Flood Risk & Drainage Requirements for the London Borough of Richmond upon Thames

Contact Us
A line drawing of the UK map with three points linked to icons: a factory, a house, and a river. A warning symbol and a person in a hard hat holding a clipboard appear on the right side.

The London Borough of Richmond upon Thames decides flood risk and drainage on Policy 8 (Flood Risk and Sustainable Drainage) of the Richmond upon Thames Local Plan 2024 to 2039, adopted on 7 October 2025, read with the London Plan 2021. Policy 8 puts land in the 1 in 100 year surface water extent in the same row of its table as Flood Zone 3a, so a Flood Zone 1 site can still need a flood risk assessment and lose its basement bedroom. Drainage has a new middle step too: greenfield runoff first, then 2 l/s or below, and only then a 50% cut in the existing peak.

Richmond upon Thames is a London borough, so one council is both the local planning authority and the Lead Local Flood Authority. It is also the only London borough with land on both banks of the Thames, tidal below Teddington Lock and a non-tidal river above it, and Policy 8 treats the two reaches differently. These are the flood risk requirements Richmond upon Thames applies to a planning application today. They cover the policies by number, the Strategic Flood Risk Assessment behind them, and the validation checklist that took effect on 20 February 2026.

We prepare flood risk assessments, sequential and exception tests and drainage strategies for applications to Richmond Council, and each section below says how our reports answer the requirement it describes. Reports for Richmond upon Thames applications come from Unda Consulting Limited, a CIWEM Business Partner, and our consultants are chartered.

Who decides what on a Richmond upon Thames application

London has no county tier and the borough has no internal drainage board. Three public bodies and the sewerage company shape a decision here, and two of the roles belong to the same council.

BodyRoleWhat it decides or is consulted on
London Borough of Richmond upon ThamesLocal planning authorityDecides the application against Policies 8, 9, 40 and 54, the London Plan and Chapter 18 of the NPPF; validates it against the February 2026 Local Validation Checklist; judges whether the Sequential Test is met (Local Plan para 16.62); confirms whether a site is in a breach hazard area (para 16.89)
London Borough of Richmond upon ThamesLead Local Flood AuthorityConsulted on sustainable drainage for every major application, as it has been since 15 April 2015; consents works affecting ordinary watercourses under the Land Drainage Act 1991; holds the Surface Water Management Plan (December 2021) and the Local Flood Risk Management Strategy (version 3.0, August 2023)
Environment AgencyStatutory consulteeRiver and tidal flood risk on the Thames, Crane, Beverley Brook, Duke of Northumberland's River, Whitton Brook and Portlane Brook; development that could affect flood defences, as a guide within 20 m of a main river bank (para 16.84); any departure from the 16 m and 8 m set-backs must be agreed with it (Policy 8 part I)
Thames WaterWater and sewerage companyWritten confirmation of capacity before surface water goes to a public sewer (para 16.77); early engagement on water supply, foul drainage and treatment capacity for major schemes (Policy 9 part D)
Mayor of LondonStrategic planning authorityLondon Plan Policies SI 12 and SI 13; applications referable to the Mayor

Because the planning officer and the drainage reviewer sit in the same authority, a major scheme's drainage strategy is read by the body that will also write the decision notice. The Environment Agency's sign-off on river or tidal levels does not cover that half. Our explainers on the Lead Local Flood Authority and on how planning authorities handle flood risk and SuDS set out the two roles.

Policy 8 and the other flood and water policies Richmond upon Thames applies

Applications are read against the Richmond upon Thames Local Plan 2024 to 2039, which the council adopted with its Policies Map on 7 October 2025, and the London Plan 2021. The council notes that the plan was examined under transitional arrangements against the earlier Framework of 2023, which matters when it is read beside today's national policy. In Ham and Petersham a neighbourhood plan adds one drainage policy of its own.

