Flood Risk & Drainage Requirements for Guildford Borough Council
Contact Us
Guildford Borough Council judges flood risk against Policy P4 of its Local Plan: Strategy and Sites, adopted in April 2019, and surface water against Policy P11 of its Development Management Policies, adopted in March 2023, with Surrey County Council advising on drainage as Lead Local Flood Authority. P11 reaches every application, a single new house included: runoff after the work may be no greater than before it, and on major or flood-risk sites a soakaway needs a metre of ground above the highest likely groundwater. P4 also allows development inside the 'developed' functional floodplain, but only where it meets the policy's other flood tests, its footprint is no larger than the existing building's and the use is no more vulnerable; the policy also expects such proposals to facilitate greater floodwater storage, a local allowance that now has to be read against Annex F of the August 2026 NPPF.
Guildford Borough Council (GBC) covers far more than the town: Ash, Tongham and Normandy in the west, Send and Ripley to the north-east, the Horsleys and Effingham to the east, and Shalford, Chilworth and Shere along the Tillingbourne. Below we take each body that has a say on flood risk and drainage, each policy it applies, and what our reports put in front of the case officer to satisfy it. We have worked on applications to Guildford Borough Council. To discuss a site, call 01293 214444 or email enquiries@unda.co.uk.
Borough, county or Environment Agency: who has a say on a Guildford scheme
The borough council makes the decision. Surrey County Council reviews surface water on major applications and tells the council whether the drainage can be supported; the Environment Agency advises where a site lies in Flood Zone 2 or 3 or beside a Main River. Smaller schemes are weighed by the council's own officers, with the county commenting where its non-major guidance says it will or where the council asks.
| Body | Role | What it decides or is consulted on |
|---|---|---|
| Guildford Borough Council | Local planning authority (until 31 March 2027) | Decides the application against the 2019 and 2023 Local Plan documents, any made neighbourhood plan for the parish and Chapter 18 of the NPPF; checks the submission against its local validation list |
| Surrey County Council | Lead Local Flood Authority | Statutory consultee on surface water for all major development; non-statutory, site-specific advice on non-major schemes inside the 1% AEP surface water flood extent (at any depth) or containing or next to a recorded watercourse; consent for works to ordinary watercourses at any scale. Not a statutory consultee on groundwater |
| Environment Agency | Statutory consultee and Main River regulator | Flood risk from the Wey, the Tillingbourne and the borough's other Main Rivers; works in, over or within 8 m of a Main River may need an environmental permit from the Agency |
| Thames Water | Sewerage undertaker | Capacity in public sewers and consent to connect; named by Policy P4's supporting text as a risk management authority alongside the council and the Agency |
| Internal drainage board | None | No internal drainage board operates in the borough, so no board consent or byelaw applies |
That arrangement has a fixed end. On 1 April 2027 West Surrey Council takes over every council service in Guildford, Runnymede, Spelthorne, Surrey Heath, Waverley and Woking, together with the services Surrey County Council provides there, so the planning authority and the flood authority become one organisation. The existing councils operate as normal until that date. Our article on local government reorganisation and flood risk planning looks at what it means for applications in progress, and our explainer on the role of a Lead Local Flood Authority covers the county's powers.
Policy P4, Policy P11 and the rest of Guildford's flood and drainage policies
Five borough-wide policies deal with flood risk and drainage: P4 in the Local Plan: Strategy and Sites, and P10, P11, D13 and D15 in the Local Plan: Development Management Policies. Seven neighbourhood plans have been made in the borough (the council's neighbourhood planning page still says four, but Lovelace, Puttenham and Send were made on 19 May 2021), and five of them add a flood or drainage clause of their own, in Burpham, East Horsley, Effingham, West Horsley and Lovelace; the Send and Puttenham plans add none, Puttenham's saying in terms that P4 already covers the ground. Policy P4 replaced the 2003 Local Plan's Policies G1 (6) Flood protection and G1 (7) Land drainage and public utility infrastructure in April 2019, and the 2003 corridor policy G11 was replaced by D13 and P10 in March 2023, so an older decision notice citing a G1 clause is no guide to a decision today.
