Flood Risk Assessment in Woolwich
Contact Us
A flood risk assessment in Woolwich usually begins at the river wall: along Woolwich Church Street, past the ferry pier and around the Royal Arsenal. The Thames Barrier stands less than two kilometres upstream of the ferry, and still the council's 2026 flood study models water more than three metres deep on parts of the riverside if a section of that wall gave way. Our consultants prepare flood risk assessments in Woolwich for planning applications, for buyers and their lenders, and for insurers, along with sequential and exception tests and surface water drainage strategies.
Here, Woolwich means three Royal Greenwich wards. Woolwich Dockyard covers the riverside west of the ferry, from the old dry docks and Mast Quay to Woolwich Church Street. Woolwich Arsenal takes in the town centre around Powis Street and General Gordon Square, the Woolwich Ferry terminal and the Royal Arsenal, including Royal Arsenal Riverside, east to Gunnery Terrace. Woolwich Common climbs south past the Royal Artillery Barracks. The outline sits almost entirely in the SE18 postcode district. Charlton and the Thames Barrier lie to the west, with Greenwich beyond; Plumstead and then Thamesmead lie to the east; North Woolwich, across the river, belongs to Newham.
On the Woolwich Ferry site, the council's July 2026 assessment models a breach of the river wall up to 3.5 metres deep in today's conditions and up to 4.6 metres by 2115, at a hazard rating it classes as dangerous for all.
Questions about a Woolwich address or scheme can go straight to our consultants on 01293 214444 or enquiries@unda.co.uk.
The Woolwich flood documents: what the council's 2026 site assessments found
Royal Greenwich published a new Strategic Flood Risk Assessment in July 2026, prepared by Metis Consultants, with a Level 2 assessment for each site the draft Local Plan allocates. The Woolwich sites carry references beginning P4-W, and their five-to-seven-page PDFs are what most people looking for the Woolwich flood documents find first. Each gives the site's share of every flood zone, the depth, level and hazard of a modelled breach of the Thames defences in present-day and 2115 conditions, the surface water, sewer, groundwater and reservoir risk, recommended escape routes, and whether the exception test applies.
| Site (draft plan capacity) | Flood zones | Breach depth, today to 2115 | What the assessment requires |
|---|---|---|---|
| Woolwich Dockyard and former dry docks, Woolwich Church Street (10.24 ha; about 1,020 homes) | 31% Flood Zone 3a, 12% Flood Zone 3b, 11% Flood Zone 2 | 1.16 m now, 2.05 m by 2115 (1-in-200 breach); up to 2.40 m in the 1-in-1,000 event | Exception test; no more vulnerable use on the Flood Zone 3b strip; escape towards Leda Road and Woolwich Church Street |
| Woolwich Ferry and Ambulance Station (1.62 ha; about 210 homes) | 36% Flood Zone 3b, 34% Flood Zone 3a, 22% Flood Zone 2 | 3.51 m now, rising to 4.59 m; hazard above 5 in every scenario | An ambulance station, a highly vulnerable use, is not permitted in Flood Zone 3; exception test if it goes in Flood Zone 2 |
| Waterfront Leisure Centre, Woolwich High Street (0.82 ha; about 310 homes) | 41% Flood Zone 3a, 9% Flood Zone 2 | 1.11 m now, up to 2.40 m by 2115; 36% of the site also at high surface water risk | Exception test; no more vulnerable use on the small Flood Zone 3b area |
| Gunnery Terrace (0.94 ha) and the IO Centre (1.91 ha), eastern Royal Arsenal | 71% and 48% Flood Zone 3a | 0.76 m now, up to 1.36 m by 2115 at Gunnery Terrace | Exception test on both; groundwater can reach below-ground spaces across both sites |
| Woolwich OSD East, over-site development above the Elizabeth line station (1.18 ha) | 4% Flood Zone 3a, 2% Flood Zone 2 | 0.69 m now, up to 1.35 m by 2115 | Exception test for the housing |
| Spray Street Quarter (2.3 ha) and the Woolwich Arsenal station sites (1.92 ha) | Flood Zone 1 | Outside the tidal flood zones | Surface water assessment only: 38% of Spray Street floods in a 1-in-100 storm, and water up to 1.2 m deep collects along the railway cutting |
The hazard numbers follow the council's four bands: below 0.75 is a caution, up to 1.25 is dangerous for some people such as children, up to 2.0 is dangerous for most people, and above 2.0 is dangerous for all. On an allocated site the assessment's starting evidence already exists, so the job is to turn it into floor levels and an escape route that meet the conditions. The Level 2 screening table lists every Woolwich allocation, including those found to need no site assessment. A windfall site, one the plan does not allocate, has no such page, and our guide to flood depth data for rivers and the sea explains where the equivalent figures come from.
Below the Barrier: Woolwich's river wall and the two TE2100 policy units
Woolwich begins just downstream of the Thames Barrier, whose ten steel gates span 520 metres of river. By November 2025 it had been closed 221 times for flood defence since it began operating in 1982. Together with the river walls, it protects the borough against a combined tide and river flood with a 1-in-1,000 chance in any year, according to the 2026 SFRA. A Woolwich scheme is judged on the risk left over: water coming over the wall in a larger event, or through it where a section fails.
- The ferry terminal splits the frontage. The Environment Agency's Thames Estuary 2100 plan divides Woolwich at the Woolwich Ferry Terminal. Land to the west, including the Dockyard and the Barrier's south bank, sits in the Greenwich policy unit under policy P5, further action to reduce flood risk. The Royal Arsenal side is the start of the Thamesmead policy unit, which runs east to Erith Pier under P4: action to keep pace with climate and land use change so that risk does not rise.
- Walls east of the Barrier are due to rise first. Both unit pages ask owners of tidal defences downstream of the Barrier to work with the Environment Agency to raise them where required by 2040, ten years ahead of the date set upstream. Councils are asked to work with their communities on how the riverside will look by 2030, and Royal Greenwich's 2026 flood strategy commits to a riverside strategy by the end of 2030.
- Ground levels decide the depth. Modelled breach levels across the Woolwich allocations run from about 5.5 to 7.5 m AOD (metres above Ordnance Datum, close to mean sea level). What sits under that water line differs from plot to plot, so the 1-in-200 breach leaves at most about a metre of water on the Dockyard and three and a half on the Ferry site, a few hundred metres apart.
- Replacing the Barrier. The council's flood strategy expects the Thames Barrier to be replaced by 2070 with a higher structure further downstream. Floor levels on a new Woolwich home have to hold for the building's lifetime, which planning guidance takes as at least 100 years for housing, and our article on the Barrier's closures, cost and future covers the plans for its successor.
Our River Thames page follows the tidal river through London, and the guide to residual flood risk explains how a breach is tested in an assessment.
Check a postcode from the old dockyard to the Royal Arsenal
Enter a Woolwich postcode to screen it against Environment Agency data for rivers and the sea, surface water and reservoirs, or open the full flood risk map for anywhere in England. The coral line follows the Woolwich Dockyard, Woolwich Arsenal and Woolwich Common wards. Read the two river layers separately: the flood zone ignores the river wall while the risk-of-flooding layer allows for it, so a riverside flat can show Flood Zone 3 and very low risk on the same screen (how the two maps differ).
Flood events in Woolwich, from the 1928 tide to Plumstead Road
Few floods in Woolwich itself are dated on the record, because the defences have mostly held since the Barrier opened. The entries below come from contemporary accounts, the Environment Agency's gauge record and the council's own flood investigations.
- 7 January 1928. A surge on a spring tide, with the river already high from rain and snowmelt upstream, came over the embankments in the early hours. Fourteen people died in London and about 4,000 were made homeless, and serious flooding was reported at Greenwich, Woolwich and places further downriver.
