PPG flood risk: what the September 2025 Sequential Test update changed
Estimated reading time 14 minutes
The PPG flood risk guidance changed on 17th September 2025, and the four paragraphs it rewrote decide how a Sequential Test gets scoped and evidenced today. The sequential approach now reads across every source of flooding, surface water included. A flood risk assessment can remove the test, but only for surface water and only on a planning application. The area of search should be proportionate to the development. And an alternative site does not have to be one you own.
Paragraphs 23, 27, 27a and 28 of Flood Risk and Coastal Change all still carry a revision date of 17th September 2025. Checked against the live guidance on 30 July 2026, nothing further has changed.
The test itself is unchanged in principle. What changed is the evidence you have to file, the ground you have to search, and the one narrow route out of it.
What changed in the PPG on 17th September 2025
Three paragraphs of the Flood Risk and Coastal Change guidance were revised and one was added: 23 on the aim of the sequential approach, 27 on applying the test to planning applications, 28 on reasonably available sites, and a wholly new 27a on the area of search. No Framework paragraph changed alongside them, so this is guidance catching up with the December 2024 NPPF rather than a change of policy. The paragraphs they cross-refer to are in section 14 of the Framework.
| Paragraph | What it now says | What it means for your application |
|---|---|---|
| 23, the aim of the sequential approach | Avoid development "in current and future medium and high flood risk areas considering all sources of flooding including areas at risk of surface water flooding" | Screening against fluvial and tidal Flood Zones alone will not do. A Flood Zone 1 site with mapped surface water risk can be caught |
| 27, applying the test to applications | A proportionate reading of NPPF paragraph 175: where an FRA shows occupiers and users stay safe from surface water risk for the lifetime of the development, the test "need not be applied". A five-year housing land supply shortfall is not relevant to applying the test | A defensible surface water FRA can remove the test. Nothing else can, and a land supply argument certainly cannot |
| 27a, the area of search (new) | The search area is "governed by local circumstances relating to the catchment area for the type of development proposed", and should suit the scale of the proposal and its settlement | Search areas are argued and justified now, not assumed to run district-wide |
| 28, reasonably available sites | Suitable for the type of development proposed, able to meet the same development needs, and a reasonable prospect of being developed at the same time. Alternatives "do not need to be owned by the applicant" | Off-market and third-party land has to be discounted on evidence, not waved away on ownership |
Does your site still need a Sequential Test?
Most sites in an area at risk of flooding from any source still do. Paragraph 27 confirms the test applies to major and non-major development under NPPF paragraphs 173 and 174, and points to paragraphs 175, 176 and 180 for the exemptions. Four gates decide it, worked through in order: whether any part of the site is in an area at risk now or in future from any form of flooding, counting rivers, sea, surface water, groundwater, reservoirs, sewers and canals; whether it is minor development or a change of use, which paragraph 176 exempts; whether it is an allocated site already sequentially tested at plan-making stage, which paragraph 180 covers; and whether the risk is surface water only with a flood risk assessment that proves lifetime safety, which is the paragraph 27 route the September 2025 update created.
Is any part of the site at risk from any source of flooding?
Rivers, sea, surface water, groundwater, reservoirs, sewers and canals all count, now and in future.
Is it minor development or a change of use?
Exempt from the Sequential Test and the Exception Test alike, though a site-specific FRA may still be required.
Was it allocated and sequentially tested at plan-making stage?
The Exception Test may still need revisiting where the proposal differs from what was assessed.
Is the risk surface water only, with an FRA proving lifetime safety?
The route the September 2025 update created. It does not reach fluvial or tidal risk, or Local Plan allocations.
Clear none of the four gates and the Sequential Test applies. The next question is the area of search.
Clear none of those gates and the test applies, at which point the question becomes how far you have to look. For the mechanics of the test and how it meshes with the Exception Test, see our explainer on the Sequential and Exception Tests. If the site sits in Flood Zone 1 but inside a Critical Drainage Area, assume the first gate is met.
When can a flood risk assessment replace the Sequential Test?
Only where the risk is surface water, and only on a planning application. Paragraph 27 sets its carve-out inside NPPF paragraph 175, the exemption for sites a flood risk assessment shows to be free of flood risk, and asks for that paragraph to be read proportionately where surface water is concerned. It does not disapply the test for fluvial or tidal risk, and it does not reach Local Plan site allocations.
In applying paragraph 175 a proportionate approach should be taken. Where a site-specific flood risk assessment demonstrates clearly that the proposed layout, design, and mitigation measures would ensure that occupiers and users would remain safe from current and future surface water flood risk for the lifetime of the development (therefore addressing the risks identified e.g. by Environment Agency flood risk mapping), without increasing flood risk elsewhere, then the sequential test need not be applied.
Planning Practice Guidance, Flood Risk and Coastal Change, paragraph 27
A site in Flood Zone 3 still needs a Sequential Test however good its flood risk assessment is. The carve-out reaches surface water and nothing else.
"Demonstrates clearly" is doing a great deal of work in that sentence, and it is where these submissions come unstuck. The Lead Local Flood Authority, not the Environment Agency, is the body that judges it, and six things generally have to be in the assessment first.
- Modelled surface water depths, velocities and hazard ratings across the site, in the design event and with the climate change allowance applied.
- Finished floor levels with freeboard above the modelled level, and a levels strategy that does not simply push water next door.
- Safe access and egress for occupiers and emergency vehicles in the design event, not a dry building footprint alone.
- Exceedance routing for events beyond the design standard, showing where water goes once the system is overwhelmed.
- Drainage designed to the discharge rates and storage the LLFA requires, with maintenance that holds for the lifetime of the development.
- An explicit lifetime assumption, usually 100 years for residential, with the climate change epoch and allowance band used to reach it.
That last point does more damage than people expect. "For the lifetime of the development" pulls the climate change allowances into the argument, so a scheme safe today but not in a century's time does not qualify. The data keeps moving too: the May 2026 update to the Flood Map for Planning brought surface water climate change data into the national mapping, and sites that screened clean before it may not now. Our guide to surface water flooding and planning covers the design side.
How wide does your area of search have to be?
As wide as the catchment for that type of development, and no wider. Paragraph 27a is the new paragraph and the most useful of the four, because it finally gives applicants something to argue with. The search area is "governed by local circumstances relating to the catchment area for the type of development proposed and the needs it is proposing to address", and should be "appropriate to the nature and scale of the proposal and the settlement it is proposed for".
For a non-major housing development, it would not usually be appropriate for the area of search to extend beyond the specific area of a town or city in which the proposal is located, or beyond an individual village and its immediate neighbouring settlements.
Planning Practice Guidance, Flood Risk and Coastal Change, paragraph 27a
That town-or-village limb is the PPG's worked example for non-major housing. Several published summaries quote it as though it were the general rule. It is not.
A 200-dwelling scheme cannot lean on it. What a major scheme can lean on is the principle above it, which is proportionality to the nature, scale and settlement of the proposal.
| Proposal | Indicative area of search | Basis in paragraph 27a |
|---|---|---|
| Non-major housing | The town or city the site sits in, or the village and its immediate neighbours | The worked example given in the paragraph |
| A school or similar service | The catchment the facility serves | "The catchment area for a school" |
| A small extension to existing premises | Usually none in practice | "A pragmatic approach" where relocating the space is impractical |
| A coastal town or settlement on a major river | May be limited to the settlement itself | Where large areas sit in Flood Zones 2 and 3 and development is needed to sustain the community, sites outside "are unlikely to provide reasonable alternatives" |
| Infrastructure of regional or national importance | May extend beyond the local planning authority boundary | Stated expressly in the paragraph |
| Large-scale development | May include splitting across several lower-risk sites | Only where those sites serve the intended markets as effectively |
Settle the search area early, in writing, at pre-application. One agreed with the case officer before you spend money on a site sift is worth considerably more than a well-argued one submitted cold. Because the boundary turns on local circumstances, it is worth reading what your council's own local requirements and validation list ask for, and screening candidates on the current Flood Map for Planning rather than an older SFRA extract.
Which alternative sites count as "reasonably available"?
Three tests, all of which have to be met. Paragraph 28 defines a reasonably available site as one whose location is suitable for the type of development proposed, that is able to meet the same development needs, and that has a reasonable prospect of being developed at the same time as the proposal.
- Suitable location. Suitable for the type of development proposed, not simply vacant land in a lower Flood Zone.
- Same development needs. A site that cannot deliver what the proposal delivers is no alternative to it.
- Same timeframe. A reasonable prospect of being developed at the same time, which rules out land with no realistic route to delivery.
- Ownership is irrelevant. Alternative sites "do not need to be owned by the applicant to be considered 'reasonably available'".
- Smaller sites can combine. The paragraph expressly contemplates "a series of two or more smaller sites" together accommodating the development.
The hardest evidence to produce is now the negative: showing why an off-market site you do not own is not reasonably available.
Ownership is the limb that catches developers out, and it is less new law than codified law. The courts had already reached the same conclusion in Mead, which our note on applying the Sequential Test post-Mead works through. What paragraph 28 adds is that the point can no longer live in a footnote. A sift that discounts land on ownership alone will not survive scrutiny.
Does a housing land supply shortfall help?
Not with the test. Paragraph 27 is explicit that "the absence of a 5-year housing land supply is not a relevant consideration in applying the sequential test for individual applications". It then adds the qualification most summaries drop: "However, housing considerations, including housing land supply, may be relevant in the planning balance, alongside the outcome of the sequential test."
Two different questions, and worth keeping apart. Land supply cannot widen or soften the test. It can still carry weight on the other side of the balance once the test has been applied and its outcome is known, which is the territory the Yatton judgment went into.
What to put in a Sequential Test submission
- The flood risk at the site from every source, with the date and version of the mapping used.
- The area of search, justified against paragraph 27a by development type, catchment and settlement.
- The date of the search and every source interrogated: Local Plan allocations, the SHLAA or HELAA, the brownfield register, live and recently determined permissions, agents' listings.
- Every candidate the search threw up, not only the ones that were easy to reject.
- A sift of each candidate against all three limbs of paragraph 28, giving the reason it fails in those terms, with its flood risk shown on the current Flood Map for Planning rather than an older SFRA extract.
- Where you rely on the paragraph 27 route instead, a cross-reference to the part of the FRA that demonstrates lifetime safety from surface water.
The date of the search matters nearly as much as the search. A sift that predates the application by a year invites the objection that a lower-risk site has come forward since.
Refresh it before determination if the application has been running for months, and again before any appeal. In our experience the Sequential Test is one of the first things a validation officer looks for, and a thin one is a common reason a submission gets bounced at validation. Our note on planning appeals in 2026 sets out why repairing it later has become the expensive option.
What the September 2025 update did not change
- The Exception Test. Passing the Sequential Test, or being exempt from it, says nothing about whether the Exception Test applies. That still turns on Flood Zone and vulnerability classification.
- The Flood Zones. Zone 1, 2 and 3 definitions are untouched, so our flood zones explainer still holds.
- The NPPF. No Framework paragraph changed on 17 September 2025. What comes next is the draft NPPF, which would take these principles further.
- When an FRA is required. The validation triggers for a site-specific flood risk assessment are unchanged.
- Wales. The guidance is England-only, and Welsh applications continue to run on TAN15.
Frequently asked questions
Does the September 2025 update apply to an application already submitted?
The guidance carries no transitional provisions, so decision-makers apply whatever is current when they determine the application. Anything submitted before 17 September 2025 and determined after it is assessed against the revised paragraphs. That cuts both ways, because the paragraph 27a proportionality argument is then available to you as well.
If the Sequential Test does not apply, does that mean the Exception Test does not either?
No. They are separate hurdles with separate triggers. NPPF paragraph 176 exempts minor development and changes of use from both, but the paragraph 27 surface water route only removes the Sequential Test. Whether the Exception Test bites depends on Flood Zone and vulnerability classification.
Does the paragraph 27 route apply to Local Plan site allocations?
It does not. Paragraph 27 is expressly about planning applications, and plan-making sequential testing of allocations is unaffected by it.
Can a planning condition or a section 106 obligation stand in for a Sequential Test?
Neither can substitute for it. The test is a policy gateway to be applied before permission is granted, not an outcome secured afterwards. Conditions and obligations manage residual risk once it has been passed.
How recent does the alternative sites search have to be?
There is no stated shelf life, but it has to support the decision being taken. A sift much more than six months old will usually be challenged, because land that was not available when you looked may be available now.
If you need a Sequential Test that will stand up to an LLFA, a case officer or an Inspector, our Sequential and Exception Test reports set out how we scope the area of search, evidence the site sift, and prove the paragraph 27 route where it is genuinely available.