Durham County Council decides planning applications against Policy 35 (Water Management) of the County Durham Plan, adopted on 21 October 2020, and as lead local flood authority it checks the drainage too. Small schemes are caught as well as major ones: every new development has to show no net increase in surface water runoff for its lifetime and send rain to the ground first, with a combined sewer last; any culvert running through the site has to be opened up unless that is clearly impractical. Durham is also one of the seven councils behind the North East lead local flood authorities' standards of July 2020, which ask for greenfield runoff rates on brownfield land and two infiltration tests before approval.
This page sets out what Durham County Council requires on flood risk and drainage when it decides a planning application, and what our reports contain to meet each requirement. It covers Policies 35, 36 and 37 of the County Durham Plan and the council's online validation checklist. It then takes the drainage standards, the 2018 strategic flood risk assessment and the new plan now in preparation in turn. Reports for applications to Durham County Council come from Unda Consulting Limited, a CIWEM Business Partner, and our chartered consultants have prepared reports for applications to this council before. To talk a site through, call 01293 214444 or email enquiries@unda.co.uk.
Who handles flood risk and drainage on a County Durham application
County Durham has had a single unitary council since 1 April 2009, so the same authority registers the application, decides it and comments on its surface water. Darlington, Hartlepool and part of Stockton-on-Tees sit in the ceremonial county but are separate unitary councils with their own plans, so a site there is outside this page. Inside the county, the council's planning officers and its Drainage and Coastal Protection team work from the same Local Plan.
| Body | Role | What it decides or is consulted on |
|---|---|---|
| Durham County Council (planning) | Local planning authority for the whole county | Decides the application against County Durham Plan Policies 35, 36 and 37, any made neighbourhood plan and the NPPF; checks the submission against its validation checklist; applies the sequential test |
| Durham County Council (Drainage and Coastal Protection) | Lead local flood authority | Consulted on surface water for major development, and the plan's supporting text (paragraph 5.371) describes it as a consultee on surface water flood risk on all sites; reads the drainage against the SuDS Adoption Guide 2016 and the North East standards; consents works on ordinary watercourses; may adopt SuDS on request |
| Environment Agency (North East) | Statutory consultee | Consulted on development in Flood Zones 2 and 3 and on works in or within 8 metres of a main river such as the Wear or the Tees; issues permits for that work |
| Northumbrian Water | Water and sewerage company | Agrees connections and any discharge rate to a public sewer; the North East standards expect its pre-planning enquiry response with the submission |
| The Coal Authority | Consultee in the Coal Mining High Risk Area | A Coal Mining Risk Assessment is a validation item there; permission is needed before intrusive works into seams or mine entries |
| Internal drainage board | None | No board operates in the county; the 2018 SFRA's list of flood risk bodies (section 1.4) names none |
How the two roles divide is set out in our guide to the lead local flood authority; our note on local planning authorities and SuDS shows where they meet on an application.
Policies 35, 36 and 37: the County Durham Plan's water policies
The County Durham Plan 2016-2035 was adopted on 21 October 2020 after an examination in 2019 and 2020, and its Appendix B replaced all remaining saved policies of the seven former district local plans. Its water policies sit together in chapter 5. Policy 35 deals with flood risk, surface water and water quality; Policy 36 covers foul water, treatment works and flood defences; Policy 37 brings flood and erosion risk into decisions on the coast. The council's Review of the County Durham Plan of September 2025 found all three consistent with the national policy of that time and effective in decision-making.