PolicyTitleWhat it requiresYour obligationHow Unda meets itSource and date
Policy 8Flood Risk and Sustainable Drainage (Strategic Policy)All sources assessed with climate change; Sequential and Exception Tests; land use limits by zone, with the 1 in 100 year surface water extent treated with Flood Zone 3a; Flood Emergency Plan on larger or cut-off sites; SuDS on every scheme to greenfield, 2 l/s or 50%; 16 m and 8 m set-backs; basement limits by zone and breach hazardEvidence on every source, the test position, floor levels, a drainage statement and, for basements, the zone and hazard bandA flood risk assessment that states which row of Table 16.4 the site is in, with a drainage strategy that tests greenfield firstRichmond upon Thames Local Plan 2024 to 2039, adopted 7 October 2025
Policy 9Water Resources and Infrastructure (Strategic Policy)Water quality protected; no misconnections between foul and surface water; major schemes show early engagement with the sewerage and water supply provider; capacity in place before occupationProof that Thames Water can serve the schemeCapacity correspondence and the foul and surface water arrangements set out in the drainage strategyRichmond upon Thames Local Plan 2024 to 2039, adopted 7 October 2025
Policy 40Rivers and River CorridorsRiver corridor development contributes to habitats, access, flood defences and flood storage; development set back from river banks and flood defences along the ThamesA layout that keeps clear of the bank and adds to the corridorThe set-back measured on the site plan and floodplain storage accounted forRichmond upon Thames Local Plan 2024 to 2039, adopted 7 October 2025
Policy 54Basements and Subterranean DevelopmentsOne storey only under homes; no more than 50% of the garden; 1 m of soil and a 200 mm drainage layer above; Screening Assessment by a chartered professional in the throughflow and groundwater policy zones or where groundwater susceptibility is 25% or more; pumped device where there is a waste outletA basement that passes Policy 8's zone rules and carries the screening evidenceFlood zone, breach hazard and groundwater checked at the basement footprintRichmond upon Thames Local Plan 2024 to 2039, adopted 7 October 2025
Ham and Petersham Neighbourhood Plan Policy E4Sustainable Drainage (SuDS)Every new building in the neighbourhood area includes a sustainable drainage system, integrated into the landscape, with a maintenance programmeSuDS and a maintenance plan on any new building in Ham or PetershamA drainage strategy that says who maintains each featureHam and Petersham Neighbourhood Plan 2018 to 2033, adopted 22 January 2019
London Plan Policy SI 12Flood risk managementResidual risk dealt with as well as mapped risk; room left for water and buildings kept back from watercourse banks where possible; a contribution to the Thames Estuary 2100 PlanWhat happens on the site if a Thames defence failsBreach depth and hazard read from the SFRA web map at the siteThe London Plan, published March 2021
London Plan Policy SI 13Sustainable drainageGreenfield runoff as the aim; rainwater managed near where it falls; planted features preferred to tanks; a hierarchy of six discharge routes; hard paving resisted unless unavoidableA reason for every hierarchy step passed overEach of the six routes tested in turn in the drainage strategyThe London Plan, published March 2021
Draft London Plan Policy GHR5Flood risk and drainage (draft; statutory consultation closed 15 October 2026)Runoff not to rise on any scheme; schemes referable to the Mayor to aim for the greenfield Qbar rate or 3 l/s/ha if that is higherA draft, so limited weight in a Richmond decision for nowThe draft rate reported beside the Policy 8 rate on referable schemesDraft London Plan (July 2026; web version updated 11 September 2026), statutory consultation 16 July to 15 October 2026

Requirements checked November 2026.

Policy 8 (Flood Risk and Sustainable Drainage): the strategic policy every scheme meets

Policy 8 asks every development in Richmond upon Thames to be safe for its lifetime and to show it avoids or reduces flooding from all sources without raising risk elsewhere. Part A reads: "All developments will need to be made safe for their lifetime and clearly demonstrate that they avoid, or reduce contributing to all sources of flooding, including fluvial, tidal, surface water, groundwater and flooding from sewers" (Local Plan, pages 205 to 217). It runs to twelve lettered parts and two tables, and it is a Strategic Policy.

The plan replaced the 2018 Local Plan and the 2013 Twickenham Area Action Plan in full (paragraph 2.8), so Policy LP 21 (Flood Risk and Sustainable Drainage) of the 2018 plan was replaced by Policy 8 in October 2025. Three other 2018 codes that people still search were superseded with it: LP 23 on water resources, LP 11 on basements and LP 18 on river corridors, whose subjects now sit in Policies 9, 54 and 40.

Part C asks for a Flood Emergency Plan on "sites of 10 dwellings or more, or 1000sqm of non-residential development or more, in Flood Zones 2 and 3, or in areas at Risk of Flooding from Surface Water in a 1 in 100 year event or greater, or within a Surface Water Management Plan hotspot, or on any other proposal where safe access/egress cannot be achieved". Part L sets the climate change basis: the appropriate allowances for surface water and river flooding, and for tidal sites the current Thames Estuary 2100 crest levels and breach modelling "to account for worst-case scenarios". How we meet it: our assessment covers each source in turn, states the allowance used and where it came from, and says at the start whether an emergency plan is triggered.

Policy 8 (Flood Risk and Sustainable Drainage) Table 16.4: what each flood zone allows

Table 16.4 sets land use limits, the tests and the assessment needed for each zone. Richmond departs from the national table in the second row, headed "Zone 3a and areas at Risk of Flooding from Surface Water in a 1 in 100 year event".

  • Flood Zone 3b. No development on undeveloped land unless it is water compatible or essential utility infrastructure. Redevelopment only with no extra building in the undeveloped functional floodplain, no increase in vulnerability and a net reduction in flood risk; no change of use to a more vulnerable class.
  • Flood Zone 3a and the 1 in 100 year surface water extent. Highly vulnerable development is not permitted, and neither are self-contained residential basements or bedrooms at basement level. A flood risk assessment is required for all development proposals; the Sequential Test applies unless a local exemption does, and the Exception Test applies to more vulnerable uses such as housing.
  • Flood Zone 2. No land use limits, but the same ban on self-contained basements and basement bedrooms. An assessment for every proposal except a change of use from water compatible to less vulnerable; Exception Test for highly vulnerable uses.
  • Flood Zone 1. No restrictions. A Drainage Statement for all major developments, and a flood risk assessment for any other proposal "where there is evidence of a risk from other sources of flooding, including surface water, ground water and sewer flooding".