| Policy | Title | What it requires | Your obligation | How Unda meets it | Source and date |
|---|---|---|---|---|---|
| P4 | Flooding, flood risk and groundwater protection zones | See Policy P4 (clauses 2 to 6), quoted in the section below | An FRA in the flood zones; drainage proof on every scheme; a groundwater assessment where the site may be at risk | An FRA covering every source, safe access and egress, climate change and floor levels, with the runoff figures P4(5) asks for | Local Plan: Strategy and Sites, adopted 25 April 2019 |
| P11 | Sustainable Surface Water Management | Runoff rates and volumes no greater than before development; greenfield rates on greenfield land; SuDS, the discharge hierarchy and, for infiltration, at least 1 m between the base of the system and the maximum likely groundwater level, on major and at-risk schemes | Show the drainage works at application stage, with test results or a reason for their absence | A surface water strategy with pre- and post-development calculations, infiltration evidence and a SuDS layout | Development Management Policies, adopted 22 March 2023 |
| P10 | Water Quality, Waterbodies and Riparian Corridors | See Policy P10 (clauses 5, 6 and 8), quoted in the section below | Keep the buffer free of built development and plan its protection during construction | Plans and an FRA that show the 10 m line from top of bank and any watercourse works needing consent | Development Management Policies, adopted 22 March 2023 |
| D15 | Climate Change Adaptation | Adaptation to more frequent and severe rainfall through water bodies, absorbent planting and permeable ground | Show how the layout slows and soaks up rain | SuDS features set out so the design team can cite them in the adaptation case | Development Management Policies, adopted 22 March 2023 |
| D13 | The Corridor of The River Wey & Godalming Navigations | Flood risk mitigation along the Navigations designed to suit the waterway's character | Resolve flood measures and design together | Mitigation options set out early enough for the architect to work them into the scheme | Development Management Policies, adopted 22 March 2023 |
| B-FD 4 | Water Supply & Sewerage Infrastructure (Burpham) | New homes justified by flood risk assessment and the sequential test; SuDS best practice; water and sewerage capacity shown | Applies in the Burpham neighbourhood area | An FRA and drainage strategy with the sewer capacity evidence the policy asks for | Burpham Neighbourhood Plan, made 12 April 2016 |
| EH-EN5 | Flooding (East Horsley) | See Policy EH-EN5, quoted in the section below | Applies in East Horsley parish | A drainage strategy that traces the outfall and checks the receiving system | East Horsley Neighbourhood Plan, made 24 July 2018 |
| ENP-G4 | Flooding (Effingham) | See Policy ENP-G4, quoted in the section below | Applies in the Effingham neighbourhood area | An FRA that sets out groundwater and surface water risk, with the runoff calculations | Effingham Neighbourhood Plan, made 10 April 2018 |
| WH13 | Sustainable Urban Drainage (West Horsley) | See Policy WH13, quoted in the section below | Applies in West Horsley parish | A drainage strategy naming and sizing the features chosen | West Horsley Neighbourhood Plan, made 4 December 2018 |
| LNPEN3 | Flooding (Lovelace) | See Policy LNPEN3 (a) to e)), quoted in the section below | Applies in the Lovelace neighbourhood area | A surface water management plan or drainage strategy sized to the trigger that applies | Lovelace Neighbourhood Plan, made 19 May 2021 |
Requirements checked November 2026.
Guildford Policy P4 (Flooding, flood risk and groundwater protection zones): what it requires
Policy P4 permits development in Flood Zones 2 and 3 only on six conditions, the central one being that "a site–specific flood risk assessment demonstrates that the development, including the access and egress, will be safe for its lifetime, taking into account climate change, without increasing flooding elsewhere, and where possible, will reduce flood risk overall" (Local Plan: Strategy and Sites, April 2019). The others read: "a) the vulnerability of the proposed use is appropriate for the level of flood risk on the site"; "b) the proposal passes the sequential and exception test (where required) as outlined in the NPPF and Government guidance"; "d) the scheme incorporates flood protection, flood resilience and resistance measures appropriate to the character and biodiversity of the area and the specific requirements of the site"; "e) when relevant, appropriate flood warning and evacuation plans are in place and approved"; and "f) site drainage systems are appropriately designed, taking account of storm events and flood risk of up to 1 in 100 year chance with an appropriate allowance for climate change".