- 31 January to 1 February 1953. The North Sea surge killed 307 people in England and led to the decision to build a movable barrier across the Thames near Woolwich. Our account of the 1953 flood covers the warnings that failed that night.
- 11 January 1993. The tide at the Environment Agency's Silvertown gauge, on the north bank opposite the Dockyard, reached 5.45 m AOD. That is still the highest level on its record, against a statutory defence level of 7.20 m at the same station.
- November 2023 to May 2024. The council's borough-wide Section 19 investigation looked at four places where homes or roads flooded in this period. One was Plumstead Road, which runs east from the town centre past the Spray Street Quarter: the road is low-lying, and gullies with large inlets let in debris that blocked the drains.
Two Environment Agency warning areas meet at the Arsenal. Tidal Thames from Woolwich Arsenal to Deptford Creek covers the frontage west towards New Charlton and the Greenwich Peninsula, and Tidal Thames from Erith High Street East to Woolwich Arsenal runs downstream through North Plumstead and Thamesmead and includes the Woolwich Arsenal site itself. Check either for a warning in force today, and follow the tidal gauges on our live river levels map.
Rain, sewers, groundwater and the reservoirs upriver
Away from the river wall, the flooding most Woolwich properties are likely to meet comes from heavy rain and from the ground. The land climbs from the riverside alluvium past Woolwich Common towards Shooters Hill, so storm water runs downhill into the town centre, where the railway cutting and the streets around Spray Street and Vincent Road collect it.
| Source | Where in Woolwich | What the evidence shows |
|---|---|---|
| Tidal Thames | The frontage and the defended land behind it | Defended to a 1-in-1,000 standard; Flood Zones 3a and 3b along the river, with residual breach and overtopping risk (SFRA, 2026) |
| Surface water | The town centre, the railway cutting at Woolwich Arsenal station, Spray Street and Vincent Road | Woolwich Town Centre is local flood risk zone 6001a within critical drainage area Group6_001 in the 2011 Surface Water Management Plan, listed again in the 2026 flood strategy |
| Sewers | The town centre, the stations and the riverside | 30 to 40 reported sewer flooding incidents in the postcode areas around the stations, and 40 or more around the Dockyard and Elizabeth line sites (Level 2 SFRA) |
| Groundwater | Riverside alluvium over Thanet Sand and, under the northern Dockyard, Chalk | The 2026 flood strategy rates the area around Woolwich at fairly high risk because of its closeness to the Thames |
| Reservoirs | The northern part of the Dockyard and the Ferry site | Breach mapping for the King George V, William Girling and Banbury reservoirs in the Lea Valley reaches the Dockyard site even on a dry day |
| Ordinary watercourses | East of the outline, through Plumstead | The Wickham Valley Watercourse, also called the Wogebourne or Plumstead River, is a high-risk channel and the council's responsibility as lead local flood authority |
Our explainer on critical drainage areas sets out what that designation means for an application, and the guide to groundwater flooding covers basements and lift pits. The Woolwich site assessments ask for ground investigation before infiltration SuDS are relied on; our geology and soakaway map gives a first view of what lies beneath a plot.
Policies E2 and E3 now, EN6 and EN7 in the draft Local Plan
A Woolwich application is decided today against the Core Strategy adopted in July 2014, whose Policy E2 deals with flood risk and Policy E3 with the residual risk behind the defences, read with the London Plan 2021 and chapter 18 of the August 2026 NPPF. The replacement Local Plan 2025 to 2040 finished its Regulation 19 consultation on 6 September 2026, and its draft policies EN6 and EN7 would add the rules below.
- What the council asks for now. Royal Greenwich's validation list of June 2025 already asks for a flood risk assessment with all development in Flood Zones 2 and 3, domestic extensions and changes of use to housing included. In Flood Zone 1 it asks for one where surface water is mapped 0.3 m deep or more, or where the site is within 100 m of a recorded sewer flood or 250 m of a groundwater flood.
- Who would need an assessment (draft EN6). A site-specific flood risk assessment would be required in Flood Zones 2, 3a and 3b and in critical drainage areas, on any site over a hectare, for major development in Flood Zone 1, and wherever a scheme adds habitable units or bedrooms below ground.
- What would be ruled out. Highly vulnerable uses, basement dwellings among them, would not be permitted in Flood Zone 3 or a critical drainage area. Bedrooms in an area at risk of tidal flooding would sit above the design tidal level, allowing for breach and climate change.
- Room for the wall. Buildings would be set back at least 16 m from the landward edge of the tidal defence, buried parts included, so the wall can be maintained and raised in line with TE2100.
- Construction phase. Major schemes would add a construction drainage strategy showing how surface water is handled from topsoil strip to completion.
- Drainage (draft EN7 and SI 13). Major schemes and new buildings would include SuDS that follow the national standards and the London Plan drainage hierarchy, aim for greenfield runoff and resist new hard surfacing. New basements connected to a sewer would need a positive pumped device. NPPF policy F8 already expects every development to meet the 2025 national standards for SuDS.
Nationally, policy F4 sets when a flood risk assessment is needed, and F5 and F6 set the sequential and exception tests. Our guides to when an assessment is needed and to the London Surface Water Strategy add the national and London-wide detail, and our Royal Greenwich guide sets out the council's requirements across the borough.
Working on one of the Woolwich allocations?
Tell us the site and what you plan to build. One of our experienced flood risk consultants will come back within 60 minutes with a free, no-obligation quote.
Start a QuoteA flood risk assessment in Woolwich: which projects need one?
On the riverside half of Woolwich, nearly always, because the flood zone alone triggers one. Higher up, on Woolwich Common and around the barracks, the trigger is more often surface water, a basement or the size of the site.
| Project | Likely requirement | Why |
|---|---|---|
| Rear extension to a house on Woolwich Common | Often no flood risk assessment | Flood Zone 1 and under a hectare, unless one of the council's validation triggers applies: surface water 0.3 m deep, or a recorded sewer or groundwater flood nearby |
| Extension or change of use on the riverside | A flood risk assessment, which for a minor extension can follow the Environment Agency's standing advice | The validation list asks for one with all development in Flood Zones 2 and 3, extensions included |
| New flats on the Dockyard, Ferry or Waterfront sites | Flood risk assessment with breach analysis, the exception test, a drainage strategy and the SuDS proforma | The Level 2 SFRA verdicts, Policies E2 and E3, draft EN6 and London Plan SI 13 |
| Housing on a windfall riverside site | As above, plus a sequential test | Only allocated sites in their allocated use would be spared the test under the draft plan |
| Basement flat or lower ground floor | Flood risk assessment and a groundwater screening study | Draft EN6 would bar basement dwellings in Flood Zone 3; groundwater lies close to the surface near the river |
| Buying a flat near the river | A pre-purchase flood survey if the search or lender flags tidal risk | Postcode screening tools allow for the defences, but the flood zone a lender may look at ignores them |
Our explainers on flood zones 1, 2 and 3 and on Flood Zone 3b, the functional floodplain cover the zones that run along the Dockyard and Ferry frontage, and basement conversions in a flood zone covers the rules below ground.
Reports for Woolwich sites, from the riverside to Woolwich Common
Three questions sit behind most Woolwich instructions: is the building safe from the river and the rain, should it be on this plot at all, and where will the surface water go. Each has its own report, and many schemes need more than one.
- New homes on the riverfront. Housing on the Dockyard, Ferry and Waterfront sites needs a flood risk assessment for planning that answers Policies E2 and E3 now and draft EN6 next.
- Every source on one plot. A flood risk assessment for a Woolwich site weighs a breach of the river wall against town centre surface water, a crowded sewer network and groundwater near the river.
- Before exchange on a riverside flat. Homes at the Royal Arsenal or by the old dockyard raise lender questions about the tidal zone, which a flood risk survey for property purchase answers with the building's own floor levels.
- Housing in Flood Zone 3. Windfall housing in the tidal zone faces the sequential and exception test, and on the Dockyard, Waterfront and Gunnery Terrace sites the council's own assessment already calls for the exception test.
- Runoff from new buildings. Draft EN7 and London Plan SI 13 expect SuDS on new buildings, set out in a drainage strategy that follows the London hierarchy.
- Wet ground near the river. Infiltration has to be proved by ground investigation on the Woolwich allocations, so a surface water drainage strategy here usually relies on attenuation and a controlled discharge rate.
- After permission. When Royal Greenwich attaches a drainage condition to a consent, we prepare the evidence for the discharge of drainage conditions.
- Breach levels for one plot. Where the Environment Agency's Downriver breach model does not reflect a site's levels or layout, flood modelling can set the design breach level that floors and escape routes depend on.
- Escape routes in a breach. The site assessments name escape routes such as Leda Road and Woolwich Church Street, and a flood warning and evacuation plan ties them to the two Woolwich Arsenal warning areas.
- Water below ground. Gunnery Terrace, the IO Centre and parts of the Ferry site show groundwater potential below ground level, so basement and lift-pit schemes benefit from a groundwater flood risk assessment.
- Cover in the tidal zone. Homes on the defended floodplain between the dockyard and the Arsenal can face questions about cover, and a flood risk assessment for insurance gives the underwriter evidence about the building itself.
- Buying allocated land. Six Woolwich allocations are flagged for the exception test, and the Ferry site rules out highly vulnerable uses in Flood Zone 3, so flood risk due diligence belongs before a land deal.
- Shops in the town centre. The 2011 surface water plan marks Woolwich Town Centre as a local flood risk zone, and a business continuity flood assessment helps shops and offices around Powis Street plan for a cloudburst or a breach.
- Commercial floorspace. The Spray Street Quarter alone is planned for about 14,820 m² of town centre uses, and a BREEAM flood risk assessment covers the Pol 03 credits.
- Sewer capacity. The Level 2 assessments record 30 to 40 or more sewer flooding reports in the Woolwich postcode areas, and draft EN7 asks for early talks with Thames Water, which a foul drainage strategy supports.
Woolwich flood contacts: the Environment Agency, Royal Greenwich and Thames Water
Responsibility in Woolwich is split by source. The Environment Agency runs the tidal defences, the Barrier and the warnings; Royal Greenwich, as lead local flood authority, handles surface water, groundwater and ordinary watercourses and investigates serious floods under Section 19; Thames Water owns the public sewers.
| Organisation | What it covers | How to reach it |
|---|---|---|
| Environment Agency | The tidal Thames, the Thames Barrier and the Woolwich flood warnings | Floodline 0345 988 1188, 24 hours; sign up for flood warnings |
| Royal Greenwich, lead local flood authority for Woolwich | Surface water, groundwater, ordinary watercourses, Section 19 investigations, drainage advice on major applications | 020 8854 8888; flooding and flood risk management pages |
| Thames Water | Public sewers and sewer flooding | Sewer flooding help |
| Thames Regional Flood and Coastal Committee | Flood scheme funding and priorities across the Thames area; Greenwich shares a seat with Bexley, Bromley and Lewisham | Committee page |
| London Resilience Forum | Emergency planning across London through the London Resilience Partnership | London Resilience Partnership |
| Emergency services and power | Anyone in danger from floodwater, or a loss of power | 999 in a flood emergency; 105 to report a power cut |
Royal Greenwich's Local Flood Risk Management Strategy, approved by the council's Cabinet in October 2026, sets out how the council will manage local flooding over the next six years, including the riverside strategy due by the end of 2030.
What Woolwich buyers and developers ask about flooding
Is all of Woolwich in Flood Zone 3, or only the riverside?
Only the lower part. The tidal zone runs along the river from the old dockyard to the Royal Arsenal. Most of the town centre, including Powis Street and the Spray Street Quarter, is in Flood Zone 1, as are Woolwich Common and the slopes towards Shooters Hill. The zones ignore the river wall, so they show how far a tide could reach without it.
Does a basement or loft conversion in Woolwich need a flood risk assessment?
A loft conversion rarely does unless the house is in Flood Zone 2 or 3. A basement is different. The draft Local Plan would require an assessment for any scheme that adds habitable rooms or bedrooms below ground, and would rule out basement dwellings in Flood Zone 3. The SFRA also asks basement schemes for a groundwater screening study using borehole levels from within 100 m of the site and no more than 20 years old.
With the Thames Barrier so close, why do Woolwich schemes still plan for a breach?
Because the Barrier holds back surge tides but cannot stop a length of river wall from failing. National policy and the council's policies ask new buildings to stay safe for their lifetime, so floor levels and escape routes are tested against a breach of the wall, with sea level rise added for later decades.
Why do fees for a flood risk assessment in Woolwich vary from site to site?
Mostly because of the breach work and the drainage. A small extension on Woolwich Common may need a short report, while flats on an allocation need breach levels, the exception test, a drainage strategy and the proforma. We quote a fixed fee once we have the address and the plans, and the quote is free.
Who is the lead local flood authority for Woolwich, and what does it check?
The Royal Borough of Greenwich. As lead local flood authority it is the statutory consultee on surface water for major applications, so it checks the drainage strategy against London Plan SI 13 and the national standards. The Environment Agency comments separately on tidal risk and on any work close to the river wall.
Does a Woolwich drainage strategy need the London sustainable drainage proforma?
For major schemes, yes. The GLA's proforma summarises the drainage strategy, and the 2026 SFRA expects it with every major application, listing greenfield, existing and proposed discharge rates for the 1-in-1, 1-in-30 and 1-in-100 year storms with 40% added for climate change. The SFRA also recommends a strategy and proforma for minor schemes and changes of use that alter a site's drainage.
How would Greenwich's draft Local Plan change things for a Woolwich site?
Not yet in full. The council expects to submit the plan for examination by the end of 2026, and until it is adopted applications are decided on Policies E2 and E3, with the draft given weight according to how far it has progressed. Once adopted, a scheme on a Woolwich allocation used as allocated would no longer need its own sequential test, unless the known flood risk had changed significantly.
Do the forecasts for 2050 put Woolwich under water?
No forecast we have found says so. National 2050 figures count properties with some modelled risk of river or sea flooding, and Woolwich stays dry because of its defences, which the Thames Estuary 2100 plan expects to raise east of the Barrier by 2040. The 2115 breach scenarios in the council's assessments test what happens if a wall fails; they do not predict that it will.
How do I check a Woolwich address for flood risk before buying?
Start with the postcode map on this page and the government's long-term flood risk service, then ask the seller about past flooding, basements and any insurance claims. If the search or the lender flags tidal risk, a site-specific survey reads the flood zone against the flat's floor level and the breach depths the council has published.
Could I prepare the flood risk assessment for my Woolwich application myself?
For a minor extension, the Environment Agency's standing advice lets an applicant set out floor levels and flood-resistant construction themselves. New homes in Flood Zone 3 are another matter: the council expects breach and overtopping to be assessed, climate change allowances applied and safe access shown, which needs specialist data and modelling.
Need Woolwich flood evidence before a deadline?
Send the address, what you are buying or building, and the date you are working to. We will reply within 60 minutes with a free quote, and there is no obligation.
Start a QuotePrefer to talk it over first? Call 01293 214444 or email enquiries@unda.co.uk. Every Woolwich report is signed off by a senior consultant. Our consultants are chartered, and Unda Consulting Limited is a CIWEM Business Partner. Further along the estuary, our Erith page covers the far end of the Thamesmead policy unit, and flood risk assessments by area lists every place we cover.