Two paragraphs of supporting text alter layouts. On the Thames, the functional floodplain is "land riverward of the Thames Tidal Flood Defences", and an island whose way on and off starts in the functional floodplain is treated as Flood Zone 3b for new development even where parts of it are higher (paragraph 16.66). Floor levels are fixed by paragraph 16.69: for river flooding, a minimum of 300 mm above the 1 in 100 year level with climate change; for defended tidal flooding, "all sleeping accommodation must be located on finished floor levels above the Thames Tidal Breach 2100 flood level".

One caution. Table 16.5, which governs basements, lists no restrictions in Flood Zone 1, while Table 16.4 bans basement bedrooms in the surface water extent whatever the river zone. On a Flood Zone 1 site inside that extent we set out both tables in the assessment and ask the council which it applies before the layout is fixed. The Unda flood risk map shows the national zones and surface water extents for any address.

Policy 8 (Flood Risk and Sustainable Drainage) and the local Sequential Test for town and local centres

The Local Plan sets out Richmond's own Sequential Test approach, developed in liaison with the Environment Agency, which on its face removes the test from much of the built-up borough. It has to be read with national Policy F5, as the Chapter 18 section below explains. Paragraph 16.59 says the test "will not be required" where the proposal is within a town centre or local centre boundary, or is residential or mixed-use and within the 800 m buffer drawn around each centre. Paragraph 16.60 adds three more cases: a Local Plan site allocation that has already been sequentially tested and is used as allocated, the redevelopment of an existing single residential property, and a conversion or change of use. Paragraph 16.61 closes the list: "The Sequential Test will be required in all other cases."

The council explains the reason in paragraph 16.58. Some centres sit in Flood Zones 2 and 3, moving development away from them "is not always a realistic option", and 800 m was chosen as a walking distance that sustains a community. The SFRA's policy web map shows the centres and their buffers, and the council's SFRA page says the 2025 plan's new centre boundaries have been carried into them. The exemption stops at the Sequential Test. Table 16.4 still asks for the Exception Test for housing in Flood Zone 3a, and paragraph 16.62 says the council will refuse a scheme that fails the Sequential Test "even where the Exception Test has been passed".

How we meet it: we check the site against Policy F5's exemptions first and the centre boundaries and buffers second, and prepare the test wherever F5 does not exempt the scheme. Our guides to the sequential and exception tests and the surface water exemption cover the national rules.

Policy 8 (Flood Risk and Sustainable Drainage) part H: greenfield runoff, 2 l/s and the 50% fallback

Part H requires SuDS "in all development proposals" and sets a three-step runoff test. First, "A reduction in surface water discharge to greenfield run-off rates wherever feasible". Second, where the applicant shows greenfield is not feasible, "the minimum requirement is to achieve at least a runoff rate of 2 l/s or below". Third, where that is not possible and is justified, the applicant details how "at least 50% attenuation of the site's surface water runoff at peak times based on the levels existing prior to the development" will be achieved.

The 2 l/s step is new in the 2025 plan. The council's own SuDS page still gives the older two-step wording, greenfield or 50%, so a strategy written from the web page alone skips a test the adopted policy sets. How we meet it: our drainage strategy calculates the greenfield rate, shows the storage needed to reach it, and only then argues for 2 l/s or the 50% fallback, with the reason for each step down.

Policy 8 (Flood Risk and Sustainable Drainage) parts I and J: the 16 m and 8 m set-backs and the Thames defences

Parts I and J protect the defences and the space behind them. Unless exceptional circumstances are shown, development is set back "a minimum of 16 metres from the landward side of any tidal flood defences and 8 metres for other main rivers including culverted main rivers", and a shortfall needs evidence at application stage that the Environment Agency agrees. Schemes must take account of the Thames Estuary 2100 Plan and the River Thames Scheme. No new active flood defences (those that have to be closed or put up when a flood is coming) may be delivered, and existing ones are replaced with permanent defences when a site is redeveloped.

Part J adds that developments adjoining the Thames must maintain and, where necessary, raise the defences to the statutory level in the Thames Estuary 2100 Plan, or show how they could be raised later. Paragraph 16.83 notes that most formal defences in the borough are privately owned, so on a riverside plot the wall is usually the applicant's to maintain. Works within those 8 m or 16 m strips can also need a flood risk activity permit from the Environment Agency (paragraph 16.85), which applicants arrange with the Agency directly. How we meet it: we measure the set-back on the site plan, record the defence line and its condition, and say what the scheme leaves room for.

Policy 54 (Basements and Subterranean Developments) and Policy 8's basement table

No part of Policy 8 is stricter than its basement table, and Policy 54 adds limits of its own. Policy 54 limits a basement under a home to one storey and half the garden, asks for a metre of naturally draining soil and a 200 mm drainage layer above any part under the garden, and requires "a suitable (positively) pumped device" wherever there is a waste outlet. Policy 8's Table 16.5 then rules by flood zone and by the SFRA's breach hazard band. Planning permission is needed in every case: two Article 4 Directions removed permitted development rights for basements across the whole borough from 1 April 2018.