Clause 5 reaches beyond the flood zones: "All development proposals are required to demonstrate that land drainage will be adequate and that they will not result in an increase in surface water run-off." The supporting text adds two triggers of its own. Paragraph 4.3.45 asks for an assessment of groundwater flood risk wherever a site is "at, or potentially at, risk of groundwater flooding", which matters on the chalk and greensand under much of the borough. Paragraph 4.3.41 says a windfall site promoted in a flood zone must pass the tests and also "demonstrate to be preferential to those sites already identified as contributing towards development supply".
Clause 6 protects drinking water. About 30% of the borough lies on principal aquifers and it contains 14 Source Protection Zones, according to paragraph 4.3.40, so development there is permitted only where it has no adverse impact on the quality of the groundwater resource and does not put the public water supply at risk.
Our assessments for P4 take each source in turn, fix floor levels and a dry route out against modelled levels with the current climate change allowances, and carry the runoff comparison that clause 5 asks for. Where the site sits on chalk or in a Source Protection Zone, the groundwater evidence goes into the same report. Our note on groundwater source protection zones explains why those zones change what can go into the ground.
Policy P4 in developed and undeveloped Flood Zone 3b
Guildford's Level 1 SFRA treats the modelled 1 in 20 year flood outline as the functional floodplain and splits it in two: building footprints inside it are "developed" Flood Zone 3b, and everything else is "undeveloped" (SFRA Volume 1, July 2016). Policy P4 clause 2 brings developed 3b within its six tests, and clause 3 adds: "Development proposals in the 'developed' flood zone 3b will also only be approved where the footprint of the proposed building(s) is not greater than that of the existing building(s) and there will be no increase in development vulnerability. Proposals within these areas should facilitate greater floodwater storage." Clause 4 keeps undeveloped 3b for flood management apart from essential infrastructure.
National policy has moved since 2019. Annex F of the August 2026 NPPF says functional floodplain will normally be land with a 3.3% or greater annual probability of flooding, wider than the SFRA's 1 in 20 year line, and its table 3 says more vulnerable and less vulnerable development in Flood Zone 3b should be refused (NPPF Annex F). Under Annex A, a plan policy that is materially inconsistent with the Framework's decision-making policies is given very limited weight unless it was examined and adopted against this Framework, which P4 was not. So the developed 3b allowance cannot be taken as a settled route: a rebuild of a shop, office or home inside the 1 in 20 year outline should expect the officer and the Environment Agency to test it against table 3, and the position is worth putting to the case officer at pre-application.
Developed 3b is where we start with the footprint. We measure the existing building, check whether the new use moves up the vulnerability scale, and look at undercrofts or voids that keep floodwater routes open. On one central Guildford mixed-use scheme with developed 3b at the rear, our revised assessment and a ground-floor colonnade led the Environment Agency to withdraw its objection. Our guide to Flood Zone 3b, the functional floodplain sets out the national rules.
Policy P11 (Sustainable Surface Water Management): runoff on every site
Policy P11 asks every scheme, of any size, to hold runoff at or below its pre-development level. Clause 2 reads: "Previously developed sites are required to achieve runoff rates and volumes as close as reasonably practicable to greenfield runoff rates. In any case, runoff rates and volumes must be no greater than the conditions of the site prior to the development" (Development Management Policies, March 2023). Greenfield sites must match greenfield rates and volumes. Clauses 1, 3 and 4 also apply to all development: intercept as much rainwater as possible, maximise permeable surfaces, and avoid boreholes or other deep structures for surface water "except for clean roof water".
Major schemes and sites at risk of flooding, which P11 defines as Flood Zones 2 and 3 and any Flood Zone 1 land with critical drainage problems notified by the Environment Agency, take on clauses 5 to 8: the discharge hierarchy, natural flood management and SuDS first, compliance with the Lead Local Flood Authority's guidance, and two infiltration rules. A soakaway needs "at least 1 metre of vertical distance between the base of the infiltration system and the maximum likely groundwater level", and in Source Protection Zone 1, on known contaminated land or where seasonal groundwater is high, a hydrogeological risk assessment is needed if anything other than clean roof drainage is to go into the ground.