| Policy | Title | What it requires | Your obligation | How Unda meets it | Source and date |
|---|---|---|---|---|---|
| Policy 35 | Water Management | No development in Flood Zone 3b unless water-compatible or essential infrastructure; the sequential test, and the exception test where needed, in Flood Zones 2 and 3a; a flood risk assessment showing the site and its access safe without raising risk elsewhere; no net increase in surface water runoff; greenfield rates on greenfield land, close to greenfield on brownfield, 50% betterment at minimum; an infiltration-first discharge order; SuDS with whole-life maintenance; de-culverting where practical; runoff quality controlled | Show the site is safe for its lifetime, that runoff will not rise, where the water goes and who maintains the SuDS | A flood risk assessment covering every source, a sequential test where one applies, and a drainage strategy that sets the rates, the discharge route and the maintenance plan against Policy 35 | County Durham Plan, 21 Oct 2020, pp. 175-176 |
| Policy 36 | Water Infrastructure | Foul water to the public sewer first, then a package treatment plant, then a septic tank to a soakaway; no non-mains drainage where public sewerage exists; new flood defences only as the most sustainable response with long-term maintenance | Show how foul water leaves the site and justify any non-mains option | A foul drainage strategy that works down the hierarchy, with the evidence the council's foul drainage assessment asks for | County Durham Plan, 21 Oct 2020, pp. 176-177 |
| Policy 37 | Durham Heritage Coast and Wider Coastal Zone | Proposals in or affecting the setting of the Heritage Coast or the wider Coastal Zone must not increase the risk from climate change, flooding, erosion or land instability | Show the scheme adds no flood or erosion risk on the coast | A flood risk assessment for tidal and surface water risk and a drainage strategy that keeps runoff off the cliffs and denes | County Durham Plan, 21 Oct 2020, p. 182 |
Requirements checked November 2026.
Policy 35 (Water Management): the flood risk tests
Policy 35 asks every proposal to consider its effect on flood risk on and off the site, allowing for climate change, and refuses development unless three conditions are met. In its words, development will not be permitted unless "in the functional floodplain (flood zone 3b), as identified in the Strategic FRA, it is water compatible or essential infrastructure", "in flood zones 2 and 3a it passes the Sequential Test, and if necessary the Exceptions Test, as required by national policy", and "it can be proven through a FRA that the development, including the access, will be safe, without increasing or exacerbating flood risk elsewhere" (County Durham Plan, page 175).
Footnote 124 sets the Flood Zone 1 triggers: "In flood zone 1 an FRA will only be required for sites over one hectare, where it has been identified as being within in a critical drainage area or where proposed development or a change of use to a more vulnerable class may be subject to other sources of flooding." National policy F4 now goes wider: in Flood Zone 1 it asks for an assessment on land "identified in a strategic flood risk assessment or the Flood Map for Planning as being at risk of flooding from any source, whether now or in the future", whatever the use. Where the footnote is narrower, an applicant should plan on the F4 trigger and the F5 sequential test; the section on national policy below explains why.
The safety test includes the access, so a house on dry ground reached through a flooded lane can still fail the policy. The 2018 SFRA's Flood Zone 3b also needs checking early, because where no detailed model exists the SFRA treats the whole of Flood Zone 3 as functional floodplain. Our flood risk assessment for a Policy 35 site maps each source against the SFRA, the Flood Map for Planning and the surface water maps. It tests the route in and out, then states the residual risk and how it is managed.
Policy 35 (Water Management): runoff, the discharge order and culverts
The surface water half of Policy 35 applies to all new development. Part (e) requires that "on all new development there is no net increase in surface water runoff for the lifetime of the development". Greenfield sites must not exceed, and where possible should reduce, greenfield runoff rates. Previously developed land must come as close to greenfield as practicable, and where that is shown to be unachievable "a betterment rate (which should be a minimum of 50% of the existing site run-off rate) will be agreed with the council". Runoff goes first to an infiltration or soakaway system, then to a watercourse, then a surface water sewer, with a combined sewer "the last resort once all other methods have been clearly explored and evidenced" (pages 175-176).
Major schemes must make water management "an intrinsic part of the overall development" and set land aside for it. Sites in an overland flow path shown in the SFRA, or in one of the 139 Surface Water Risk Areas in the Surface Water Management Plan of August 2011, need protection built in. Part (i) adds a culvert rule: "all new development with culverts running through the site must seek to de-culvert watercourses for flood risk management and environmental benefit, unless it can be clearly demonstrated that this is not practical." National policy F8 now asks for the same where possible. Our explainer on culverts covers what opening one involves.
Our drainage strategy for a County Durham site sets out the existing and proposed runoff rates and the infiltration result, which decides whether the first step of the order is open. It records any culvert and whether it can be opened, and attaches the maintenance plan part (h) asks for. Policy 35 also asks commercial, industrial and major residential schemes to control runoff quality during construction and for their lifetime, so the strategy includes treatment stages.
