Flood Risk & Drainage Requirements for Boston Borough Council
Contact Us
Boston Borough Council decides flood and drainage questions under Policy 4 of the South East Lincolnshire Local Plan 2011-2036, adopted on 8 March 2019, with Lincolnshire County Council advising on surface water as Lead Local Flood Authority. In Boston the policy reaches beyond the flood zones: any site shown at risk in a breach or overtopping of the defences on the Strategic Flood Risk Assessment maps is caught, and no development is permitted within 50 metres of the toe of the raised Witham Haven Banks.
This page sets out what Boston Borough Council and the bodies it consults ask for on flood risk and drainage, policy by policy, and what our reports do to meet each requirement. It covers the depth-based floor level rules in the 2017 Strategic Flood Risk Assessment, what the council asks for at validation, Lincolnshire County Council's drainage standards and the three drainage boards whose consent sits outside planning. To talk through a Boston site, call 01293 214444 or email enquiries@unda.co.uk.
Behind the Boston Barrier: why Boston sites are judged on breach depth
Almost the whole borough is floodplain. The South East Lincolnshire SFRA (version 6, December 2017) records that about 85% of Boston lies in the floodplain, 84% of the borough in Flood Zone 3 and 1% in Flood Zone 2, leaving 26,503 homes and 1,212 commercial properties at risk. With so little land outside Flood Zone 3, the zones alone cannot rank sites, so the SFRA models overtopping and individual breaches of the defences for a 0.5% tidal and 1% river event and a 0.1% event, today and in 2115, and bands the result into hazard categories from danger for all down to low hazard.
Those maps decide most Boston cases. The SFRA says it used the 2115 breach hazard map to choose the Local Plan's housing sites, and that where a site would be inundated the minimum finished floor levels should come from the flood depth maps. Its standing advice matrix (Appendix C, marked draft version 4) sets floor levels from the 2115 maximum depth, asks for at least two storeys with no ground floor habitable rooms where depths exceed 1.6 metres, and makes single storey schemes use the 0.1% event in 2115. The SFRA also records that Boston has no functional floodplain (Flood Zone 3b).
The Boston Barrier lowers the odds of a tidal flood, and planning still tests the breach. The Environment Agency completed the primary barrier gate in December 2020, first operated it against a high tide on 7 November 2021 and now expects the whole scheme, including new gates at the Port of Boston wet dock, to be finished in 2028. The gate reduces the risk to over 13,000 homes and businesses. Planning still asks what happens if a bank is breached or overtopped over the life of the building, which is why our flood risk assessments for planning in Boston start from the SFRA depth and hazard at the site and not from the defended picture. Our explainer on why a defended site can still sit in a flood zone covers the reasoning.
Borough, county, Environment Agency and three drainage boards: who decides what for Boston
| Body | Role | What it decides or is consulted on |
|---|---|---|
| Boston Borough Council | Local planning authority | Validates and decides the application against Policy 4 and the other plan policies; applies the sequential test; sets conditions |
| South East Lincolnshire Joint Strategic Planning Committee | Plan-making body (Boston, South Holland and Lincolnshire County Council members) | Prepares and reviews the shared Local Plan; now starting the new Joint Local Plan |
| Lincolnshire County Council | Lead Local Flood Authority and highway authority | Consulted on surface water for every major scheme, as defined in the national Development Management Procedure Order; regulates ordinary watercourses where no drainage board operates |
| Environment Agency | Statutory consultee; operator of the Boston Barrier | Advises on Flood Zones 2 and 3, the tidal Haven and the main rivers; permits for work near a main river or flood defence |
| Witham Fourth, Black Sluice and Welland and Deepings drainage boards | Internal drainage boards | Byelaw consent for discharges into board drains and for work close to them, separate from planning permission |
| Anglian Water | Water and sewerage company | Sewer capacity and connections; Policy 4 allows a surface water connection to the public sewer only in exceptional circumstances |
The Witham Fourth board covers the fens from Boston north towards Coningsby and Wainfleet, the Black Sluice board drains the fen to the west and south-west of the town to the South Forty Foot Drain, and the Welland and Deepings board reaches north to Kirton and Fosdyke. Lincolnshire County Council's flood risk management page says it regulates ordinary watercourses outside the boards' districts, and that the boards act as its agents there. Our guides to the Lead Local Flood Authority's role, how planning authorities handle flood risk and SuDS and why internal drainage boards matter for planning explain each regime.
Boston shares its Local Plan, its SFRA and its county drainage rules with South Holland District Council, and the county drainage rules with East Lindsey District Council to the north. Every council we cover is on our local authorities hub.
Policy 4 and the other Local Plan policies a Boston application must answer
Policy 4 holds the flood tests, and six more policies of the adopted South East Lincolnshire Local Plan touch drainage, water quality or the two urban extensions on Boston's edge. All seven were adopted on 8 March 2019, when every saved policy of the Boston Borough Local Plan (1999) was deleted. Appendix 2 of the plan lists the old Policy G3 (Foul and Surface Water Disposal) among those replaced by Policy 2; Policy 4 itself was new.
| Policy | Title | What it requires | Your obligation | How Unda meets it | Source and date |
|---|---|---|---|---|---|
| Policy 4 | Approach to Flood Risk | Sequential and exception tests; a site-specific assessment of all sources with climate change, criteria a to h; surface water managed in every zone; no building within 50 m of the Witham Haven Banks | Show the site passes the tests and is safe at the SFRA breach depth, with drainage and foul routes | A flood risk assessment built on the SFRA depth and hazard maps, a sequential test where needed, and a drainage strategy | Local Plan, adopted 8 March 2019 |
| Policy 31 | Climate Change and Renewable and Low Carbon Energy | Sequential approach and exception test, flood mitigation in design, SuDS for all major applications; 110 litres per person per day | Show flood mitigation and SuDS are built into the scheme | Mitigation and SuDS set out in the assessment and the drainage strategy | Local Plan, adopted 8 March 2019 |
| Policy 3 | Design of New Development | Flood-resistant and flood-resilient design and SuDS secured where relevant | Show the layout and building design deal with flooding | Resistance and resilience measures specified for the building and layout | Local Plan, adopted 8 March 2019 |
| Policy 2 | Development Management | Sustainable drainage and flood risk among the tests every application must meet | Address drainage and flood risk on any scheme needing permission | A report sized to the scheme, from a short flood risk statement to a full strategy | Local Plan, adopted 8 March 2019 |
| Policy 30 | Pollution | No unacceptable harm through surface and groundwater quality | Show runoff is treated before it leaves the site | Treatment stages set out in the drainage strategy | Local Plan, adopted 8 March 2019 |
| Policies 13 and 14 | South West Quadrant and South of the North Forty Foot Drain Sustainable Urban Extensions | Satisfactory mitigation of flood risk on each urban extension | Show each phase is safe in a breach and drains to an agreed outfall | Phase assessments tied to the SFRA depth maps and a whole-site drainage strategy | Local Plan, adopted 8 March 2019 |
Requirements checked November 2026.
Policy 4 (Approach to Flood Risk): what Boston applications must show
Policy 4 permits development in an area at risk of flooding only where the sequential test is passed, the exception test is passed where it applies, and a site-specific flood risk assessment shows the scheme will be safe. Its opening sentence defines that area as "Flood Zones 2 and 3 of the Environment Agency's flood map or at risk during a breach or overtopping scenario as shown on the flood hazard and depths maps in the Strategic Flood Risk Assessment" (Local Plan, March 2019). The assessment must cover "risk from all sources of flooding including the impacts of climate change" and meet eight criteria. Criterion b asks it to "identify the relevant predicted flood risk (breach/overtopping) level" and the measures that make the development safe. Criterion d asks for warning and evacuation procedures where necessary, prepared in consultation with the council's emergency planning staff.
Three further rules bite in Boston. Development in all flood zones, and any site over a hectare in Flood Zone 1, must show its surface water "can be managed and will not increase the risk of flooding to third parties". A change of use creating self-contained ground floor homes in the danger for some, most or all hazard bands "will not be supported", and in those bands the policy also requires unrestricted access to a habitable room above the flood level and an emergency evacuation plan. Last, "No development will be permitted within a 50m buffer from the toe of the raised Witham Haven Banks (flood defences)", shown on the plan's Appendix 10, so the Environment Agency keeps room to widen and raise the banks.
The sequential test is not needed for sites allocated in the plan, for minor development or for a change of use, unless the change is to a caravan, camping or chalet site or a mobile or park home site. For any other proposal, Policy 4(1) allows a search of settlements across the whole borough, and national policy now treats that as an upper limit: the area shrinks to whatever the development's catchment actually is. Our sequential and exception tests define that area of search and the hazard band of each alternative. On riverside plots, our flood risk assessments plot the 50 m buffer against the site before any layout is fixed, read the breach depth for 2115, set floor levels to the Appendix C matrix and include an evacuation plan that refers to the county's evacuation routes. Our guide to the sequential and exception tests explains the national tests the policy builds on.
Policy 31 (Climate Change and Renewable and Low Carbon Energy): SuDS on every major scheme
Policy 31 makes sustainable drainage a standard part of major development. Clause A2 asks every proposal to address climate change through "the adoption of the sequential approach and Exception Test to flood-risk and the incorporation of flood-mitigation measures in design and construction to reduce the effects of flooding, including SuDS schemes for all 'Major' applications". Clause A3 adds the Building Regulations water efficiency standard of 110 litres per person per day for new homes. Paragraph 3.5.7 of the plan says the same of major schemes: SuDS are expected "as standard". Our surface water drainage strategies for Boston majors show the SuDS components, the climate change allowance and the outfall, so the county can test the scheme against Policy 31 and its own standards together.
Policy 3 (Design of New Development): resilience in the building itself
Policy 3 asks proposals to show how they will secure "the mitigation of flood risk through flood-resistant and flood-resilient design and sustainable drainage systems (SuDS)" where that is relevant to the scheme. In Boston it nearly always is, since the SFRA expects floor levels and resilience to follow the predicted depth. Our assessments specify the resistance measures, the resilient fabric and the height of services such as electrics, so the architect can carry them into the drawings rather than leave them to a condition.
Policy 2 (Development Management): drainage on smaller schemes
Policy 2 lists "sustainable drainage and flood risk" among the sustainable development considerations every application must meet. That brings smaller schemes, which the county does not see, into the drainage question: the borough's officers judge them. For a single plot or a conversion we prepare a proportionate statement that shows where roof and yard water will go, often into a board drain, and when the board's consent will be needed.
Policy 30 (Pollution): water quality from the drainage
Policy 30 refuses development that would cause unacceptable harm by way of "surface and groundwater quality", after mitigation is taken into account. On a fen site draining to a pumped board system, the treatment of runoff from roads, yards and car parks is part of that test. Our drainage strategies set out the treatment stages before discharge, using the SuDS components already proposed for storage wherever they can do both jobs.
Policy 13 (South West Quadrant Sustainable Urban Extension) and Policy 14 (South of the North Forty Foot Drain Sustainable Urban Extension): flood mitigation on Boston's growth sites
Both urban extensions must provide "Satisfactory mitigation of flood risk", clause 7 of Policy 13 and clause 6 of Policy 14. The plan's supporting text for the South West Quadrant says the site is "vulnerable to the severest flood risk with a failure in tidal defences providing a threat of 'danger for all'", so flood mitigation is an essential requirement there. Allocated sites are treated as having passed the sequential test, but paragraph 3.5.4 of the plan says a site-specific assessment must still show the development will be safe for its lifetime, including if the defences fail. For a phase of either extension we tie the assessment to the 2115 breach depth for that parcel and the drainage strategy to the outfall agreed for the site as a whole.
The new Joint Local Plan to 2044, and reorganisation
A new Joint Local Plan for Boston and South Holland is at its earliest stage, under the plan-making system that came into force in 2026. The Joint Strategic Planning Committee on 27 May 2026 endorsed starting work on a plan to 2044 and a target of December 2026 for the formal notice of intention. The project initiation document plans a vision and strategy consultation in summer 2027 and adoption in October 2029, and lists a new SFRA among the evidence to commission. No draft policy has been published, so Policy 4 and the 2017 SFRA remain the tests.
Reorganisation is a second unknown. The government chose two unitary councils for Lincolnshire in July 2026, with Boston in a new Lincolnshire unitary, then paused reorganisation plans for review on 7 September 2026. Our explainer on reorganisation and flood risk planning sets out what usually carries over to a successor council.
Boston site near the Haven or in a danger band?
We read the SFRA breach depth for your plot, check the Haven banks buffer and set out the reports Policy 4 needs before you commit to a layout. Get a no-obligation, free quote. One of our experienced flood risk consultants will get back to you within 60 minutes, with a fixed quote within the hour. Call 01293 214444 or email enquiries@unda.co.uk.
Start a QuoteFrom Haven-side flats to fen farm buildings: which Boston schemes need which report
National policy sets the triggers in Chapter 18 of the NPPF, and Policy 4 widens them to land at risk in a breach on the SFRA maps. You can check the national flood zone for a postcode on our flood risk map, then read the SFRA hazard band for the same spot.
| Trigger | Flood risk assessment | Sequential test | Exception test | Drainage strategy, consents |
|---|---|---|---|---|
| Site in Flood Zone 2 or 3, or in a breach or overtopping area on the SFRA maps | Yes, criteria a to h of Policy 4, with breach level and climate change | Yes, unless exempt; no wider than the scheme's catchment, and never beyond the borough's settlements | Where Annex F table 3 of the NPPF requires it | Surface water management shown under Policy 4 |
| Allocated site, including the two urban extensions | Yes, safe for its lifetime if defences fail | No, treated as passed | Not where it was applied when the site was allocated (F6) | Whole-site strategy and phase detail |
| Within 50 m of the toe of the raised Witham Haven Banks | Not permitted under Policy 4 | Not applicable | Not applicable | Environment Agency permit for any work near the defence |
| Flood Zone 1, over 1 hectare | Yes (NPPF F4) | Only if at risk from another source | Not required: F6 is limited to Zones 2, 3a and 3b | Yes: surface water shown to cause no third-party risk |
| Change of use to ground floor flats in a danger band | Yes | Not required | Not required | Not supported; where allowed, a room above flood level and an evacuation plan |
| Major development: 10 or more homes (or a housing site of 0.5 ha or more where the number is not yet known), 1,000 m2 or more of floorspace, or a site of at least 1 ha | Depends on zone | Depends on zone | Depends on zone | Yes: SuDS under Policy 31; Lincolnshire County Council consulted |
| Householder extension, small non-residential extension under 250 m2 | Yes in Flood Zones 2 and 3 | Not required (F5) | Not required | Drainage under Policy 2 |
| Discharge into a board drain, or work beside one | As above | As above | As above | Byelaw consent from the drainage board |
The commonest gaps in Boston submissions follow from these rules: an assessment that quotes the flood zone but not the SFRA breach depth, a riverside layout drawn inside the Haven banks buffer, and a drainage strategy with no board outfall agreed. Our article on planning applications invalidated on flood and drainage grounds covers how they are avoided.
The 2017 SFRA and what Boston asks for at validation
The SFRA report is version 6, dated 18 December 2017, and was prepared by the South East Lincolnshire Joint Planning Unit with the Environment Agency, Lincolnshire County Council and the drainage boards. It remains the published study. For the sequential test it says the search area "should be the whole of the Council area unless the functional requirements of the development justify a reduced search area". It also expects single storey schemes to mitigate the 0.1% scenario. The new Joint Local Plan's project document plans a fresh SFRA, but none had been published by November 2026, and the 2017 study predates the climate change allowances of 2022, so our assessments read it alongside the current Environment Agency allowances. Our explainer on strategic flood risk assessments covers how planners use them.
Boston has validated applications against the national requirements since 1 April 2021. The council's submission page says its local validation list, adopted in early 2019, "is a guidance document but not a formal requirement". The accompanying validation guidance (April 2021) still describes when a flood risk assessment is expected: Flood Zones 2 and 3, sites of a hectare or more in Flood Zone 1, and land with local flooding issues. It also lists a surface water drainage assessment for major, minor and rural schemes and new hardstanding, and a sustainable drainage assessment for majors. That guidance cites the 2019 NPPF, so the triggers now come from Chapter 18 of the August 2026 Framework. In practice an application in a flood zone that arrives without an assessment cannot pass Policy 4, whatever the checklist says.
Lincolnshire County Council's drainage standards on Boston sites
Lincolnshire County Council tests surface water on major schemes against its 2021 design approach for development roads and sustainable drainage. We found no county statement adopting the National Standards for Sustainable Drainage published in June 2025, so the 2021 document is the county's published basis, while NPPF policy F8 separately asks for SuDS designed to the National Standards. The rules that shape a Boston scheme:
- Greenfield rate. Standard S2: peak runoff for the 1 in 1 and 1 in 100 year events never above the greenfield rate for the same event.
- Brownfield sites. Standard S3: as close to the greenfield rate as reasonably practicable, and never above the rate before redevelopment.
- Climate change and creep. Plus 40% on peak rainfall intensity, or 25% with sensitivity testing to 40% (Design Approach, 2021); 10% added to impermeable area for urban creep.
- Flooding on site. None on any part of the site in a 1 in 30 year event (S7) and none in buildings or vulnerable plant in a 1 in 100 year event (S8); systems drain down within 48 hours.
- Infiltration. Test pits filled three times and the worst rate used; borehole tests are not accepted; at least 1 metre between the base of the SuDS and the highest recorded groundwater.
- Outfalls. Never to a foul sewer; the county notes typical drainage board pump discharge rates of 1.4 l/s/ha on the fens.
On Boston's silts and clays the water table is usually too high for infiltration to work, so most schemes attenuate and discharge to a board drain at a rate the board will consent. That consent is given under the board's byelaws, separately from planning permission, and can be refused after permission is granted. Our drainage strategies set infiltration aside only on test or groundwater evidence, size storage to the county's allowances and the board's rate, and show treatment for Policy 30. Early checks can use our ground conditions and soakaway map, the BRE 365 infiltration rate calculator and our drainage calculators. Where the county does object, our article on answering an LLFA objection sets out the usual route, and our guide to ordinary watercourse consent covers works in a drain.
How Chapter 18 of the August 2026 NPPF sits alongside Policy 4
Policy 4 is read with Chapter 18 of the National Planning Policy Framework, published on 17 August 2026. Policy F4 sets when a site-specific assessment is needed, including land shown at risk from any source in an SFRA. F5 sets the sequential test and its exemptions for allocated sites, householder development, small non-residential extensions and most changes of use. F5 also says the search area "should not be greater than the anticipated catchment of the development in terms of its likely occupiers or users", That limit applies to every sequential test in Boston, so the borough-wide search in Policy 4(1) is the largest area an applicant can be asked to cover, not the starting point. F6 sets the exception test, F7 the conditions for safe development and F8 the SuDS requirements, with Lead Local Flood Authority advice on major schemes.
The government's flood risk and coastal change guidance was last revised in September 2025. Our summaries of what the August 2026 NPPF changed and of climate change allowances for planning go further, and our NPPF guidance and advice service applies them to a scheme.
Surges on the Haven and the South Forty Foot Drain: Boston's flood risk in brief
Tidal surge up the Haven is the risk the town is built around. On 5 December 2013 a North Sea surge flooded over 800 homes across 55 streets in Boston, the event that set the case for the barrier. The town's history, watercourses and defences are on our area page for flood risk assessment in Boston, and the wider county on our Lincolnshire page.
River and drain flooding matter too, even behind the barrier. In January 2025 rain on frozen, saturated ground drove the South Forty Foot Drain to a record 3.192 m AOD at Hubberts Bridge, and Lincolnshire County Council had 36 homes in Boston reported as flooded, chiefly on Wyberton West Road and Park Road (Environment Agency review, May 2025). Pumped, defended land of this kind keeps a residual risk that an assessment has to address. River levels can be followed on our live river levels map, and the long-term pressures on the fen system are set out in our piece on Fens 2100+.
Reports we prepare for applications to Boston Borough Council
We have prepared reports for applications to Boston Borough Council, and each service below is tied to the policy, standard or SFRA finding that calls for it. Three reports are often confused: a flood risk assessment asks whether the site is safe, a sequential or exception test whether the scheme should be there at all, and a drainage strategy where the rain that falls on it goes.
- All sources. Policy 4 asks for "risk from all sources of flooding", which in Boston means the tidal Haven, the drains, surface water and groundwater: our flood risk assessment service covers each.
- Breach levels. Criterion b of Policy 4 wants the predicted breach or overtopping level and the mitigation that follows: a flood risk assessment for planning sets both from the SFRA maps.
- Buying in the town. Homes behind the barrier and the Haven banks show as high risk in searches and lender checks: a flood risk survey for property purchase assesses the building itself.
- Windfall sites. Outside the allocations, the test covers the development's catchment, up to the whole borough's settlements under Policy 4: our sequential and exception test reports define the search and rank the alternatives.
- Surface water and foul. Criteria e and g of Policy 4 ask for SuDS and adequate foul treatment: a drainage strategy shows both routes.
- County standards. Major schemes go to Lincolnshire County Council against its 2021 Design Approach: a surface water drainage strategy gives the rates, storage and board outfall.
- After permission. Conditions often ask for final calculations, maintenance and board consent: we prepare the discharge of drainage conditions submission.
- Evacuation. Criterion d of Policy 4 asks for warning and evacuation procedures agreed with the council's emergency planners: a flood warning and evacuation plan provides them.
- Beyond the SFRA maps. Where the 2017 breach points do not represent a site, or a drain needs a level the maps lack: flood modelling supplies it.
- High water table. The county asks for 1 metre between the SuDS base and the highest recorded groundwater: our groundwater assessments establish that level.
- Foul capacity. Policy 4 criterion g asks that foul treatment exists or can be provided in time, including off-mains in the fen villages: a foul drainage strategy answers it.
- Port and industrial land. Commercial sites on the Haven sit in the danger bands and beside the barrier works: a due diligence flood risk assessment informs a purchase or loan.
- After 2013 and 2025. Homes in the town flooded from the sea in 2013 and from the South Forty Foot Drain in 2025: a flood risk assessment for insurance gives brokers site-specific evidence.
- National policy. Every Boston decision applies NPPF Chapter 18 alongside Policy 4: our NPPF guidance and advice explains it for a scheme.
Boston planning, flood risk and drainage: questions applicants ask
What does Policy 4 (Approach to Flood Risk) of the South East Lincolnshire Local Plan require in Boston?
Policy 4, adopted in March 2019, permits development in an area at risk of flooding, including land shown at risk in a breach or overtopping on the SFRA maps, only where the sequential test and, if needed, the exception test are passed and a site-specific assessment covers all sources and climate change. It also requires SuDS unless not technically feasible, adequate foul treatment, and no development within 50 metres of the toe of the raised Witham Haven Banks.
When does Boston Borough Council need a site-specific flood risk assessment?
For development in Flood Zones 2 and 3, for land shown at risk in a breach or overtopping on the SFRA hazard and depth maps, and in Flood Zone 1 for sites of a hectare or more or land at risk from another source such as surface water. Allocated sites still need one to show they are safe for their lifetime if the defences fail.
Which body checks surface water drainage on a Boston planning application?
Lincolnshire County Council, as Lead Local Flood Authority, is the statutory consultee on surface water for major development (10 or more homes, 1,000 m2 of floorspace, a site of 1 hectare, or 0.5 hectares of housing where numbers are unknown), and tests it against its 2021 Design Approach. On smaller schemes Boston Borough Council's officers judge the drainage under Policy 2, and the drainage board consents any discharge into its drains.
Will Boston Borough Council expect separate flood and drainage reports for one scheme?
Often. They are separate reports: the assessment shows the site is safe, and the drainage strategy shows where surface water goes and at what rate. Policy 31 expects SuDS on every major application, and Policy 4 asks every flood zone, and any site over a hectare in Flood Zone 1, to show surface water will not increase risk to others.
Since the Boston Barrier opened, can a site skip the flood risk assessment?
No. The barrier gate, working since December 2020, cuts the tidal risk, but Policy 4 and the 2017 SFRA test sites against a breach or overtopping of the defences over the development's lifetime. Floor levels come from the SFRA depth maps, and single storey schemes are tested against the 0.1% event in 2115.
What discharge rate does Lincolnshire County Council accept on a Boston site?
Its 2021 Design Approach caps peak runoff from a greenfield site at the greenfield rate for the 1 in 1 and 1 in 100 year events, and asks a previously developed site to come as close to greenfield as practicable and never exceed its existing rate. Storage allows 40% for climate change, or 25% with sensitivity testing, and 10% for urban creep; the board may set its own rate for its drain.
Can I build close to the Witham Haven banks in Boston?
Not within 50 metres of the toe of the raised Witham Haven Banks: Policy 4 permits no development in that strip, shown on Appendix 10 of the Local Plan, so the Environment Agency has room to raise and widen the banks. Beyond the buffer, work close to the defences may also need an Environment Agency permit.
Draining to a Witham Fourth or Black Sluice drain?
We size the storage to Lincolnshire's 2021 standards and to the rate the board will consent, and show the Policy 4 drainage case in one report. Get a no-obligation, free quote. One of our experienced flood risk consultants will get back to you within 60 minutes, with a fixed quote within the hour. Call 01293 214444 or email enquiries@unda.co.uk.
Start a QuoteFor a scheme anywhere in Boston borough, from the Haven side to the fen villages, call 01293 214444 or email enquiries@unda.co.uk. Unda Consulting Limited's chartered consultants can take a Boston site through the assessment, the sequential test and the drainage case together. Reports for applications to Boston Borough Council come from Unda Consulting Limited, a CIWEM Business Partner.