Two parts of P11 now sit awkwardly with Surrey County Council's practice. Clause 7(b) points to Defra's 2015 non-statutory technical standards, while the county has assessed every new consultation against the June 2025 National Standards for sustainable drainage since 6 October 2025. And the county's major-development guidance says deep bore soakaways may suit parts of Surrey, while P11 expects Guildford schemes to avoid them for anything but clean roof water. Our strategies for P11 show the before-and-after rates and volumes, the infiltration test results against the 1 m rule, and the treatment train, written to the 2025 standards so they also clear the county.
Policy P10 (Water Quality, Waterbodies and Riparian Corridors): the 10 m buffer
Policy P10 keeps development back from rivers. Clause 5 reads: "Development proposals are required to retain or reinstate an undeveloped buffer zone on both sides of a main river measuring a minimum of 10 metres from the top of the riverbank that is supported by a working methods statement detailing how the buffer zone will be protected during construction, and a Landscape and Ecological Management Plan detailing how it will be enhanced in the long-term. For ordinary watercourses, an appropriate buffer is expected that is sufficient to protect and enhance the biodiversity and amenity value of the watercourse." Clause 6: "Development proposals that include the culverting of watercourses, hard bank revetment or which prevent future opportunities for de-culverting and naturalisation of watercourse banks will not be permitted. Development proposals are expected to return banks to a natural state." Clause 8: "Development proposals are required to identify opportunities for Natural Flood Management, creating wetland features and reconnecting rivers with their floodplains in order to restore natural processes, enhance biodiversity and help manage flood risk." (Development Management Policies) We plot the top of bank and the 10 m line on the drainage and flood plans, so outfalls, levels and any compensatory storage stay outside the buffer.
Policy D15 (Climate Change Adaptation) and heavier rainfall
Policy D15 asks proposals to "demonstrate adaptation for more frequent and severe rainfall events through measures including: a) retaining existing and incorporating new water bodies; b) designing planting and landscaping schemes to absorb and slow down surface water; and c) the use of permeable ground surfaces wherever possible" (Development Management Policies). It overlaps with P11, and the council's Climate Change, Sustainable Design, Construction and Energy SPD, adopted on 3 October 2024, carries a questionnaire for non-major applications. We list the SuDS features in the drainage strategy in terms that can be lifted straight into that questionnaire or a sustainability statement.
Policy D13 (The Corridor of The River Wey & Godalming Navigations)
Policy D13 applies to proposals affecting the Navigations and their setting, and clause 1(e) asks them to "integrate flood risk mitigation measures where the design and material palette are responsive to the character and the site's immediate context". A flood wall or raised threshold on the towpath frontage is therefore a design question as much as a flood one, so we set out the mitigation options and their levels before the elevations are fixed.
Burpham Policy B-FD 4 (Water Supply & Sewerage Infrastructure)
In Burpham, Policy B-FD 4 approves new homes once the applicant shows that water and sewerage demand will be met, that "The development can be justified having regard to appropriate flood risk assessments and application of the sequential test in accordance with Planning Practice Guidance", and that surface water will be dealt with by SuDS where appropriate (Burpham Neighbourhood Plan). Its notes add that surface water must not go to the foul sewer. Our Burpham reports pair the FRA with the sewer capacity response the policy expects.
East Horsley Policy EH-EN5 (Flooding): drainage that passes through higher-risk land
East Horsley's Policy EH-EN5 looks downstream. Where surface water from a site will "at some point downstream" run through land at higher risk than Flood Zone 1, the applicant must show "the system is capable of accepting the anticipated extra load". The policy continues: "Development proposals in such locations are required to ensure that existing drainage systems are not worsened, and ideally are improved, as a result of the proposed development. They must also ensure that no increase in surface water flooding will arise at the development site or the surrounding area as a consequence of the development." (East Horsley Neighbourhood Plan) We trace the outfall to the receiving ditch or sewer and check its capacity as part of the drainage strategy.