Policy 36 (Water Infrastructure): foul water and new defences
Policy 36 sets a three-step order for foul water: "connection to the public sewer", then a package sewage treatment plant, then a septic tank draining to a soakaway rather than a watercourse. It adds that "Applications involving the use of non-mains methods of drainage (including Septic Tanks/Cess Pits) will not be permitted in areas where public sewerage exists." The supporting text (paragraph 5.385) advises a foul drainage assessment as a minimum wherever a non-mains system is proposed. In the dales, where farmsteads and barns can lie well beyond the sewer network, the assessment has to show why each higher step is unavailable. The same policy allows new flood defences only where they are "the most sustainable response" to a threat and long-term maintenance can be shown.
Policy 37 (Durham Heritage Coast and Wider Coastal Zone): sites on the coast
Policy 37 covers more than 17 kilometres of coast from Ryhope Dene to Crimdon Dene. Development in the Heritage Coast or the wider Coastal Zone, or affecting their setting, must "not increase the risk from climate change, flooding, erosion or land instability" (page 182). The plan records that the Shoreline Management Plan finds no significant risk of coastal change along the Durham coast except at Red Acre Cliffs near Seaham. On a coastal site we provide the flood risk assessment and a drainage strategy that keeps runoff away from cliff tops and the denes; a coastal erosion study, where one is needed, is specialist work we do not prepare.
The new County Durham Plan: what changes and when
Durham County Council gave notice on 25 March 2026 that it would prepare a new County Durham Plan under the 2026 plan-making regulations, and ran a scoping consultation from 22 June to 17 August 2026. Its Gateway 1 Assessment of October 2026 records that the 30-month preparation period began on 30 October 2026. The revised timetable has a consultation on proposed plan content and evidence from 3 May to 14 June 2027, the proposed plan from 10 January to 6 March 2028, submission on 1 July 2028 and adoption on 1 May 2029, subject to the pre-election period. The Development Plan page still links the earlier June 2026 timetable, which had adoption in March 2029. No draft flood or drainage policies have been published, so Policies 35, 36 and 37 remain the policies applied.
Is there a culvert under your County Durham site?
Policy 35 expects it opened up unless that is clearly impractical, and the answer shapes the layout. Send the site plan and a line on the scheme, and we will say what the policy asks for. Get a no-obligation, free quote. One of our experienced flood risk consultants will get back to you within 60 minutes, with a fixed quote within the hour. Call 01293 214444 or email enquiries@unda.co.uk.
Start a QuoteDrainage standards Durham's flood team applies
Two documents set the drainage numbers. The council's own Sustainable Drainage Systems Adoption Guide 2016 (version 1.1, October 2016) is linked from its SuDS page and from Policy 35, which applies it "or any subsequent iterations". Durham is also one of the seven councils behind the North-East Lead Local Flood Authorities Sustainable Drainage Local Standards, final issue July 2020, alongside Gateshead, Newcastle, Northumberland, North Tyneside, South Tyneside and Sunderland. Its own SuDS page links only the 2016 guide, so a strategy here is written to satisfy both.
| Requirement | What the County Durham documents say |
|---|---|
| Discharge rate | Greenfield (QBar) rate, and as close to greenfield as practicable on previously developed land with a betterment rate agreed otherwise (Adoption Guide Requirement 11; Policy 35(e)); the North East standards ask for equivalent greenfield runoff rates on all sites, brownfield included, limited only by the smallest flow control Northumbrian Water accepts (LS1) (NE standards, July 2020) |
| Discharge order | Ground first, then a surface water body, then a sewer only where both are shown to be impractical, with infiltration tests and levels as the evidence (Adoption Guide Requirement 10) |
| Climate change | A climate change statement with every SuDS proposal (Adoption Guide Requirement 6); 40% on the 100-year event in the North East standards (LS9), which was the upper end allowance when they were written; current figures by management catchment are in the Environment Agency's climate change allowances, last updated 27 May 2022 |
| Urban creep | Up to 10% on residential schemes, none on commercial (LS5) |
| Storms and freeboard | Storms from 15 to 360 minutes as a minimum (LS8); 300 mm freeboard or 300 mm between the 1 in 100 year plus climate change water level and finished floor level (LS10) |
| Infiltration testing | At least two representative six-hour falling head tests to BRE Digest 365 before planning approval, except where ground contamination, proven ground stability concerns such as those in a coal mining report, or groundwater within 1 m of the surface rule testing out (LS19) |
| Interception and treatment | 5 mm of rainfall kept on site by source control (LS20); treatment assessed with the CIRIA SuDS Manual simple index method (LS22) |
| Modelling | 1D or 2D modelling of an ordinary watercourse in or beside the site may be required (LS11); overland flow modelling where flow routes cross the site (LS12) |
| Adoption | The council may adopt SuDS on major sites that meet its criteria, normally once the site is substantially complete, with adoption, legal and survey fees (Adoption Guide sections 5.12 and 8.3) |
Neither document reflects the National Standards for Sustainable Drainage Systems published in June 2025, and the plan's own reference (footnote 130) is to the 2015 non-statutory standards; no council statement on the 2025 standards was found. NPPF policy F8 now asks SuDS to follow the National Standards and, on major development, to take account of the lead local flood authority's advice. We write a County Durham strategy to the National Standards and check it against the local figures above; our summary of the 2025 National Standards explains what changed.
The coalfield adds a step. The plan (paragraph 5.375) expects groundwater to rise in parts of the county as mine water pumping changes. LS19 also lets proven ground stability concerns rule infiltration out, so the Coal Mining Report and the infiltration result are read together before a soakaway is relied on. Our ground conditions and soakaway map shows the mapped geology before a trial pit is dug. The BRE 365 infiltration rate calculator turns a trial pit result into a rate, and the urban creep and climate change calculator applies the LS5 and climate uplifts. Our article on when infiltration testing is needed covers the test itself.
Culverting, de-culverting or any work that affects flow in an ordinary watercourse needs the council's prior written consent, and the plan (paragraph 5.390) says consent to culvert will not normally be given except as a means of access. Work in or within 8 metres of a main river needs a permit from the Environment Agency. Our explainers on ordinary watercourse consent and main rivers and ordinary watercourses set out who regulates which.
When a County Durham application needs each report
Three sources decide what an application here needs. Policy 35 and national policy F4 to F6 set the flood risk assessment and the tests; the validation checklist sets what must arrive with the application; the drainage standards set the surface water detail. Check the flood zone and surface water risk on our flood risk map first, then read across the table.
| Trigger | Flood risk assessment | Sequential and exception tests | Drainage submission |
|---|---|---|---|
| Development in Flood Zone 3b (functional floodplain) | Required (F4; Policy 35; validation item 35) | Policy 35(a) allows only water-compatible uses and essential infrastructure; essential infrastructure needs the exception test under Annex F table 3 | As for the scheme size |
| Development in Flood Zone 2 or 3a, including listed changes of use | Required (F4; Policy 35; validation item 35) | Sequential test unless F5 exempts the scheme; exception test only where Annex F table 3 calls for one | Drainage details on major schemes (validation item 35); SuDS under Policy 35(h) on smaller ones |
| Extension to a house in Flood Zone 2 or 3 | Required by F4; the checklist asks for one for operational development under 1 ha in those zones | Not required: F5 exempts householder development, and no exception test follows | No net increase in runoff (Policy 35(e)); a soakaway where the ground allows |
| Flood Zone 1 land of a hectare or more, whatever the use | Required (F4; validation item 35; Policy 35 footnote 124 says over one hectare) | No exception test in Flood Zone 1; a sequential test only if some of the land is at risk from surface water, groundwater or another source | Surface water drainage strategy (the site is major development) |
| Flood Zone 1 land in a critical drainage area, or shown at risk from any source by the SFRA or the Flood Map for Planning | Required by F4(2)(b) and (c) and by footnote 124 for critical drainage areas, though the checklist does not list it | Sequential test unless F5(2)(b) applies, for example where the site is at risk of surface water flooding only and occupiers "would remain safe from current and future surface water flood risk for the lifetime of the development without increasing flood risk elsewhere" | As for the scheme size; protection where the site sits in a Surface Water Risk Area (Policy 35(g)) |
| Major development (10 or more homes, 0.5 ha for housing, 1,000 square metres of floorspace or a 1 ha site) | Where a trigger above applies | As above | Outline drainage strategy statement or full surface water drainage strategy statement, with infiltration testing, levels and the Environment Agency and CIRIA SuDS strategy template (validation item 35); the lead local flood authority is consulted |
| Culvert or watercourse on or beside the site | As for the scheme | Not triggered by this alone | De-culverting where practical (Policy 35(i)); ordinary watercourse consent from the council, or an Environment Agency permit on a main river |
| Foul drainage with no public sewer connection | Not triggered by this alone | Not applicable | Foul drainage assessment (paragraph 5.385); not permitted where public sewerage exists (Policy 36) |
| Site in the Coal Mining High Risk Area | Not triggered by this alone | Not applicable | Coal Mining Risk Assessment (validation item 13, householder and some other types exempt), read with the infiltration evidence |
Two sets of national exemptions apply to the rows above. F5 exempts householder development, non-residential extensions under 250 square metres and changes of use, except changes to a caravan, camping or chalet site or a mobile or park home site, which still need the test. It also exempts a site where an assessment shows that no built development, access or escape route would sit on land at risk from any source, now and in the future. The same goes where the risk is from surface water only and the layout keeps occupiers safe for the lifetime of the development without increasing flood risk elsewhere. Our guide to the sequential and exception tests explains both, and the surface water exemption has its own explainer.
What Durham's validation checklist asks for on water
The council's planning validation requirements are an online checklist of national and local items. The page carries no date, but it cites the policy letters of the current NPPF, so it has been revised since August 2026. The council says an application without the required information will be declared invalid and will not progress until it arrives. Three items bear on flood risk and drainage.
- Item 35, flood risk assessment. Required for all development on sites of 1 hectare or more and for operational development under 1 hectare in Flood Zone 2 or 3. It is also needed for changes of use that create a highly or more vulnerable use in Flood Zone 2 or 3 or a less vulnerable use from a water-compatible one in Flood Zone 3, and for small non-residential extensions that culvert or control a watercourse or sit within 20 metres of the top of a main river bank. The assessment covers all sources, climate change and safe access, and includes SuDS details where the drainage threshold applies.
- Item 35, surface and foul water drainage. Required for 10 or more homes or 0.5 hectares, and for 1,000 square metres of non-residential floorspace or 1 hectare. Outline applications need an outline drainage strategy statement with a preliminary SuDS layout, outline calculations, infiltration testing and a topographical survey. Full applications need a surface water drainage strategy statement with the drainage layout, a full hydraulic model, evidence of agreement to the outfall and a maintenance schedule.
- Item 13, Coal Mining Risk Assessment. Required within the Coal Mining High Risk Area, with reserved matters, householder schemes, changes of use and some other types exempt, following Appendix C of the plan.
Item 35 lists only the 1 hectare trigger in Flood Zone 1. Policy 35 also covers critical drainage areas and other sources for more vulnerable uses, and F4 covers any land at risk from any source. An application can pass validation and still draw a request for an assessment from the case officer. Our article on applications invalidated over flood risk and drainage covers how that happens. Non-residential major schemes also need a sustainability statement showing how they reach BREEAM "very good" (item 36). A made neighbourhood plan for the parish forms part of the development plan, so the council's neighbourhood planning page is worth checking for local flood clauses.
The 2018 County Durham SFRA and its replacement
- Level 1 SFRA, April 2018. The Level 1 Strategic Flood Risk Assessment by AECOM (final report, revision B, April 2018) covers river, sea, surface water, groundwater, sewer and reservoir flooding across the county, with an interactive map on the council's SFRA page. Its 2019 sequential test of the plan sites fed the allocations, so an allocated site can rely on it under F5(2)(a).
- How it draws Flood Zone 3b. The SFRA treats land within the 5% (1 in 20) annual flood envelope, or designed to flood in an extreme event, as functional floodplain, and where no detailed model exists it assumes Flood Zone 3b equals Flood Zone 3a. It notes that 3b is often close to Flood Zone 2 in the narrow Wear valley between Willington and Durham, minimal in Durham city behind its defences, and extensive on the upper Skerne east of Newton Aycliffe. Annex F of the Framework now normally starts from a 3.3% annual probability, so an assessment says which definition it relies on; our note on Flood Zone 3b explains the change.
- Groundwater. The SFRA links groundwater susceptibility to thin glacial till in the west and along the river corridors. It records repeated groundwater flooding of low ground at Bishop Middleham and West Auckland, and notes groundwater at or close to the surface around Newton Aycliffe, and above it a short distance to the south and west, where infiltration may not work.
- The update under way. The council has commissioned Jacobs to review the 2018 SFRA and water cycle study for the new plan (Contracts Finder award notice, published 27 November 2025; contract to 31 August 2027). Until it is published the 2018 study is the evidence the council uses.
The plan itself (paragraph 5.373) tells applicants to allow for Environment Agency flood map changes since the SFRA and for current climate change allowances. A site-specific assessment therefore reads the 2018 maps beside the current Flood Map for Planning and says where they differ. Our guide to strategic flood risk assessments explains how councils build these studies.
NPPF Chapter 18 and the 2020 County Durham Plan
National flood policy is in Chapter 18 of the National Planning Policy Framework, published on 17 August 2026. Policy F4 says when a site-specific assessment is needed, F5 and F6 set the sequential and exception tests, F7 asks that development is safe for its lifetime with residual risk managed, and F8 covers sustainable drainage and watercourses. Planning practice guidance on flood risk and coastal change (last updated 17 September 2025) adds the method, and our summary of the August 2026 NPPF changes covers what moved.
Policy 35 and Chapter 18 mostly agree, and in places the plan asks for more: no net increase in runoff on every development, the 50% minimum betterment on brownfield land and an infiltration-first order. The Framework goes further in two places. F4 asks for an assessment on any Flood Zone 1 land at risk from any source, and F5 applies the sequential test to land at risk from any form of flooding, while Policy 35 names Flood Zones 2 and 3a. Annex A of the Framework gives a plan policy, or part of one, that is materially inconsistent with the Framework very limited weight unless it was examined and adopted against it. In practice an applicant should expect the F4 assessment and the F5 test where Policy 35's wording is narrower, and confirm the scope with the case officer. F8's call to remove culverts where possible matches Policy 35(i). Our NPPF flood risk guidance page explains the national rules in more depth.
Rivers, mine water and surface water across County Durham
The SFRA puts the county's greatest river flood risk on the low land beside the Wear, from Wearhead down to Chester-le-Street. The council's Preliminary Flood Risk Assessment of May 2016 records riverfront parts of Durham city centre flooding from the Wear on five occasions in the ten years before it, most recently in July 2009. That month about 50 mm of rain fell in around 40 minutes on 2 July, and more than 100 mm in 24 hours on 17 July. Our River Wear page follows the river, the River Tees page covers Teesdale and Barnard Castle, and the live river levels map shows the gauges.
For Durham city's riverside, defences and DH1 streets, see our Durham page. The Chester-le-Street page covers the Chester Burn culvert and the town's flood scheme, and the Lanchester page covers the Smallhope Burn. For the county's flood history and flood map as a whole, our page on flood risk assessment in County Durham brings them together. Bishop Auckland, Consett, Stanley, Seaham, Peterlee, Newton Aycliffe, Spennymoor and Barnard Castle have no page of their own yet.
The plan (paragraph 5.377) describes the county's flood risk as mainly from rivers, with surface water and groundwater events increasing. The 2011 Surface Water Management Plan found most of its 139 risk areas in the east of the county, in and around the urban areas, and Policy 35(g) asks for protection on sites inside them. Beneath the east lies the Magnesian Limestone principal aquifer, a drinking water source the plan protects, and in the former coalfield mine water and rising groundwater bear on which drainage will work. Our groundwater flood risk explainer covers how that is assessed, and the council's flood risk management page lists its schemes and plans.
Reports for a Durham County Council application
Three separate reports answer Policy 35. The flood risk assessment deals with part (c), the safety of the site and its access. The sequential test deals with part (b): whether a lower-risk site is reasonably available. The drainage strategy deals with parts (d) to (i), covering the runoff, the discharge order, the SuDS and any culvert. A single application to Durham County Council may need any combination of the three.
- Riverside sites under Policy 35. Plots beside the Wear, Tees, Browney, Gaunless and Skerne need a flood risk assessment for planning that answers Policy 35(c) on access and residual risk as well as the national tests.
- Every source the council asks about. Policy 35 counts surface water, groundwater and sewers alongside rivers, so a flood risk assessment for a County Durham site maps each one against the 2018 SFRA and the 2011 risk areas.
- Before buying. Riverfront property in Durham city has flooded from the Wear, and for a home or premises there or in a Surface Water Risk Area a flood risk survey for property purchase sets out the risk to the building before exchange.
- Unallocated land in Flood Zone 2 or 3. Policy 35(b) and F5 bring in sequential and exception test work: a sequential test over a search area no wider than the anticipated catchment of the scheme, and an exception test only where Annex F table 3 requires one.
- The Policy 35 runoff rules. No net increase in runoff, greenfield rates and the infiltration-first order are met through a drainage strategy that works down the discharge order and records why each step is or is not available.
- Major schemes the flood team reviews. Validation item 35 asks for a surface water drainage strategy statement on full applications, checked against the Adoption Guide, the North East standards and the infiltration tests.
- Conditions after approval. Where maintenance plans, construction runoff or final drainage details are left to conditions, the discharge of drainage conditions gathers what the council's drainage officers ask for.
- Farmsteads and barns off the sewer. Policy 36 bars non-mains drainage where a public sewer is available and paragraph 5.385 asks for a foul drainage assessment, which a foul drainage strategy supports.
- Mine water and rising groundwater. The SFRA records groundwater flooding at Bishop Middleham and West Auckland and the plan expects levels to rise as pumping changes, so a groundwater assessment settles whether infiltration can work.
- Separating Flood Zone 3a from 3b. The SFRA asks Flood Zone 3 applications for detailed modelling to separate 3a from 3b, and LS11 may ask for an ordinary watercourse model; flood modelling supplies the levels.
- Safe access on the floodplain. Policy 35 counts the access in its safety test, so a flood warning and evacuation plan sets out the route and the warning for riverside occupiers.
- Non-residential major schemes. Validation item 36 asks for a BREEAM "very good" route on non-residential major development, and a BREEAM flood risk assessment covers the flood risk credit.
- Solar and other energy schemes. The checklist has its own items for large solar farms, and a renewable energy flood risk assessment covers runoff from arrays and access tracks on rural land.
Other councils' requirements are on our local authorities index; the uplifts a County Durham drainage strategy applies are explained in our guide to the climate change allowances.
Questions on Durham County Council's flood and drainage rules
What does County Durham Plan Policy 35 require?
Policy 35 (Water Management) allows only water-compatible uses and essential infrastructure in Flood Zone 3b, applies the sequential test and, where needed, the exception test in Flood Zones 2 and 3a, and asks for a flood risk assessment showing the site and its access safe. For surface water it requires no net increase in runoff on all new development, greenfield rates on greenfield land, at least 50% betterment on brownfield land where greenfield cannot be reached, an infiltration-first discharge order, SuDS with whole-life maintenance and de-culverting where practical.
Does a house extension in Flood Zone 2 in County Durham need a flood risk assessment?
Yes. National policy F4 asks for one with any development in Flood Zone 2 or 3, and the council's validation checklist asks for one for operational development under 1 hectare in those zones. Householder schemes are exempt from the sequential test under F5, so the assessment concentrates on the risk to the extension and its effect on neighbours.
Can a householder prepare their own flood risk assessment for Durham County Council?
For a small householder extension the Environment Agency's standing advice and template are written for applicants to use. For new homes, a change of use in a flood zone or anything that engages Policy 35's runoff rules, the assessment has to cover all sources, climate change, safe access and residual risk, which goes beyond the template. Call 01293 214444 to talk a site through.
Does Durham County Council use the North East SuDS standards?
Durham is one of the seven councils that issued the North-East Lead Local Flood Authorities Sustainable Drainage Local Standards in July 2020, alongside its own SuDS Adoption Guide of 2016. The North East standards ask for greenfield runoff rates on all sites, brownfield included, and two six-hour infiltration tests before planning approval.
Will a new County Durham Plan replace Policy 35?
Not yet. The council began a new plan under the 2026 regulations. Its Gateway 1 Assessment of October 2026 has a consultation on proposed content and evidence from 3 May to 14 June 2027, submission on 1 July 2028 and adoption on 1 May 2029. No draft flood or drainage policies have been published, so Policies 35, 36 and 37 still apply.
Is there a culvert rule in County Durham?
Policy 35(i) says all new development with culverts running through the site must seek to de-culvert them unless it can be clearly shown that this is not practical. Any culverting, de-culverting or work affecting flow in an ordinary watercourse also needs the council's written consent, and the plan says consent to culvert will not normally be given except as a means of access.
Two six-hour infiltration tests before approval?
In County Durham the soakaway question decides the whole drainage route, and the North East standards want the tests done before the decision. Get a no-obligation, free quote. One of our experienced flood risk consultants will get back to you within 60 minutes. Call 01293 214444 or email enquiries@unda.co.uk.