  • Flood Zone 3b. No basements, basement extensions, conversions to a more vulnerable use or self-contained units.
  • Flood Zone 3a, extreme, significant or moderate breach hazard. New basements for less vulnerable or water compatible uses only. A more vulnerable use is considered only where a site-specific assessment shows the risk to life can be managed; no basement bedrooms and nothing self-contained.
  • Flood Zone 3a with low or no breach hazard, and Flood Zone 2 in the higher hazard bands. Residential basements may be permitted if they are not self-contained or used for bedrooms and, where it applies, the Exception Test is passed. They need internal access to a higher floor and flood resistant and resilient construction.
  • Throughflow and groundwater policy zones. In Richmond Hill, Strawberry Hill, Marble Hill and St Margarets West a basement stays within the curtilage, takes no more than 50% of each garden or open area, and needs a Screening Assessment.
  • Near the defences. New basements are structurally independent of the flood defences or outside their zone of structural influence, whichever distance is greater.

Policy 54 extends the Screening Assessment beyond the four zones to any site "in an area with >=25% susceptibility to groundwater flooding", and the council's Basement Assessment User Guide sets the questions. If screening finds a possible impact, or cannot rule one out, a Basement Impact Assessment by a chartered professional follows. Paragraph 16.93 asks that assessment for borehole information with "at least two data recordings" taken "within a period of at least 12 months", which is why groundwater monitoring is best started long before the application. The assessments should be completed before any permission is granted (paragraph 16.94). Because the mapping is updated, the applicant is also expected to confirm with the council whether the site is in a breach hazard area (paragraph 16.89).

How we meet it: we read the flood zone, breach hazard band and groundwater susceptibility from the SFRA web maps at the basement footprint, and state whether the use proposed is one Table 16.5 allows. The structural and land stability parts of a Basement Impact Assessment sit with the scheme's structural engineer; the flood, groundwater and drainage parts are ours. Our article on basement and cellar conversions in a flood zone covers the national classification.

Policy 9 (Water Resources and Infrastructure): sewer capacity and water quality

Policy 9 asks major schemes to prove the network can take them. Part D requires major residential and non-residential development to show "early engagement by the applicant with the sewerage and water supply network provider", and paragraph 16.101 expects written confirmation that capacity exists. Part C asks every proposal to protect river and groundwater quality and to "take action to minimise the potential for misconnections between foul and surface water networks". Where capacity is short, paragraph 16.102 asks for a drainage strategy showing the infrastructure needed and how it will be funded. We include the Thames Water correspondence and the separate foul and surface water routes in the drainage strategy.

Policy 40 (Rivers and River Corridors): the bank-side strip

Policy 40 expects development beside a river to give something back to the corridor: public access, habitat, and "improvements of flood defences and flood storage". Part F repeats, for the Thames, the requirement to set development back from river banks and existing flood defences. On a Thames, Crane or Beverley Brook site we show the strip on the plans beside the Policy 8 set-back, so the ecology and flood defence cases use the same line.

Ham and Petersham Neighbourhood Plan Policy E4 (Sustainable Drainage (SuDS))

In the Ham and Petersham neighbourhood area one extra policy applies, and it has no size threshold: "All new buildings will be expected to include a sustainable drainage system to dispose of surface water. All sustainable drainage systems must be integrated into the landscape and have a maintenance programme" (Ham and Petersham Neighbourhood Plan 2018 to 2033, adopted by the council on 22 January 2019). The 2025 Local Plan left the neighbourhood plan in force, and the February 2026 validation checklist lists Policy E4 beside Policy 8 under its drainage item. The plan's reason is local: the surface water sewers in Ham have a flat gradient and fill quickly in a summer storm. For a new building there we say who maintains each feature and how often.

London Plan Policy SI 12 (Flood risk management): what a breach would do below Teddington

Part C of Policy SI 12 in the London Plan reads: "Development proposals should ensure that flood risk is minimised and mitigated, and that residual risk is addressed." It goes on to ask for space for water and, where possible, a set-back from watercourse banks. Downstream of Teddington the Thames defences keep the tide out, so the question SI 12 poses in Mortlake, Kew or Twickenham is what a breach would do. So we report the breach depth and hazard at the site from the SFRA map, not the zone alone, and our note on residual flood risk gives the background.

London Plan Policy SI 13 (Sustainable drainage): the hierarchy Policy 8 follows

Policy SI 13 part B says proposals "should aim to achieve greenfield run-off rates and ensure that surface water run-off is managed as close to its source as possible". Part C resists new impermeable surfacing "unless they can be shown to be unavoidable, including on small surfaces such as front gardens and driveways", which catches a paved-over front garden in Teddington as much as a large scheme. Richmond's Policy 8 part H is the local and firmer version, with the 2 l/s and 50% steps written in. Paragraph 16.76 of the Local Plan repeats SI 13's six discharge routes in the same order, with the combined sewer last.

The next Local Plan and the draft London Plan's proposed Policies GHR5 and GHR9

Richmond upon Thames has not started its next Local Plan. The council's page on shaping the next Local Plan (updated 24 July 2026) says it is considering how to prepare a plan under the plan-making system that took effect on 25 March 2026. Its Local Development Scheme page (updated 17 July 2026) says work on the formal stages of a new Local Plan is expected to start in 2027, with a timetable to follow later in 2026. No notice of plan-making had been published when we checked in November 2026, so Policy 8 applies as adopted.

The change closer to hand is the Mayor's. Under Mayoral Decision MD3515, signed on 9 July 2026, the draft London Plan went out to 13 weeks of statutory consultation from 16 July, closing on 15 October 2026, and Richmond's own page says the council was preparing a response. In that consultation draft, proposed Policy GHR5 (Flood risk and drainage) says development "should not increase surface-water runoff", and for schemes referable to the Mayor sets an aim of greenfield rates "as measured in Qbar (mean average flood flow) or 3l/s/Ha (whichever is higher)". Draft Policy GHR9 (Clean and healthy waterways) asks Local Plans to reflect ten Riverside Strategy principles for the Thames. Adoption of the draft would replace the whole 2021 Plan, and SI 12 and SI 13 with it. Until that happens Richmond decides on the 2021 policies.

Is your Richmond upon Thames site inside a centre buffer, a breach hazard band or the surface water extent?

We will check which row of Policy 8's table the site falls in, whether a Sequential Test is needed and what a basement can be used for. Get a no-obligation, free quote. One of our experienced flood risk consultants will get back to you within 60 minutes.

Start a Quote

Drainage strategy requirements in Richmond upon Thames: the proforma, the SuDS statement and the 2 l/s test

Richmond's drainage standard is Policy 8 part H; there is no separate adopted design guide with its own rates. Around it the council publishes forms and guidance of different ages, so a strategy is written to the policy first and the forms second. The three-step rate, and the written sewer capacity confirmation that paragraph 16.77 asks for, are covered above.

  • The proforma. The council's SuDS page says applicants have had to complete the London Sustainable Drainage Proforma for all planning applications since 1 April 2019, and the February 2026 checklist says "All relevant applications should complete and submit the London Sustainable Drainage Proforma (Excel spreadsheet)". The council's copy of the form still cites the superseded LP21 wording; the form is right, its policy references are not.
  • The SuDS statement. The checklist asks for a statement showing how surface water could affect the site and its surroundings after development, the SuDS features proposed, and their long-term management and maintenance, "including who will be responsible and how maintenance will be funded".
  • Who reviews it. The council as Lead Local Flood Authority is consulted on every major application. Maintenance is secured by planning condition or obligation for the lifetime of the development (paragraph 16.80).
  • Climate change. Policy 8 part L asks for the appropriate allowance; the council sets no figure of its own, so the rate comes from the Environment Agency's peak rainfall allowances (last updated 27 May 2022) for the site's management catchment.
  • Local guidance. Delivering SuDS in Richmond (February 2015) is still the borough's SuDS guidance document. It predates Policy 8, so it is useful on techniques and out of date on rates.

We found no council decision adopting the 2025 National Standards for sustainable drainage, but two 2026 documents point to them. The validation checklist says SuDS proposals "should also have regard to the National standards for SuDS", and the Sustainable Construction Checklist SPD, adopted on 27 March 2026, lists them as a resource in its flooding and drainage section. That SPD's checklist must be submitted with any scheme creating a new dwelling or 100 m² or more of non-residential floorspace, and it asks whether greenfield rates are met. Chapter 18 of the NPPF goes further and says SuDS should be designed in accordance with the National Standards. Our notes on the SuDS proforma and the 2025 National Standards explain both.

Infiltration is the second step of the hierarchy, and the ground decides whether it is available. The SFRA records London Clay, with very low permeability, beneath the whole borough; river terrace sands and gravels lie over much of it, and Langley Silt, which water moves through less easily, over other parts. A drainage strategy here shows which of those the site sits on and how deep groundwater is, with testing to BRE 365 where infiltration is proposed. Our BRE 365 infiltration rate calculator and ground conditions and soakaway map are a starting point.

The Richmond upon Thames SFRA: four web maps, breach hazard and 31 surface water hotspots

The evidence behind Policy 8 is the Level 1 Strategic Flood Risk Assessment, prepared by Metis Consultants: version 1.2 in September 2020 and version 1.3, with updates on subterranean development, in March 2021. The council's SFRA page holds the report and four interactive maps, and says a further update is being kept under review. There is no Level 2 SFRA. The Local Plan's allocations were tested instead in a Flood Risk and Development Sequential Test report (Metis, April 2023).