Effingham Policy ENP-G4 (Flooding) and the sequential test
Effingham's plan area drains to the River Mole, and Policy ENP-G4 starts from avoidance: "Proposals for development should avoid areas at highest risk of flooding in favour of lower risk areas." It continues: "Given that many parts of the Plan Area are susceptible to groundwater and surface water flooding, it is appropriate that the Sequential Test […] should be applied to all proposed developments. All development proposals will be required to demonstrate that they will not result in an increase in surface water run-off and should have regard to appropriate mitigation measures identified in the Guildford Surface Water Management Plan. Priority will be given to incorporating SuDs (Sustainable Drainage Systems) to manage surface water drainage, unless it can be demonstrated that they are not appropriate. Where SuDs are provided, arrangements must be put in place for their management and maintenance over their full lifetime." (Effingham Neighbourhood Plan, April 2018; the bracket omits the plan's reference to a paragraph of an earlier Framework.) The plan predates the August 2026 NPPF, whose policy F5 exempts householder development, small non-residential extensions and most changes of use from the sequential test, so how much weight ENP-G4 carries on a small scheme is a point to confirm with the case officer.
West Horsley Policy WH13 (Sustainable Urban Drainage)
Policy WH13 supports proposals that include one or more of four sustainable drainage features, "adequate to the scale of the development": "permeable driveways and parking areas; water harvesting and storage features; green roofs; and soakaways". It adds: "Any new development will need to ensure that appropriate provision and any necessary mitigation is assessed, delivered and maintained for the lifetime of the development, unless demonstrated to be inappropriate." and "Developers will be required to demonstrate that there is adequate waste water capacity both on and off the site to serve the development and that it would not lead to problems for existing or new users." (West Horsley Neighbourhood Plan) Our West Horsley strategies name the features used and size each one in the calculations.
Lovelace Policy LNPEN3 (Flooding): the 250 sq m threshold
In the Lovelace neighbourhood area, Policy LNPEN3 reads: "Developers must, where applicable: a) Provide a surface water management plan for major developments b) Provide mitigation measures prior to occupation to avoid adverse impacts of surface water, water pollution and flood risk. This includes new areas of hard-standing greater than 250 sqm. c) Design all flood prevention measures to avoid adverse impacts on the TBHSPA. d) Maximise the use of soft landscaping and permeable surfacing materials to increase absorption capacity. e) Incorporate Sustainable Drainage Systems (SuDS) in major developments in locations affected by flood risk." (Lovelace Neighbourhood Plan, May 2021) So a new yard or car park of more than 250 sq m in the area needs its runoff mitigation in place before anyone moves in.
Guildford's next Local Plan and the 2027 handover to West Surrey
Guildford is preparing a new Local Plan under the 2026 plan-making regulations, but it has no draft flood or drainage policies yet, so P4 and P11 remain the policies applied. The council published its notice of intention on 5 June 2026, ran a scoping consultation from 2 September to 15 October 2026, and published its Gateway 1 self-assessment on 30 October 2026, the formal start of plan-making (New Guildford Local Plan).
The timetable updated that day puts the consultation on proposed plan content and evidence, which may include initial draft policies, at 7 April to 19 May 2027, the proposed plan at 1 March 2028, examination from 29 September 2028 and adoption on 30 April 2029. Most of that falls after vesting day, when West Surrey Council becomes the planning authority, and the council's Gateway 1 page notes that the government intends transitional regulations for plan-making across the reorganisation. For any application made before 2029, the 2019 and 2023 plans and the made neighbourhood plans are the documents to answer.
Rebuilding in Guildford's developed floodplain?
Send the address and the drawings, and we will check the P4(3) conditions and the P11 runoff test before the layout is fixed. Get a no-obligation, free quote. One of our experienced flood risk consultants will get back to you within 60 minutes.
Start a QuoteGuildford's validation list: when an FRA, a sequential test or a drainage strategy is needed
The council's Local Validation Checklist was "last updated and reviewed on 7 July 2021", according to its guidance on what to submit. That is more than two years ago, and the Development Management Procedure Order lets a council insist on a local list item only where the list was published or reviewed in the two years before the application, so its flood and drainage items now work as published guidance. They still describe what officers expect to see, and a submission that ignores them invites a request for more information.
The flood risk assessment item asks for an assessment for every proposal in Flood Zones 2 and 3, including 3b, and in Flood Zone 1 where the area has critical drainage problems, is affected by surface water flooding, the site exceeds 1 hectare or a more vulnerable use is introduced. It still cites paragraphs of the superseded 2019 Framework. For major schemes, the council's drainage requirements page asks for a surface water drainage form with the application, and the 2015 advice note it links says that major applications submitted without a Sustainable Drainage Statement "will not be regarded as a 'valid' application". The form it links is Surrey County Council's 2017 pro-forma, written before the county moved to the 2025 National Standards, so we complete it and also address each standard in the strategy. Our article on the SuDS pro-forma explains what the form records.
| Trigger | What is needed | Source |
|---|---|---|
| Every proposal inside Flood Zone 2, 3a or 3b | Site-specific flood risk assessment | NPPF F4(1); council FRA guidance; Policy P4 |
| Flood Zone 1: site of 1 hectare or more, critical drainage problems, land the SFRA or the Flood Map for Planning shows at risk from any source now or in the future, or a change to a more vulnerable use | Site-specific flood risk assessment | NPPF F4(2); council FRA guidance |
| Site at, or potentially at, risk of groundwater flooding | Groundwater flood risk assessment (within the FRA) | Policy P4 supporting text 4.3.45 |
| New development on land at risk from any source of flooding, now or in the future (Flood Zones 2 and 3, and Flood Zone 1 land at risk from surface water, groundwater or other sources), unless the site was allocated after a sequential test, an FRA shows the F5(2)(b) exemption applies, or it is householder development, a small non-residential extension under 250 sq m or a change of use other than to a caravan, camping, chalet, mobile home or park home site | Sequential test; a windfall must also be shown preferable to allocated sites | NPPF F5; Policy P4(2)(b) and its supporting text 4.3.41 |
| Highly vulnerable use in Flood Zone 2; more vulnerable use or essential infrastructure in Flood Zone 3a; essential infrastructure in 3b | Exception test (none in Flood Zone 1, none where the sequential test is not required, and none on a site allocated after an exception test at plan-making unless the flood risk to the site has since increased significantly or the development has changed significantly so as to introduce a more vulnerable use) | NPPF F6 and Annex F table 3 |
| A more vulnerable or less vulnerable use proposed inside Flood Zone 3b | Should be refused under Annex F table 3; Policy P4(2)-(3) allows development in developed 3b only where the clause 2 tests are met, the footprint is no larger than the existing building's and there is no increase in vulnerability, and expects proposals to facilitate greater floodwater storage; very limited weight likely under Annex A | NPPF F6, Annexes A and F; Policy P4(3) |
| Major development (10 or more homes, 1,000 sq m of floor space, a site of 1 hectare or more, or 0.5 hectares of housing where the number of homes is not yet known) | Surface water drainage strategy and statement with the county pro-forma; Surrey County Council consulted | Council drainage requirements page; 2015 advice note; Policy P11 |
| Any development | Evidence that runoff will not exceed the pre-development rate and volume | Policies P4(5) and P11(2) |
| Infiltration SuDS on a major development or a site at risk of flooding (Flood Zone 2 or 3, or Flood Zone 1 with critical drainage problems), in Source Protection Zone 1, on contaminated land or with high seasonal groundwater, taking more than clean roof drainage | Hydrogeological risk assessment | Policy P11(8)(b) |
| Culverting or other works on an ordinary watercourse; any works within 8 m of a Main River | Consent from Surrey County Council (ordinary watercourse); a possible environmental permit from the Environment Agency (Main River) | Surrey non-major guidance 3.4 and 3.5 |
| Internal drainage board consent | Not needed: no board operates in the borough | Council and county guidance |
National policy goes further than the council's list in one respect: F4(2)(c) covers any Flood Zone 1 land shown at risk from any source in the SFRA or the Flood Map for Planning, now or in the future, not only land affected by surface water. A first check on our flood risk map shows the flood zone and the surface water bands for an address, and our article on planning applications invalidated over flood risk and drainage covers how missing drainage evidence delays registration.
Surrey County Council's SuDS rules on Guildford sites
Surrey County Council reviews drainage for Guildford major schemes against its guidance for major development, reviewed on 15 September 2026, and the 2025 National Standards. Its non-major guidance, reviewed on 10 March 2026, applies the same principles to smaller sites. The points that shape a Guildford strategy most often:
- Rainwater use first. Surrey is a water-stressed area, so the county always requires collection for non-potable use, normally paired with an outfall to ground or off site.
- Lowest achievable discharge. Rates are limited to the lowest achievable for the design storm; where a site adds runoff volume, most are held to the 50% AEP (1 in 2 year) rate, and a brownfield relaxation applies only in exceptional circumstances.
- Infiltration evidence. BRE Digest 365 test results and groundwater levels with the application, or a reason and a desk study; the county's condition asks for a 1 m unsaturated zone below each soakaway and half-drain times.
- Design storms. Calculations for the 1 in 30 and 1 in 100 year events with climate change, plus a 10% allowance for urban creep.
- First 5 mm on site. On a non-major scheme that does not infiltrate, the first 5 mm of every rainfall event must be managed on site.
- Highways kept separate. No new private surface water into highway drains or onto the road surface; an exceedance plan with levels and flow directions.
P11's 1 m rule and the county's 1 m unsaturated zone point the same way, and on the chalk that can mean winter groundwater readings before a soakaway is relied on. Our BRE 365 infiltration rate calculator and ground conditions map give a first view, and our guide to BRE 365 infiltration testing covers the test itself. The county also offers chargeable pre-application advice, and our article on answering an LLFA objection covers what happens when it is not satisfied. The 2025 National Standards article sets out the seven standards in full.
Guildford's 2016 SFRA, Level 1 and Level 2
The evidence behind P4 is a Level 1 SFRA and a Level 2 SFRA, both prepared by Capita in 2016. Neither has been replaced, and the council's old SFRA landing page now returns an error, so the documents are reached directly:
- Level 1, Volume 1 (July 2016). The Decision Support Document maps flood zones, surface water, groundwater and sewer flooding, and splits the 1 in 20 year outline into developed and undeveloped 3b; where no 1 in 20 year modelling exists, Flood Zone 3 stands in or the extent is agreed with the Environment Agency.
- Level 2 (May 2016). The Level 2 SFRA assessed the sites the council was considering for allocation, to inform the exception test, giving the share of each site in each flood zone.
- Surface water studies. P4(5) asks proposals to have regard to the Guildford Surface Water Management Plan and the Ash Surface Water Study, both by Halcrow, which name hotspot streets and actions.
- No update yet. The new Local Plan's evidence pages list no new SFRA so far, so the 2016 documents remain the council's flood evidence.
Two things follow for an applicant. The SFRA's 1 in 20 year line is narrower than the 3.3% definition in Annex F, so a site just outside the mapped 3b may still be treated as functional floodplain; and SFRA climate change extents predate the allowances last updated on 27 May 2022, so we rerun or adjust them for the site. Our explainer on strategic flood risk assessments sets out what an SFRA can and cannot settle.
Chapter 18 of the August 2026 NPPF in a Guildford decision
Guildford decisions now apply Chapter 18 of the National Planning Policy Framework, which took effect on 17 August 2026. F4 sets when a site-specific assessment is needed, including on Flood Zone 1 land "identified in a strategic flood risk assessment or the Flood Map for Planning as being at risk of flooding from any source, whether now or in the future". F5 sets the sequential test and caps its reach: "The area to which the test is applied should not be greater than the anticipated catchment of the development in terms of its likely occupiers or users."
F5(2) also exempts allocated sites that were tested when the plan was made, and sites where an assessment shows clearly that "No built development within the site boundary, including access or escape routes, land raising or other potentially vulnerable elements, would be located on an area that would be at risk of flooding from any source, now and in the future", or that, at risk of surface water flooding only, occupiers and users would stay safe for the development's lifetime "without increasing flood risk elsewhere". F6 sets the exception test, which does not apply where the sequential test is not required, and F8 expects sustainable drainage to follow the 2025 National Standards, taking account of the Lead Local Flood Authority's advice on major schemes.
Alongside the Framework sit the flood risk and coastal change guidance, last updated on 17 September 2025, and the climate change allowances, last updated on 27 May 2022. Our NPPF guidance and advice page covers the national rules, our article on the August 2026 NPPF changes explains what moved, and our explainers on how the sequential and exception tests work and the surface water exemption go into F5 and F6.
Where flooding comes from across Guildford borough
The Wey is the main source in the town. The SFRA records no formal flood defences in the borough, and the Environment Agency, the borough council and Surrey County Council submitted the Outline Business Case for a Guildford Flood Alleviation Scheme in June 2026, which the council says would protect around 750 properties (council news, 5 June 2026). Until a scheme is funded and built, assessments use today's flood levels; our article on the Guildford Flood Alleviation Scheme follows its progress, and the town's history is on our page on flood risk assessment in Guildford.
Away from the main river, the River Tillingbourne runs through Gomshall, Shere and Chilworth to join the Wey at Shalford, and Cranleigh Waters joins the Wey near Shalford too; our River Wey page follows the river from source to the Thames, and the live river levels map shows current readings. The Ash side of the borough drains to the Blackwater, the area the Ash Surface Water Study covers, and Effingham lies in the Mole catchment, where the neighbourhood plan records groundwater coming up to the surface in parts of the village. Surface water is the other recurring source: Surrey County Council's Section 19 report on the town centre records 15 properties and one commercial property flooded on three dates in August, September and October 2024, mostly away from the river.
Guildford shares Surrey County Council's drainage rules with Waverley, Elmbridge, Mole Valley and Spelthorne, and Waverley and Spelthorne join it in West Surrey Council. The county as a whole is on our Surrey page, and every council we cover is listed under local authorities.
Reports for a planning application to Guildford Borough Council
A flood risk assessment asks whether the site is safe and keeps risk from rising elsewhere; a sequential test asks whether a lower-risk site was available; a drainage strategy works out where the rain goes and how fast. In Guildford P4 drives the first two and P11 the third, and each is a separate report with its own evidence. Applications to Guildford Borough Council receive reports from Unda Consulting Limited, a CIWEM Business Partner whose consultants are chartered.
- Every source in one report. P4 asks for safety over the development's lifetime from the Wey, surface water, groundwater and sewers alike, which our flood risk assessment work covers.
- Flood Zones 2 and 3, and the Zone 1 triggers. An application in the flood zones, over a hectare or on mapped surface water risk needs a flood risk assessment for planning.
- Buying beside the Wey. Homes near the Wey can be flagged in conveyancing searches, and a flood risk survey for property purchase looks at the building itself.
- Windfall sites in the flood zones. F5 asks new development on land at risk from any source of flooding, now or in the future, to pass the sequential test unless one of its exemptions applies, and F6 adds the exception test in the cases Annex F table 3 sets out: the sequential and exception test.
- Runoff on every scheme. P11(2) caps runoff rates and volumes at their pre-development level on any site, so most applications need a drainage strategy.
- Major schemes reviewed by the county. Surrey County Council checks rates, storage, infiltration and exceedance against the 2025 standards in a surface water drainage strategy.
- After permission. The county's standard condition asks for final details and a verification report, which discharge of drainage conditions provides.
- National policy in each decision. Every Guildford decision now weighs P4 against Chapter 18 and Annexes A and F, set out in our NPPF guidance and advice.
- Chalk, greensand and SPZ1. P4's supporting text calls for groundwater evidence, and P11(8)(b) for a hydrogeological risk assessment where infiltration SuDS on a major or at-risk site in Source Protection Zone 1, on contaminated land or with high seasonal groundwater would take more than clean roof drainage, covered by a groundwater flood risk assessment.
- