster Council
Assessments for Doncaster schemes come from chartered consultants at Unda Consulting Limited, a CIWEM Business Partner, and each answers the policies above directly. A flood risk assessment, a sequential or exception test and a drainage strategy deal with different questions, so each is its own report, scoped to Policy 57 or Policy 56 as the site needs.
- Assessment against Policy 57. Any site in Flood Zone 2 or 3, over a hectare, in a residual flood risk area or at risk from surface water or groundwater needs a flood risk assessment that works through the SFRA's floor-level advice.
- The planning submission. A flood risk assessment for planning written to the validation list of 1 October 2025, so the case officer can register the application without a request for more.
- Buying land or a home. A flood risk survey for property purchase reads the 2026 SFRA layers and the residual zones before exchange.
- Settlement-wide search. A sequential and exception test built on the Policy 57 C area, the catchment limit in F5 and the SPD's Table 4 evidence.
- Runoff under Policy 56. A drainage strategy that follows the infiltration-first order and shows the 10 metre buffer.
- Major schemes. A surface water drainage strategy answering the validation list's nine SuDS questions with the 30% brownfield reduction or greenfield rate calculated.
- After permission. Discharge of drainage conditions for the detailed drawings, Section 104 evidence and maintenance plan the conditions ask for.
- National policy. Our NPPF guidance and advice covers how F5's catchment limit and Annex A sit against Policy 57's areas of search.
- Groundwater. The SFRA puts the highest emergence risk at Bentley, Adwick-le-Street and Tickhill, where a groundwater assessment decides whether infiltration or basements are realistic.
- Breach and defended reaches. Behind the Lower Don defences the SFRA asks for a breach analysis; flood modelling supplies the levels and the rapid inundation zone.
- Emergency planning. The Flood Risk SPD makes an emergency plan essential for caravans, camping, hostels and hotels at risk, which a flood warning and evacuation plan provides.
- Recorded flooding. With 773 properties affected in November 2019, an insurance flood risk assessment sets out the actual risk to a building for underwriters.
The council's Local Plan page and flood risk and drainage page are the primary sources for everything above. Requirements for neighbouring councils are set out from our local authorities hub. To discuss a Doncaster site, call 01293 214444 or email enquiries@unda.co.uk.
Questions on Doncaster's flood and drainage policies
Does Doncaster Local Plan Policy 57 mean a sequential test for every site in Flood Zone 2?
Not every site. Policy 57 applies the NPPF sequential test, and for windfall housing and some commercial, business and industrial uses (E(c), E(g) other than offices, and B2) at Tiers 1 to 3 of the settlement hierarchy in Flood Zones 2 and 3a it normally confines the search to the same settlement. F5 of the August 2026 NPPF exempts householder schemes, non-residential extensions under 250 m², most changes of use and sites allocated in the development plan that were sequentially tested when the plan was prepared. It also exempts sites where an assessment shows no built development, access, land raising or other vulnerable element on land at risk now or in future, or a surface water risk only with occupiers kept safe for the lifetime of the development without increasing flood risk elsewhere. The search can never be wider than the development's catchment.
Who reviews the drainage on a major Doncaster application, and against what?
City of Doncaster Council's flood risk team, acting as Lead Local Flood Authority, comments on surface water for major development. It works from Policy 56, the South Yorkshire Interim Local Guidance for SuDS (June 2015) and section 7 of the Technical and Developer Requirements SPD (August 2023), and it can recommend refusal where the information does not show the site can drain safely.
Does an extension in Flood Zone 2 in Doncaster need a flood risk assessment?
It does. The householder validation list of 1 October 2025 asks for one in Flood Zone 2 or 3, and NPPF F4 also covers Flood Zone 1 land at risk from other sources. A householder extension is exempt from the sequential and exception tests but still needs the assessment, which can usually follow the Environment Agency's standing advice on floor levels.
What floor level does the council expect in the 1947 and 2007 flood area?
The February 2026 SFRA keeps the Environment Agency's advice that floors sit above the recorded flood level and no lower than 5 m AOD. Where that area overlaps another residual flood risk area, the highest of the floor levels applies, and new bungalows and basements are not permitted in the residual zone.
Can surface water go into a Doncaster East IDB drain?
Only with the board's consent. Its byelaws, confirmed on 24 January 2025, require consent for any increase in flow and for structures within nine metres of a board-maintained watercourse. The Water Management Consortium's advice note AN06 recognises an agricultural rate of 1.4 litres per second per hectare, with 3.0 l/s as the practical minimum, and charges more for higher rates.
Is there a Level 2 SFRA for Doncaster?
No. Policy 57 D committed the council to one, but it chose to replace the 2015 Level 1 first, and the February 2026 Level 1 by JBA Consulting is the current evidence. Sites that need more detail than the Level 1 gives, such as those behind the Lower Don defences, need their own modelling or breach analysis in the site-specific assessment.
Doncaster submission going in with the drainage still open?
We write the assessment and drainage strategy to Policies 56 and 57, the February 2026 SFRA and the October 2025 validation list together, so the case officer has what the validation list asks for from day one. Get a no-obligation, free quote. One of our experienced flood risk consultants will get back to you within 60 minutes, with a fixed quote within the hour.