  • Four web maps. Fluvial and tidal flood risk; surface water; groundwater, sewer and artificial sources; and a policy map showing the centres with their 800 m buffers and the Article 4 Direction boundary. Policy 8 sends applicants to these as well as the Environment Agency's Flood Map for Planning (paragraph 16.54).
  • Tidal breach. The fluvial and tidal map shows the extent, depth, level and hazard of a breach in the Thames defences, modelled to the year 2100. Table 16.5 and the sleeping-level rule both key to it.
  • Flood Zone 3b. The SFRA draws the functional floodplain from the Environment Agency's 1 in 20 year modelled extents, allowing for defences, plus flood storage areas. For the Thames, the 2025 Local Plan now defines it as land riverward of the tidal defences. The council's page also notes that the Flood Map for Planning published on 25 March 2025 includes a 3.3% (1 in 30) defended scenario, which national guidance says will normally form the functional floodplain. A site near the edge needs all three checked.
  • Groundwater and throughflow. The groundwater map shows where susceptibility to groundwater flooding is 25% or more, the screening trigger, and the four throughflow catchments from the council's Further Groundwater Investigations (2020).
  • Surface water hotspots. The Surface Water Management Plan was updated in December 2021. It replaced the earlier Critical Drainage Area approach with 31 hotspots, each drawn from the 1 in 100 year surface water extent where at least 15 homes are at risk, and rates seven of them high. Policy 8 and the checklist use the hotspots as triggers. The 2021 SFRA still lists the seven older Critical Drainage Areas.

When the SFRA was published in March 2021, it recorded that the Environment Agency had designated no area with critical drainage problems in the borough. That national trigger for an assessment did not apply here then; the council's own surface water triggers apply instead. Parts of the SFRA's own drainage text predate the 2025 plan (it speaks of three times the greenfield rate), and where the two differ we follow Policy 8. Our explainers on what an SFRA is for and Flood Zone 3b give the background.

The February 2026 Local Validation Checklist: which report each Richmond upon Thames application needs

The Local Validation Checklist for All Applications was agreed on 19 February 2026 after public consultation and took effect the next day. Five of its items concern flooding and drainage: item 34 (Flood Risk Assessment), 35 (Flood Emergency Plan), 36 (Drainage Strategy incorporating SuDS), 37 (Basement Assessment) and 38 (Foul Sewage and Utilities Statement). Its Appendix 3 reprints Policy 8's zone table.

Triggers from the February 2026 Local Validation Checklist, Policies 8, 9 and 54, and NPPF Chapter 18
TriggerFlood risk assessmentSequential and Exception TestsDrainage and other documents
Householder development or a non-residential extension under 250 m² in Flood Zone 2 or 3The council's declaration form for householder and other minor extensions, or a site-specific assessment; without one the application is invalid (item 34)Sequential Test not needed (NPPF Policy F5); Exception Test not needed where the Sequential Test is not (Policy F6)SuDS still expected under Policy 8 part H where runoff changes
Other development in Flood Zone 3a or 3bYes, for all proposals (Table 16.4; item 34)Sequential Test unless NPPF Policy F5 exempts it (the wider local exemptions in paragraphs 16.59 and 16.60 are discussed under Chapter 18 below); Exception Test for more vulnerable uses and essential infrastructure in 3a (Local Plan paragraph 16.56; NPPF Annex F table 3) and for essential utility infrastructure in 3bFlood Emergency Plan if major, or if safe access cannot be achieved (item 35; Policy 8 part C)
Other development in Flood Zone 2Yes, except a change of use from water compatible to less vulnerableSequential Test unless exempt; Exception Test for highly vulnerable usesAs above
Flood Zone 1 site in the 1 in 100 year surface water extent or a 2021 SWMP hotspot, major or minorYes (item 34); Table 16.4 applies the Flood Zone 3a restrictions to the surface water extentSequential Test under Table 16.4 unless exempt; NPPF Policy F5 exempts surface-water-only sites shown to keep occupiers safe without raising risk elsewhere, and sites with no built development on land at risk. On the Exception Test the two differ: Table 16.4 requires it for more vulnerable development in this extent, while NPPF Policy F6 applies it in Flood Zones 2, 3a and 3b only, so we confirm the council's position on each siteFlood Emergency Plan if major (item 35); drainage strategy (item 36)
Flood Zone 1 site of 1 ha or more; land identified as at increased flood risk in future; a more vulnerable use on land subject to other sources of floodingYes (item 34; NPPF Policy F4)Sequential Test where the land is at risk from any source, subject to the Policy F5 exemptionsDrainage strategy
Major development anywhere (DMPO 2015: 10+ homes, 0.5 ha+ for housing where numbers are unknown, 1,000 m² floorspace, or a 1 ha site)Where any trigger above appliesAs aboveDrainage Strategy incorporating SuDS with the London proforma (item 36); LLFA consulted; Foul Sewage and Utilities Statement with evidence of early engagement with Thames Water (item 38; Policy 9 part D)
Any other development with evidence of flood risk, or that could change surface water runoffYes where there is evidence of risk from surface water, groundwater or sewers (item 34)As the zone requiresDrainage strategy and SuDS statement (item 36); in Ham and Petersham, SuDS on every new building (Policy E4)
Basement or cellar in a throughflow and groundwater policy zone, or where groundwater susceptibility is 25% or moreYes (item 34)As the zone requiresScreening Assessment and, if it finds a possible impact, a Basement Impact Assessment with a verification form signed by the chartered professional (item 37; Policy 54 part B5); cross-section showing 1 m of soil and a 200 mm drainage layer under gardens
Within 16 m of a tidal defence or 8 m of another main river, culverted reaches includedYes where in a flood zone; the line and condition of the tidal defence shown for sites beside the Thames (item 34)As the zone requiresSet-back or evidence agreed by the Environment Agency (Policy 8 part I); the Environment Agency consulted

The first row decides whether an extension application is valid. A rear extension in Flood Zone 2 does not need a full assessment, but it does need the council's declaration form filled in, and the checklist says in terms that a missing form or assessment makes the application invalid. The national standing advice for minor extensions sits behind that form. The checklist also warns that "minor" has a flood risk meaning in national guidance that is narrower than the planning meaning; a single new house in Flood Zone 2 or 3 is minor development for planning purposes and still needs the full assessment and, outside the exemptions, the Sequential Test.

Chapter 18 of the August 2026 NPPF beside Richmond's local Sequential Test

Since 17 August 2026 national flood policy has sat in Chapter 18 of the National Planning Policy Framework. Policy F4 says when a site-specific assessment is needed, F5 and F6 set the Sequential and Exception Tests, F7 the safety tests, and F8 asks for SuDS designed to the National Standards. Richmond's plan was examined against the earlier Framework of 2023, so the two have to be read together.

On most points they agree, and where Policy 8 is stricter (the surface water row, the basement tables, the 2 l/s step) the local rule is the one an application is tested against. They differ on the Sequential Test in two ways. Policy F5 caps the search at "the anticipated catchment of the development in terms of its likely occupiers or users", which limits the area any Richmond search can cover. And F5's list of exemptions is not the same as paragraphs 16.59 and 16.60. It covers tested allocations, householder development, small non-residential extensions and changes of use (other than to caravan, camping, chalet, mobile home or park home sites). It also covers sites with no built development on land at risk and surface-water-only sites shown to be safe. It has no town centre or 800 m buffer route and no single-dwelling replacement route.

The Framework says how that difference is weighed. Its Annex A on implementation states that development plan policies "which are materially inconsistent with national decision-making policies in this Framework should be given very limited weight", and that "The only exception to this is where they have been examined and adopted or made against this Framework". Other plan policies "should not be given reduced weight simply because they were adopted prior to the publication of this Framework". Richmond's plan was examined against the earlier Framework of 2023, so the exception does not cover it.

For an applicant the practical effect is this. A scheme that relies only on the centre boundary, the 800 m buffer or the single-dwelling route should expect to be asked for a Sequential Test under Policy F5, searched within the scheme's catchment. The exemptions the two documents share (tested allocations, changes of use) are unaffected. We confirm the position with the case officer before the application goes in, and where F5 has no matching exemption we prepare the test. The national Planning Practice Guidance on flood risk and coastal change was last updated on 17 September 2025. Changes to national flood policy are tracked on our NPPF guidance and advice page.

Tidal below Teddington, river above it, storm water everywhere: flood risk across the borough

The River Thames is tidal up to Teddington Lock. Below it, through Twickenham, Richmond, Kew, Mortlake and Barnes, the Thames tidal defences and the Thames Barrier hold back the tide. The Environment Agency's Thames Estuary 2100 Plan covers that reach in three policy units: Richmond, Twickenham and Barnes and Kew. All three have policy P5 for tidal flooding, meaning further action to reduce risk, and none has a riverside strategy yet; councils are asked to plan theirs by 2030. Barrier operation is due to change in 2035, which matters upstream of Kew because the Barrier is also closed against high river flows today. Defence owners are asked to work with the Agency by 2050 to raise defences where required. Unda's guide to the Thames Barrier explains the closures.

Above the lock, Teddington, Hampton Wick and Hampton face the non-tidal Thames, which rises over days after long rain. Policy 8 asks schemes to take account of the River Thames Scheme, whose works include extra capacity at Teddington weir; our note on the River Thames Scheme's delays has the current position. The River Crane and the Duke of Northumberland's River cross Twickenham and Whitton, and Beverley Brook runs through Barnes to the Thames.

Surface water and sewer flooding reach the most homes. The Local Plan calls the borough "very susceptible to surface water flooding" (paragraph 16.75), and the council's Section 19 investigation (version 2.0, June 2023) into the storm of 12 July 2021 recorded ten reports of flooding at eight locations, six of them inside buildings, at Chestnut Road, Eleanor Grove, Lower Mortlake Road, The Quadrant and Halcyon Close. Our area pages for Richmond upon Thames and Twickenham have the local history and a postcode map, the London overview covers the wider city, and the live river levels map shows current gauge readings.

Reports we prepare for applications to Richmond Council

A flood risk assessment says whether the site is safe, a sequential or exception test says whether the development should be there, and a drainage strategy says where the water goes. Richmond's checklist lists them as separate items, and each of ours is written to the Policy 8 part it answers.

  • Every source, both reaches. Policy 8 part A names river, tidal, surface water, groundwater and sewer flooding, and our flood risk assessment deals with each for the site.
  • Checklist item 34. A flood risk assessment for planning that states the Table 16.4 row, sets floor levels to paragraph 16.69 and, beside the Thames, records the defence line.
  • Buying beside the river or in a hotspot. A flood risk survey for property purchase where a search flags the defended tidal zone, the non-tidal Thames at Hampton or surface water on a home.
  • Where Policy F5 does not exempt the scheme. A sequential and exception test report searched within the scheme's catchment, including for sites inside the centre buffers where the officer applies the national list, and the Exception Test case for housing in Flood Zone 3a.
  • Greenfield, 2 l/s or 50%. A drainage strategy that takes Policy 8 part H one step at a time and gives the reason for each step down.
  • Major schemes and item 36. A surface water drainage strategy with the London proforma completed and the maintenance and funding statement the checklist asks for.
  • After consent. The evidence for the discharge of drainage conditions the council uses to secure SuDS maintenance under paragraph 16.80.
  • Basements in the throughflow zones. A groundwater flood risk assessment for the flood, groundwater and drainage parts of the screening that Policy 54 asks for on Richmond Hill, Strawberry Hill, Marble Hill and St Margarets West.
  • The Policy 8 emergency plan. A flood warning and evacuation plan to meet part C and checklist item 35 on major schemes in Flood Zones 2 and 3, the surface water extent or a hotspot.
  • Major schemes and item 38. A foul drainage strategy to stand behind the utilities statement and the Thames Water capacity evidence Policy 9 requires.
  • Homes that have flooded. An insurance flood risk assessment for owners in the streets the 2021 Section 19 investigation recorded as flooded inside.

Every quote is a fixed fee.

Frequently asked questions

What does Richmond upon Thames Policy 8 (Flood Risk and Sustainable Drainage) require from a planning application?

Policy 8, in the Local Plan adopted on 7 October 2025, asks every development to be safe for its lifetime and to avoid or reduce flooding from all sources without raising risk elsewhere. It sets land use limits and the Sequential and Exception Tests by flood zone, and treats the 1 in 100 year surface water extent with Flood Zone 3a. It requires a Flood Emergency Plan on larger or cut-off sites and limits basements by breach hazard. On drainage it requires SuDS to greenfield runoff, 2 l/s or a 50% cut, and it sets 16 m and 8 m set-backs from defences and main rivers.

Is a flood risk assessment required for a house extension in Richmond or Twickenham?

In Flood Zone 2 or 3, something must be submitted. For householder development and non-residential extensions under 250 m², the February 2026 validation checklist accepts the council's declaration form for minor extensions in place of a full site-specific assessment, and says an application with neither is invalid. In Flood Zone 1 an assessment is needed where there is evidence of risk from surface water, groundwater or sewers, for example inside the 1 in 100 year surface water extent.

Does a site in Richmond town centre or Twickenham need a Sequential Test?

Plan for one unless national Policy F5 exempts the scheme. Local Plan paragraph 16.59 says the test is not required inside a town or local centre boundary, or for residential or mixed-use schemes within the 800 m buffer around each centre, but Policy F5 has no such exemption. Annex A of the August 2026 Framework gives very limited weight to plan policies that are materially inconsistent with it unless the plan was examined against it, and Richmond's was examined against the 2023 version. Confirm the position with the case officer early.

Can I add a basement bedroom in Richmond upon Thames?

Not in Flood Zone 2 or 3, and not within the 1 in 100 year surface water extent under Table 16.4 of Policy 8. Self-contained basement flats are barred in the same areas. Elsewhere a basement needs planning permission because of the borough-wide Article 4 Directions, must meet Policy 54's size and soil-depth limits, and needs a Screening Assessment in the four throughflow zones or where groundwater susceptibility is 25% or more.

What runoff rate does Richmond Council expect from a new development?

Greenfield runoff wherever feasible. If the applicant shows that is not feasible, Policy 8 part H sets a minimum of 2 l/s or below; if that cannot be met either, at least 50% attenuation of the site's existing peak runoff, with the justification written down. Surface water going to a public sewer needs written confirmation of capacity from Thames Water.

Which SFRA does Richmond upon Thames use, and is a new one planned?

The Level 1 SFRA by Metis Consultants, version 1.3 of March 2021, with four interactive web maps for river and tidal risk, surface water, groundwater and policy zones. There is no Level 2 SFRA. The council's SFRA page, updated on 3 June 2026, says a further update is being kept under review, and notes that the 2025 Local Plan redefined the Thames functional floodplain as land riverward of the tidal defences.

Submitting to Richmond Council with a basement, a riverside plot or a major scheme?

We set out the Policy 8 position, the breach hazard and the runoff rate before the application is validated. Get a no-obligation, free quote, with a fixed quote within the hour.

Start a Quote

To talk through a site in Richmond upon Thames, call 01293 214444 or email enquiries@unda.co.uk. Other councils are listed on our local authorities hub.

Get a no-obligation, free quote

If you need a quote or to discuss your requirements in more detail contact one of our experienced Flood Risk and Drainage Consultants.