Flood Risk & Drainage Requirements for Lambeth Council

Contact Us
A line drawing of the UK map with three points linked to icons: a factory, a house, and a river. A warning symbol and a person in a hard hat holding a clipboard appear on the right side.

Lambeth Council decides flood risk and drainage on Policies EN5 (Flood risk) and EN6 (Sustainable drainage systems and water management) of the Lambeth Local Plan 2020-2035, adopted on 22 September 2021. Both are read with Annex 4, the plan's zone-by-zone flood table. For housing, Annex 4 sets a lower bar than national policy in Flood Zone 1: a site over 0.5 hectares or with 10 or more homes needs a flood risk assessment, and so do commercial sites over 1 hectare or 1,000 m² and smaller sites with a critical drainage problem. It also rules out basement bedrooms wherever the land is susceptible to flooding, and the plan counts high surface water risk as susceptible.

Lambeth Council is both the local planning authority and the Lead Local Flood Authority. One council decides the application and reviews the surface water drainage behind it. The tidal Thames runs along its northern edge from Waterloo to Vauxhall, the River Graveney crosses the far south in the Streatham and Norbury area, and the council's own flooding page states that "there are no ordinary watercourses in Lambeth". Most of what an applicant has to prove here concerns the defended tidal floodplain, the basement rules, and surface water and sewers across the rest of the borough.

Annex 4 of the Lambeth Local Plan: what each flood zone triggers

Policy EN5 part A(iv) permits development in Flood Zones 1, 2, 3a and 3b "subject to meeting the criteria set out in Annex 4". The annex is a table with one row per flood zone and columns for restrictions, the sequential test, the exception test and the flood risk assessment, and it carries most of the borough's flood rules. The council's December 2024 Local List repeats its Flood Zone 1 thresholds. The table below sets out when each report is asked for, with the national position from Chapter 18 of the August 2026 National Planning Policy Framework where it differs.

TriggerFlood risk assessmentSequential and Exception TestsDrainage and other documents
Any development in Flood Zone 2, 3a or 3b, including householder extensions and changes of useYes (EN5 C; Annex 4; Local List item 34; NPPF Policy F4)Annex 4 marks the Sequential Test "Required for all developments" in these zones. NPPF Policy F5 lists exemptions for householder development, non-residential extensions with a footprint under 250 m² and changes of use (other than to a caravan, camping or chalet site, or a mobile home or park home site): confirm with the case officer how the council applies the annex to those. Exception Test for highly vulnerable uses in Zone 2, more vulnerable uses and essential infrastructure in Zone 3a, and essential infrastructure in Zone 3b (Annex 4; NPPF Policy F6)Floor levels, safe access and the basement limits in Annex 4; SuDS strategy where the scheme is major or the site is at risk of flooding (Local List item 73)
Flood Zone 1: residential site over 0.5 ha or with 10 or more dwellings; commercial site over 1 ha or with more than 1,000 m² of floorspaceYes (Annex 4; Local List item 34)No Exception Test in Flood Zone 1. A Sequential Test only where the site is at risk from another source (see below)SuDS strategy reaching a greenfield runoff rate (Local List item 73); the documents on the council's sustainable drainage page for major applications
Flood Zone 1 site of one hectare or more of any other kindYes (NPPF Policy F4)No Exception Test in Flood Zone 1Drainage strategy
Flood Zone 1 site under 1 ha with a critical drainage problem, or land inside one of the 11 Critical Drainage Areas in the 2021 Surface Water Management PlanYes (Annex 4; Local List item 34; NPPF Policy F4)Annex 4 applies the Sequential Test in Flood Zone 1 "within a critical drainage area". No Exception Test in Flood Zone 1Greenfield runoff and SuDS (Annex 4, Flood Zone 1 row)
Flood Zone 1 land shown at risk from surface water, groundwater or sewers in the SFRA, the Local Flood Risk Management Strategy or the Flood Map for PlanningYes (Local List item 34; NPPF Policy F4)The Local List asks for sequential testing on sites at high or medium surface water risk. NPPF Policy F5 applies the test on land at risk from any source, unless the assessment shows no built development (including access or escape routes, land raising or other potentially vulnerable elements) on land at risk from any source, now and in the future, or that, where the risk is from surface water only, occupiers stay safe for the lifetime of the development without increasing flood risk elsewhereSurface water mitigation in the layout
New basement or basement extension, in any zoneA Basement Impact Assessment every time (Local List item 14; Q27); a flood risk assessment wherever a trigger above appliesException Test only where the use and zone require it. Annex 4: no self-contained basement units or basement bedrooms in the tidal residual risk zone of Flood Zone 3a or where at risk from other sources; none at all in Flood Zone 3bPositive pumped device against sewer flooding (Q27 E(ii)); escape to a floor above the flood level
Major development anywhere (the DMPO 2015 definition: 10 or more homes, 0.5 ha where the number of homes is not known, 1,000 m² of floorspace, or a site of 1 ha)Where any trigger above appliesAs aboveSuDS strategy (Local List item 73); foul water and water supply capacity assessment (Local List item 35); the council consulted as Lead Local Flood Authority
Site beside the Thames or River Graveney defencesYes (Flood Zone 3)As the first rowDefence walls maintained, repaired or improved where needed (EN5 G); a 16 m set-back from the rear of the Thames defences and 8 m on the Graveney sought where the site allows (para 9.45)
Site allocated in the Site Allocations Development Plan Document (October 2026)Yes (each site policy)NPPF Policy F5 removes the Sequential Test for allocations tested at plan stage, and Policy F6 the Exception Test where it was applied at plan stage, unless the flood risk has increased significantly or the scheme now brings a more vulnerable use. Site 7's policy still asks for the Exception Test if NHS facilities are re-provided on siteBreach levels verified on site; greenfield QBar given in the site policy

