Leigh Flood Storage Area: How the Barrier Works and What the 2026 Expansion Changed

Posted on 3rd November, 2026
by Antony Rousou

Estimated reading time 13 minutes

Home » Latest News and Blogs » Leigh Flood Storage Area: How the Barrier Works and What the 2026 Expansion Changed

The Leigh flood storage area is the Environment Agency's flood barrier and reservoir on the River Medway, between Leigh and Penshurst, a few kilometres upstream of Tonbridge. In a flood its gates close, the peak of the river is held back over farmland behind an earth embankment, and the water is let out once Tonbridge and Hildenborough can take it. On 30th September 2026 the Environment Agency opened a £42 million expansion, the first increase in the storage area's capacity since it was built in 1982.

The expanded Leigh flood storage area holds about 7.4 million cubic metres, roughly 23% more than before, and now reduces flood risk to 1,870 homes and 575 businesses, according to the Environment Agency's opening announcement.

That is a real reduction in risk for the towns downstream. It does not change the planning tests. A site in Tonbridge's floodplain still sits in the same Flood Zone it did before the gates were replaced, and a flood risk assessment for planning still has to start from the undefended position and then show what happens if the defences are exceeded or fail.

What is the Leigh flood storage area?

The Leigh flood storage area is an online flood storage reservoir: the River Medway flows straight through it every day, and it only stores water when the river is high. It was completed in 1982 by the Southern Water Authority after the flood of September 1968, and it is now operated and maintained by the Environment Agency. Locally it is usually called the Leigh barrier or the Leigh flood barrier.

  • The embankment. An earth bank about 1.3 km long and up to 5.7 m high runs across the Medway valley, with a clay core and gravel shoulders, according to a 2001 account of the barrier's operation.
  • The control structure. Three steel gates set in a concrete structure in the embankment either let the river through normally or restrict the flow so water backs up behind them.
  • The storage area. When full, the reservoir covers about 278 hectares of fields between Leigh and Penshurst, per the Environment Agency's Leigh flood storage area page.
  • The catchment. Around 500 square kilometres of the upper Medway and the River Eden drain to the barrier.
  • Its legal status. It is a large raised reservoir under the Reservoirs Act 1975, so it is inspected and maintained to reservoir safety standards. Works required under the Act, completed in December 2022, cost £8.7 million.

Storage is one of the main types of flood defence in England. Instead of walling the river in through the town, it changes the shape of the flood before it gets there: the same volume of water arrives, spread over a longer time and at a lower peak.

How does the Leigh barrier work in a flood?

The Leigh barrier works by trimming the peak of a flood. When flows on the Medway rise past a set threshold, the gates are lowered to restrict what passes downstream, the excess spreads over the storage area, and the stored water is released in a controlled way after the peak has gone through Tonbridge. The sequence runs like this:

  1. Normal flow. The gates stay open and the river passes through the control structure as if the barrier were not there.
  2. Rising river. Telemetry from gauges upstream on the Medway and the Eden, and rain gauges across the catchment, tell the operators a flood is coming.
  3. Impounding. Under the River Medway (Flood Relief) Act 1976, storing can start once flows exceed 35 cubic metres a second. The operators then lower the gates to hold water back.
  4. Holding the peak. Water spreads across the fields behind the embankment, up to a maximum level fixed in law and measured at the control structure.
  5. Release. After the peak has passed downstream, the gates are opened in stages and the reservoir is emptied. After the October 2000 flood that took two days.
New steel radial gate at the Leigh flood storage area control structure on the River Medway, with staff on the walkway.
New gate. One of the three replacement 12.5-tonne gates at the Leigh barrier, which restrict the Medway's flow so water is stored upstream in a flood.

Live levels at the barrier are published by the Environment Agency for the River Medway at Leigh flood storage area gauge.

In October 2000 the inflow to Leigh passed 250 cubic metres a second, more than the 226 cubic metres a second recorded in 1968, and the embankment was not overtopped.

How often has the Leigh flood storage area been used?

The Environment Agency's records show a significant flood on this stretch of the River Medway roughly every 15 years. The table sets out the floods and works that matter for the barrier.

Leigh flood storage area: key events, 1968 to 2026
YearEventWhat happened
1968September floodSignificant flooding in Tonbridge and Hildenborough; the event that led to the barrier being built (see the Great Flood of 1968)
1982Barrier completedBuilt by the Southern Water Authority to reduce flood risk to about 1,200 homes and businesses
2000Autumn floodsInflow above 250 m³/s; the reservoir reached its peak within 14 hours and was not overtopped
2013Christmas floodUp to 76 mm of rain fell in 24 hours on saturated ground on 23rd and 24th December; the barrier protected 938 homes, but the flood exceeded its design capacity
2019Winter 2019/20 floodsListed by the Environment Agency among the significant floods on record
2022Reservoirs Act worksEmbankment erosion protection completed a year early at £8.7 million
2026Expansion opened£42 million scheme opened on 30th September; storage up about 23% to around 7.4 million m³

The Christmas 2013 flood made the case for an expansion that the 2010 Middle Medway Strategy had already proposed. The Environment Agency's River Medway flood storage areas project records that the barrier protected 938 homes that winter but that the flood exceeded its design capacity. A paper by Samuels and Howe for Flood & Coast 2016 described that flood as comparable in severity to 1968 and 2000, with a different pattern of flows across the catchment.

What did the 2026 expansion change?

The expansion raised the highest level the reservoir is allowed to hold, so the same footprint of land can store more water in a big flood. It also added a new flood defence at Hildenborough. The work took about three years and the barrier stayed in service throughout.

  • A higher legal water level. The maximum stored level is set by the River Medway (Flood Relief) Act 1976. Raising it from 28.05 m AOD to 28.6 m AOD, an increase of 55 cm, needed an application to amend the Act, a local inquiry in April and May 2021 and the Secretary of State's approval in September 2021.
  • More land. Storing to the higher level brings about 16.4 hectares of extra land into the storage area, according to the Leigh expansion and Hildenborough embankment scheme page.
  • New gates. The three gates in the control structure were replaced with new 12.5-tonne gates, with new lifting and electrical systems and moving platforms for maintenance.
  • An eel pass. A new pass beside the control structure restores a migration route for eels.
  • Hildenborough. A 98 m embankment, a sheet-piled wall and a new pumping station and penstock on the Hawden Stream.
  • Cost and partners. The final cost was £42 million, up from an earlier estimate of £36.14 million, funded by government with Kent County Council, Tonbridge and Malling Borough Council and the South East Local Enterprise Partnership. VolkerStevin was the contractor.

This is a major investment in the safety and resilience of communities along the River Medway.

Simon Curd, Flood Risk Manager for Kent, Environment Agency, 30th September 2026

What does the Leigh flood storage area not protect against?

The Leigh flood storage area reduces the chance of the Medway flooding Tonbridge and Hildenborough; it does not remove it. The Environment Agency's own page says that exceptional rainfall may still cause flooding downstream, only less than there would have been without the barrier. Several kinds of residual flood risk are left behind.

The 55 cm rise in the stored level adds room for bigger floods. It does not make a site behind the barrier low risk for planning purposes.

Once the storage area is full, any further water in a flood bigger than the one it was designed for carries on downstream, and climate change makes those bigger flows more likely over the life of any new building. Because Leigh is a large raised reservoir, there is also the very unlikely but serious case of the embankment failing while it is holding water; areas that would flood in that case are shown on the national reservoir flood maps, and reservoir flood risk is assessed separately from river flooding in a planning application.

The barrier also does nothing for flooding that does not come down the main Medway channel. Smaller watercourses in Tonbridge such as the Botany Stream and the Hilden Brook, surface water and sewer flooding all sit outside it, and the Tonbridge area guide sets those out street by street. Communities further down the river, including Yalding and East Peckham, sit where the Beult and the River Teise join the Medway below Tonbridge, and are covered by separate property flood resilience schemes rather than by Leigh.

What does the expansion mean for development in Tonbridge and Hildenborough?

For planning purposes, nothing changes on the Flood Map for Planning. England's Flood Zones are drawn as if the defences were not there, and the Flood Zones stay the same after new defences are built. A site in Flood Zone 3 in Tonbridge town centre is still in Flood Zone 3 after the expansion, and every planning test that follows from that still applies.

…the presence of existing flood risk management infrastructure should be ignored…

Planning Practice Guidance: Flood risk and coastal change, paragraph 024, on applying the Sequential Test

The consequences for a planning application are direct:

  • The Sequential Test still applies. New homes or other development in Flood Zones 2 or 3 in Tonbridge must still show there is no reasonably available site at lower risk, and the barrier cannot be used to argue the site is lower risk than its zone. A Sequential Test report is judged on the undefended zones; failing it can be enough on its own for refusal.
  • The Exception Test still applies. Housing in Flood Zone 3a still has to pass all three limbs of the Exception Test: that its wider benefits outweigh the flood risk, that it will be safe for its lifetime and that it will not increase flood risk elsewhere.
  • Residual risk has to be assessed. The Planning Practice Guidance warns: "Areas behind flood defences are at particular risk from rapid onset of fast-flowing and deep-water flooding". An FRA behind Leigh or the Tonbridge town walls needs to cover what happens when they are overtopped or fail, and that can mean hydraulic flood modelling of a breach or exceedance scenario rather than reading levels off a map.
  • Floor levels and safe access. Finished floor levels, safe routes out and, for many schemes, a flood warning and evacuation plan are set against the residual flood level, not the defended one. Get these wrong and the scheme either fails the Exception Test or is approved with conditions that cannot be met.
  • The storage area itself is off limits. Land designed to flood, such as a flood storage reservoir, counts as functional floodplain (Flood Zone 3b) even if it only fills in an extreme event. Under the NPPF, homes and other vulnerable uses in Flood Zone 3b should be refused, with no Exception Test route, and the local line is drawn in Tonbridge and Malling's Strategic Flood Risk Assessment.
  • Lost storage must be replaced. Building or raising ground anywhere in the Medway floodplain removes room for water, so it needs level-for-level compensatory flood storage on the site.

What the expansion does change is the evidence. A site that now sits behind a higher standard of protection has better defended modelling to draw on, lower residual flood depths in some cases, and a stronger case on the safety limb of the Exception Test. It still needs the assessment to show it. The same applies to anyone buying in the area: a flood risk survey before buying a property looks at the defended and residual risk as well as the Flood Zone.

Frequently asked questions

Who decides when the Leigh barrier is used?

The Environment Agency operates the barrier and decides when to close the gates, working from river and rain gauges across the upper Medway and the Eden. Warnings for the town are a separate service: the Agency issues them for the Tonbridge and Hildenborough flood warning area, and residents sign up to them directly.

Does the Leigh flood storage area protect Maidstone?

Not directly. The barrier holds back flows from the upper Medway and the Eden, but the Beult and the Teise join the Medway below Tonbridge. The Environment Agency's wider Medway project looked separately at storage on the Teise and the Beult, walls around Yalding and dredging towards Maidstone, and the communities below Tonbridge rely on their own defences and resilience measures.

Will the expansion lower my insurance premium?

It may, but not automatically. Insurers price from their own flood models, which do take account of defences, and a premium will only move once the insurer's model reflects the higher standard of protection.

Does the Flood Map for Planning now show Tonbridge as protected?

No. The Flood Zones on the Flood Map for Planning ignore defences by design, so the expansion does not move them. The benefit is more likely to show in the Environment Agency's defended modelling and its long-term flood risk service, which take defences into account.

Planning a site near the Medway

For a new home, extension or change of use in the Tonbridge or Hildenborough floodplain, the first thing to establish is the site's undefended Flood Zone, then whether it sits in the storage area's 3b land, then how deep and how fast water would arrive if the barrier or the town walls were exceeded. Those three answers set the floor levels, the access route and whether the Sequential Test is needed at all. A flood risk assessment for planning in Tonbridge works through them in that order, using the Environment Agency's post-expansion modelling where it is available.

About the author. Antony is a Senior Flood Risk and Drainage Consultant leading Unda's drainage and SuDS team. Unda has been trading since 2014, is a CIWEM Business Partner with CIWEM member and chartered (C.WEM MCIWEM) consultants, and has delivered 5,000+ flood risk assessments and drainage strategies across England and Wales.

Antony Rousou · BSc (Hons), C.WEM MCIWEM