The Local List points applicants to "Annex 5 of the Lambeth Local Plan" for the sequential test, and the 2023 basements guidance makes the same slip: the flood zone table is Annex 4 (Annex 5 lists open spaces). Read Annex 4 wherever either document cites Annex 5.

Lambeth Council, the Environment Agency and Thames Water: who decides each part

No county council and no drainage board sit between Lambeth and the applicant: the decision rests with the borough, advised by the Environment Agency and Thames Water.

BodyRoleWhat it decides or is consulted on
Lambeth CouncilLocal planning authorityDecides the application against EN5, EN6, Q27, Annex 4, the Site Allocations DPD, the London Plan and Chapter 18 of the NPPF; validates it against the Local Information Requirements (December 2024)
Lambeth CouncilLead Local Flood AuthorityComments on surface water flood risk and runoff management (its flooding page); consulted on major development (Local Plan para 9.51); holds the Surface Water Management Plan (May 2021) and the Local Flood Risk Management Strategy (October 2018 revision). No ordinary watercourses to consent in the borough
Environment AgencyStatutory consulteeTidal Thames and River Graveney flood risk; the 2017 Thames tidal breach model and site-specific breach data; works on or near a main river or flood defence, which can need an environmental permit from the Environment Agency
Thames WaterSewerage undertakerPublic sewers, sewer flooding and network capacity (EN5 E, EN6 vii, Local List item 35)
Mayor of LondonStrategic planning authorityReferable applications; London Plan 2021 Policies SI 12 and SI 13

Highway drainage is split: flooding on the council's own roads goes to Lambeth, and on red routes to Transport for London. Our explainers cover the local planning authority's flood and SuDS role and the Environment Agency's part in planning.

Policies EN5, EN6 and Q27: Lambeth's flood, drainage and basement policies

Applications are read against the Lambeth Local Plan 2021 and the London Plan 2021. The council adopted its plan on 22 September 2021, after the Inspector found it sound subject to main modifications. The 2021 plan replaced the Lambeth Local Plan 2015, whose Policies EN5 (Flood risk) and EN6 (Sustainable drainage systems and water management) had the same codes and titles. An officer report from before 2021 that cites EN5 is quoting the earlier wording. The Site Allocations Development Plan Document, adopted on 14 October 2026, adds flood rules for 13 named sites.

PolicyTitleWhat it requiresYour obligationHow Unda meets itSource and date
Policy EN5Flood riskSequential, risk-based location; Annex 4 criteria by zone; FRA for major development in Flood Zone 1, all development in Zones 2, 3a and 3b and sites at risk from other sources; every source assessed; safe for its lifetime; no basement bedrooms where susceptible to flooding; defence walls maintainedA proportionate FRA covering all seven sources EN5 D lists, with climate changeA flood risk assessment that works through Annex 4 for the zone, the 2017 breach model and the surface water mappingLambeth Local Plan 2020-2035, adopted 22 September 2021
Policy EN6Sustainable drainage systems and water managementNet decrease in the volume and rate of runoff through SuDS and the London Plan drainage hierarchy; compensatory flood storage; flow routes kept; water and sewer capacity shownA drainage strategy with a SuDS Management Plan (para 9.52)A drainage strategy that tests greenfield runoff first and shows the net decrease in rate and volumeLambeth Local Plan 2020-2035, adopted 22 September 2021
Policy Q27Basement developmentNo unacceptable impact on groundwater, slope stability or surface flow and flooding; a positive pumped device; one storey under homes; generally 70% of the rear garden kept free; Stage 1 Basement Impact AssessmentA screening Basement Impact Assessment, with flooding coveredThe flood and drainage evidence for the assessment: Annex 4 basement limits, surface water and groundwaterLambeth Local Plan 2020-2035, adopted 22 September 2021
London Plan Policy SI 12Flood risk managementFlood risk minimised and mitigated and residual risk addressed; set back from defences; support for Thames Estuary 2100A residual risk case for sites behind the Thames wallsBreach depths and hazard carried into the assessmentLondon Plan 2021, March 2021
London Plan Policy SI 13Sustainable drainageAim for greenfield runoff, manage water close to its source, green features before grey, six-step hierarchyEvidence for each step of the hierarchy that is passed overA drainage strategy that takes the hierarchy in orderLondon Plan 2021, March 2021
Draft London Plan Policy GHR5Flood risk and drainage (draft, consulted on until 15 October 2026)Runoff no higher than today; a referable scheme aims for greenfield QBAR or 3 l/s/ha, if that is higherNot yet adopted; its weight rises as the draft moves to examinationFor a referable scheme we report the draft rate alongside the SI 13 positionDraft London Plan 2026 (consultation 16 July to 15 October 2026)

Requirements checked November 2026.

Policy EN5 (Flood risk): the sequential approach and Annex 4

Policy EN5 asks every application to avoid flood risk where it can and to put uses in the lowest-risk parts of Lambeth and of the site. Annex 4 then sets the limit for each zone. Part A(ii) applies the Sequential Test "in accordance with the NPPF, taking the vulnerability of the proposed uses into account, as set out in the Lambeth Strategic Flood Risk Assessment", and part A(v) asks schemes to take account of the Thames Estuary 2100 Plan. Part B goes further than avoidance: all development in Zones 2, 3a and 3b, or at risk from other sources, "should contribute positively to actively reducing flood risk through avoidance, reduction, management and mitigation."

In Flood Zone 3a, Annex 4 allows water compatible, less vulnerable and more vulnerable uses, and refuses highly vulnerable ones. For more vulnerable development, "finished floor land/or threshold levels should be set at least 300mm above the 1 in 100-year + climate change fluvial flood level" where the risk is from the Graveney, and floors go above the 1 in 200-year tidal level in areas of tidal residual risk. Flood hazard on access routes "should be no greater than very low hazard" as the SFRA defines it, and where safe access cannot be achieved an emergency plan may inform the council's decision.

Policy EN5 (Flood risk) parts C to E: what an assessment for Lambeth must cover

Part C sets the triggers: "A Flood Risk Assessment (FRA) will be required for major development proposals within Flood Zone 1, all development within Flood Zones 2, 3a and 3b, or where the development may be subject to other sources of flooding." Part D lists the sources the assessment must deal with: "fluvial, tidal, surface water run-off, groundwater, ordinary watercourse, sewer (separate or combined) and reservoir." Part E asks for the development to be safe for its lifetime and for sewer flooding measures to be discussed with Thames Water.

Two lines of supporting text shape the work. Paragraph 9.40 recommends pre-application discussion to confirm the flood zone. Paragraph 9.41 says the SFRA's breach models "are for guidance only and they should be verified by site-specific breach models to determine more accurate flood zones." How we meet parts C to E: our assessment states the Annex 4 row the site falls in and takes breach depth and hazard for the site from the Environment Agency's 2017 Thames tidal breach model. It covers every source part D lists, and sets floor and threshold levels against the tidal or fluvial water level that applies.

Policy EN5 (Flood risk) part F: basements where land is susceptible to flooding

Part F governs how a basement may be used: "The use of basement space for bedrooms and non-residential uses where flooding could threaten the safety of people will not be permitted in areas susceptible to flooding (including but not limited to areas within current modelled breach flood extent and surface water modelling)." Paragraph 9.44 widens "susceptible" to include "areas at high risk of surface water flooding" on the Environment Agency's long-term flood risk map. It lists nurseries, daycare centres and hospital beds alongside bedrooms, and asks for positively pumped devices and non-return valves against sewer flooding.

  • Flood Zone 2. No self-contained basement units or basement bedrooms without mitigation in line with Environment Agency guidance; free and open escape to a floor above the design flood level; resilient and resistant construction (Annex 4).
  • Flood Zone 3a. No self-contained basements or basement bedrooms in the tidal residual risk zone or where at risk from other sources; escape routes and raised thresholds above the 1 in 200-year tidal level, or the 1 in 100-year plus climate change level where the risk is fluvial (Annex 4).
  • Flood Zone 3b. No basements, basement extensions or conversions to a higher vulnerability or to self-contained units (Annex 4).
  • Any zone. Surface water, groundwater and sewer flooding considered for every basement, with raised thresholds and surface water storage as possible mitigation (Annex 4, Flood Zone 1 row).

How we meet part F: we check the basement footprint against the breach extent and the surface water map, state which Annex 4 row applies, and set out the escape route, thresholds and pumped protection the council asks for.

Policy EN5 (Flood risk) part G: the Thames and Graveney defences

Part G applies beside the River Thames and River Graveney: "maintenance, remediation and improvements to the flood defence walls will be required where necessary", and development next to defences and culverts must not undermine their structural integrity, operation or future maintenance. Paragraph 9.45 asks Thames-side schemes to "maximise opportunities to achieve a 16m setback from the rear of the flood defences" and Graveney schemes an 8 m set-back from the watercourse, defences and culverts. The Environment Agency's Thames Estuary 2100 page for the Wandsworth to Deptford policy unit expects councils to plan their riverside by 2030 and defence owners to raise defences where required by 2050. A riverside layout has to leave room for that work. How we meet part G: the assessment records the defence line, its owner and condition, the set-back achieved, and any reason a full set-back cannot be met, for the Environment Agency to consider.

Policy EN6 (Sustainable drainage systems and water management): a net decrease in runoff

Policy EN6 part (iv) asks development to "demonstrate that there will be a net decrease in both the volume and rate of run-off leaving the site" through SuDS in line with the London Plan drainage hierarchy. The test applies to every scheme the policy reaches, major or minor, and it covers volume as well as rate. The supporting text sets the target: "Development should aim to achieve greenfield run-off rates, although it is recognised that this is not always possible" (para 9.48), with brownfield sites to reduce rate and volume "to the standards set within the London Plan" (para 9.49).

Part (ii) asks for compensatory storage where flood storage is lost, and part (iii) protects flow routes across the site. Part (vii) asks for proof that water supply and sewerage have "adequate capacity both on and off-site", with phasing conditions where they do not. Paragraph 9.52 adds that "Developers must demonstrate the maintenance and long-term management of SuDS through a SuDS Management Plan" submitted with the drainage strategy. How we meet EN6: our drainage strategy calculates existing and proposed runoff, shows the net decrease in both rate and volume, works down the hierarchy, and includes the SuDS Management Plan.

Policy Q27 (Basement development): the Basement Impact Assessment

Policy Q27 supports basements where applicants can show no unacceptable impact on groundwater flow, slope stability and "surface flow and flooding", among other matters. It expects basement accommodation to "include a positive pumped device (or equivalent) to mitigate against the risk of sewer flooding", limits residential basements to one storey, and asks for a Stage 1 (Screening) Basement Impact Assessment with every proposal. The council's Lambeth Design Guide SPD Part 5: Basements, adopted on 8 August 2023, adds that "Fitting only a 'non return valve' is unacceptable" and asks basement schemes to manage runoff "as close as reasonably practicable to the greenfield condition" on previously developed sites. How we meet Q27: we prepare the flood, surface water and groundwater sections of the screening assessment, with the Annex 4 position for the basement, and our groundwater assessments where the screening needs more.

London Plan Policy SI 12 (Flood risk management): residual risk behind the walls

Policy SI 12 of the London Plan 2021 asks that "flood risk is minimised and mitigated, and that residual risk is addressed", and that schemes next to defences protect their integrity and allow access for maintenance and upgrading. In Lambeth the residual risk is a breach or overtopping of the Thames walls, which is why the council's site policies ask for breach levels verified on site. Our explainer on residual flood risk covers what that means for a design.

London Plan Policy SI 13 (Sustainable drainage): the hierarchy EN6 follows

Policy SI 13 says development "should aim to achieve greenfield run-off rates and ensure that surface water run-off is managed as close to its source as possible", in a six-step order: rainwater use, infiltration, green attenuation, discharge to a watercourse, then a surface water sewer, with the combined sewer last. Lambeth's EN6 points straight to this hierarchy, so each step skipped needs a reason in the strategy. Lambeth has no ordinary watercourses, so the watercourse step is open only on the Thames frontage and beside the Graveney. The Site Allocations DPD says St Thomas' Hospital could discharge straight to the Thames. Away from the river, blue or green roofs and attenuation come before any controlled sewer connection.

The new Lambeth Local Plan and the draft London Plan's proposed Policies GHR5 and GHR9

Lambeth has started a new Local Plan under the 2026 plan-making Regulations. The council's notice of intention is dated 30 June 2026. Its published timetable shows a scoping consultation from 1 September 2026 (the council's announcement gave 13 October as the closing date) and Gateway 1 on 31 October 2026. Consultation on the proposed plan follows in July and August 2028, with submission on 30 November 2028 and adoption on 30 April 2029. No draft policy wording has been published, so EN5, EN6 and Q27 remain the policies applied.

The Mayor consulted on the Draft London Plan 2026 from 16 July to 15 October 2026; the Mayor's decision MD3515 programmes the examination in public for autumn or winter 2027 and publication of the new plan in March 2028. Its flood content sits in draft Policy GHR5 (Flood risk and drainage, consultation stage), which would ask referable schemes to aim for greenfield QBAR or 3 l/s/ha, whichever is higher. Draft Policy GHR9 (Clean and healthy waterways, consultation stage) covers space beside waterways for maintenance and future defences. On adoption the new London Plan as a whole would replace the 2021 Plan, SI 12 and SI 13 included.

Is your Lambeth site behind the Thames wall or in a Critical Drainage Area?

We will tell you which Annex 4 row applies, whether a basement bedroom is possible and what EN6 needs from the drainage. Get a no-obligation, free quote. One of our experienced flood risk consultants will get back to you within 60 minutes.

Start a Quote

Lambeth's Local Information Requirements (December 2024): the flood and drainage items

Lambeth's validation list, the Local Information Requirements (the Local List) 2024, was consulted on from 30 October to 24 December 2023 and issued in December 2024, so it is under two years old and its local items can be required at validation. Four items deal with flooding and drainage.

  • Item 14, Basement Impact Assessment. "All applications for basement development (whether new build or extension to an existing building), which provide extra floorspace below ground", covering flooding, groundwater, surface runoff and basement flooding.
  • Item 34, Flood Risk Assessment. All proposals in Zones 2, 3a and 3b, and in Zone 1 the Annex 4 thresholds (residential over 0.5 ha or 10 or more dwellings, commercial over 1 ha or 1,000 m², sites under 1 ha with a critical drainage problem, and sites with evidence of risk from other sources in the SFRA or the strategy). The assessment supplies the evidence for the Sequential Test and, where it applies, the Exception Test.
  • Item 35, Foul Water and Water Supply Capacity and Water Utility Assessment. All major proposals: capacity on and off site, and connections to foul and storm sewers, assessed in consultation with Thames Water (EN6 vii).
  • Item 73, Sustainable Urban Drainage System (SUDS) Strategy. "All applications for major built development and all new developments in areas at risk of flooding". The strategy shows SuDS chosen before hard-engineered solutions, the drainage hierarchy followed, biodiversity and amenity value, a greenfield run-off rate and a net decrease in runoff.

Item 73 is firmer than the plan: EN6's supporting text asks schemes to aim for greenfield runoff, while the list asks the strategy to show that the system "achieves a greenfield run-off rate". Where greenfield is not reachable we say why in the strategy and show the closest rate the site allows, so the point is settled before validation. Our article on why applications are invalidated over flood risk and drainage covers the usual gaps.

What Lambeth's flood team expects in a drainage strategy for a major scheme

Lambeth has no stand-alone SuDS design guide. Its requirements sit in EN6, the Local List, the council's sustainable drainage page for major planning applications and, for basements, the Design Guide SPD. The major applications page says an application "will not be made valid" without six items:

  1. Site layout. A detailed layout at an identified scale.
  2. Topographical survey. Levels for the whole site.
  3. SuDS details. Plans, drawings and specifications, including hard construction, soft landscaping and planting.
  4. Calculations. Discharge and runoff rates and storage capacity, with evidence they meet the site's needs.
  5. Off-site works. Details of any work beyond the boundary and the consents it needs.
  6. Maintenance. A management and maintenance plan for every SuDS feature.

The page gives 10 dwellings and 1,000 m² of commercial floorspace as examples of major development. The DMPO 2015 definition also takes in housing sites of 0.5 ha where the number of homes is not known and any site of 1 ha. The council asks drainage questions to go to flooding@lambeth.gov.uk. Rainfall is uplifted using the Environment Agency's peak rainfall intensity allowances (last updated 27 May 2022); Lambeth publishes no figure of its own. Its 2021 Surface Water Management Plan tested a 40% uplift on rainfall to map future risk. We found no council statement adopting the 2025 National Standards for Sustainable Drainage Systems, and EN6 still cites the earlier non-statutory technical standards. NPPF Policy F8 now asks SuDS to follow the National Standards, so we write our strategies to both. The Local List does not name the London Sustainable Drainage Proforma, which some London boroughs require; see our SuDS proforma guide if the case officer asks for one.

Infiltration is the second step of the hierarchy, so the strategy has to show from site investigation whether it works on the site. For a basement, Q27 asks for the effect on groundwater flow as well. Our ground conditions and soakaway map gives a first read of the geology, and the BRE 365 infiltration rate calculator turns trial pit results into a design rate.

The Lambeth SFRA: a 2013 study with a breach addendum and a 2021 surface water plan

The Lambeth Strategic Flood Risk Assessment (Level 1 and Level 2, final report March 2013, URS) is still the borough's SFRA. It is read with the 2017 Environment Agency Thames tidal breach modelling addendum, which the Local Plan dates to 2018. We found no newer SFRA on the council's site. Four points matter for a site-specific assessment.

  • The breach model. The Environment Agency's 2017 model tested 5,679 breach locations between Teddington Weir and the Thames Barrier, 167 of them on hard defences in Lambeth, for the 2005 and 2100 epochs. It replaced the 2012 model, which had four breach locations in the borough. It says the 2013 SFRA's policy and site-specific FRA guidance "remain effective and unchanged". Site-level depths and hazards come from the Environment Agency's Product 4 data.
  • Flood Zone 3b. The 2013 SFRA draws the functional floodplain from the 1 in 20 year modelled flood on the River Graveney, and finds no tidal Flood Zone 3b, because the Thames defences protect to a much higher standard. NPPF Annex F now normally uses 3.3% (1 in 30); the 1 in 20 line is the SFRA's own.
  • Where the risk sits. Local Plan paragraph 9.42 names Waterloo, Vauxhall and the land next to the River Graveney as the areas of highest tidal and river risk.
  • Surface water. The Surface Water Management Plan (AECOM, 14 May 2021) defines 11 Critical Drainage Areas: Clapham, Oval, Railton Road, South Lambeth, Streatham, Streatham Hills, Streatham Vale, Tulse Hill, Wandsworth Road, West Dulwich and West Norwood. Several cross into Southwark, Wandsworth or Croydon.

The council's flood risk evidence paper for the site allocations (January 2024) summarises the SFRA, the addendum and the Environment Agency's surface water mapping for the 13 allocated sites. The Local Flood Risk Management Strategy (October 2018 revision) sets the council's objectives as Lead Local Flood Authority, and EN5 C asks assessments to take account of it, the SFRA and the Surface Water Management Plan. For the wider role of these studies, see our guide to strategic flood risk assessments.

How Chapter 18 of the August 2026 NPPF reads against Lambeth's 2021 plan

National flood policy moved into Chapter 18 of the National Planning Policy Framework on 17 August 2026. Policy F4 says when a site-specific assessment is needed, F5 governs the Sequential Test, F6 the Exception Test, F7 the safety of the development and F8 sustainable drainage. EN5 and Annex 4 were written under an earlier Framework (the plan's supporting text cites the 2019 version), and three points need care in Lambeth.

First, Annex 4 applies the Sequential Test in Flood Zone 1 only within a Critical Drainage Area, and the Local List only on land at high or medium surface water risk. NPPF Policy F5 applies it on any land "known to be at risk now or in the future from any form of flooding", subject to its listed exemptions. Under Annex A of the Framework, plan policies materially inconsistent with national decision-making policy "should be given very limited weight". On Flood Zone 1 land at risk from another source we therefore prepare for a Sequential Test, or show that an F5 exemption applies, and confirm the approach with the case officer. Second, Annex 4 lists the Sequential Test for all development in Zones 2, 3a and 3b, while F5 exempts householder development, small non-residential extensions and most changes of use. The local wording is stricter, so we confirm with the case officer before a minor scheme goes in without a test. Third, F5 caps the area of search at "the anticipated catchment of the development in terms of its likely occupiers or users", so the whole borough is a ceiling, not a starting point.

The flood risk Planning Practice Guidance, last updated on 17 September 2025, explains how the tests are applied; the Local List still cites its August 2022 version. Our NPPF guidance and advice page follows each change, and our guides to the sequential and exception tests and the surface water exemption go into the detail.

Behind the Albert Embankment, beside the Graveney and over the Effra: flood risk in Lambeth

Lambeth's river risk is concentrated in the north. The River Thames is held back by the Thames Barrier and the river walls. Behind them, much of the land in Waterloo, parts of Kennington and Vauxhall sits in Flood Zone 3, where the risk is a breach or overtopping (see our page on the Thames Barrier). In the south, a 1 km stretch of the River Graveney, a tributary of the River Wandle also known upstream as the Norbury Brook, crosses the Streatham and Norbury area. The 2013 SFRA lists Environment Agency records of flooding on it between 1968 and 1987, including gardens and a garage on Abercairn Road, SW16.

Everywhere else the risk is surface water and sewers. The River Effra, one of London's lost rivers, now runs as a sewer from Herne Hill through Brixton and Kennington to the Thames by Vauxhall Bridge, and the SFRA treats its flooding as sewer flooding. The Local Flood Risk Management Strategy records surface water flooding back to 1911 and significant surface water flooding of properties and businesses in Herne Hill in April 2004. Check a site on our flood risk map, and follow the Thames and the Graveney on the live river levels map.

Flood and drainage reports for a planning application to Lambeth Council

We prepare flood risk assessments and drainage strategies for applications to Lambeth Council, and every report is written to EN5, EN6, Annex 4 and the Local List. Unda Consulting Limited, which prepares these reports, is a CIWEM Business Partner, and the consultants who write them are chartered. A flood risk assessment, a sequential or exception test and a drainage strategy are three separate reports; groundwater and flood modelling feed into the assessment.

  • Site-specific assessments. EN5 C and Annex 4 ask for one across Zones 2 and 3 and on larger Zone 1 sites, and our flood risk assessment service sets out how each one is built.
  • For the planning application. Item 34 of the Local List names what the assessment must show, from every source to the evidence for the tests: a flood risk assessment for planning.
  • Buying in the floodplain. The Local Plan names Waterloo, Vauxhall and the Graveney corridor as the borough's highest-risk areas, and a purchaser there can commission a flood risk survey for property purchase.
  • Testing other sites. Annex 4 marks the test for all development in Zones 2, 3a and 3b and for Zone 1 sites in a Critical Drainage Area, which calls for a sequential and exception test report sized to the scheme's catchment.
  • Runoff and capacity. EN6 asks for a net decrease in both rate and volume and proof of sewer capacity, which is the job of a drainage strategy.
  • The Local List SuDS item. Item 73 asks majors and sites at risk of flooding to show greenfield runoff and the hierarchy followed, in a surface water drainage strategy.
  • After permission. Lambeth secures SuDS and their maintenance by condition or Section 106 (its major applications page), and discharge of drainage conditions provides the details for sign-off.
  • Chapter 18 against a 2021 plan. EN5's supporting text cites the 2019 Framework, so we read it alongside Chapter 18 and Annex A; our NPPF flood risk advice covers how.
  • Basements and groundwater. Q27 and the Local List ask every basement to address groundwater flow, and the SFRA maps areas susceptible to groundwater flooding: see groundwater flood risk assessment.
  • Breach levels on site. Paragraph 9.41 and the allocation policies ask for breach results verified for the site, which flood modelling provides.
  • Evacuation in Zone 3. Annex 4 accepts an emergency plan where safe access cannot be achieved, and the Waterloo allocations ask for an evacuation plan: our flood warning and evacuation plan covers it.
  • Foul capacity. Local List item 35 asks every major scheme to show foul and water supply capacity with Thames Water, set out in a foul drainage strategy.
  • BREEAM schemes. Policy EN4 asks all new non-residential development to reach BREEAM Excellent, and the flood credits come from a BREEAM flood risk assessment.

Our pages on Southwark and Wandsworth cover the neighbouring boroughs in the same Thames Estuary 2100 policy unit, our London guide covers the capital as a whole, and the local authorities index lists every council we cover.

Questions about Lambeth's flood and drainage requirements

What does Lambeth Policy EN5 (Flood risk) require from a planning application?

EN5, in the Lambeth Local Plan adopted on 22 September 2021, asks for a flood risk assessment for major development in Flood Zone 1, all development in Zones 2, 3a and 3b, and sites at risk from other sources. The assessment covers fluvial, tidal, surface water, groundwater, ordinary watercourse, sewer and reservoir flooding, shows the development is safe for its lifetime, and meets the Annex 4 criteria for its zone. Part F bars basement bedrooms where land is susceptible to flooding, and part G asks for the Thames and Graveney defence walls to be maintained.

Do I need a flood risk assessment for a Lambeth site in Flood Zone 1?

In many cases, yes. Annex 4 and the December 2024 Local List ask for one on residential sites over 0.5 hectares or with 10 or more homes, commercial sites over 1 hectare or 1,000 m², smaller sites with a critical drainage problem, and sites with evidence of surface water, groundwater or sewer risk. National policy adds any Flood Zone 1 site of one hectare or more and land the SFRA or the Flood Map for Planning shows at risk from any source.

Can a basement in Lambeth have a bedroom?

Not where the land is susceptible to flooding. EN5 F rules out basement bedrooms in the modelled breach extent and in areas at high surface water risk, and Annex 4 bars self-contained basements and basement bedrooms in the tidal residual risk zone of Flood Zone 3a and anywhere in Flood Zone 3b. Every basement needs a Basement Impact Assessment and a positive pumped device against sewer flooding, and in Zones 2 and 3a an escape route to a floor above the flood level.

Does Lambeth require greenfield runoff rates?

EN6 asks for a net decrease in both the rate and volume of runoff, and its supporting text asks schemes to aim for greenfield rates. Item 73 of the Local List goes further for major schemes and new development in areas at risk of flooding, asking the SuDS strategy to show a greenfield run-off rate. The allocation policies give each site's greenfield QBar.

Which SFRA does Lambeth use for planning applications?

The Lambeth Level 1 and Level 2 Strategic Flood Risk Assessment of March 2013, read with the addendum that adopts the Environment Agency's 2017 Thames tidal breach model. The Local Plan expects breach results to be verified for the site, and the 2021 Surface Water Management Plan maps the borough's 11 Critical Drainage Areas.

Is Lambeth preparing a new Local Plan?

Yes. The council published a notice of intention dated 30 June 2026 under the 2026 plan-making Regulations, held a scoping consultation in September and October 2026, and its timetable shows submission on 30 November 2028 and adoption on 30 April 2029. No draft policies have been published, so EN5, EN6 and Q27 still apply. Call 01293 214444 to check how that affects a scheme.

Submitting to Lambeth with a basement, a riverside plot or a major scheme?

Tell us the site and the scheme, and we will set out what EN5, EN6 and the December 2024 Local List need before you validate. Get a no-obligation, free quote. One of our experienced flood risk consultants will get back to you within 60 minutes, with a fixed quote within the hour.

Start a Quote

To talk through a Lambeth site, call 01293 214444 or email enquiries@unda.co.uk. You will speak to one of our experienced flood risk consultants.

Get a no-obligation, free quote

If you need a quote or to discuss your requirements in more detail contact one of our experienced Flood Risk and Drainage Consultants.

Call +44 (0) 1293 214444, email enquiries@unda.co.uk or fill in the form below

  • This field is for validation purposes and should be left unchanged.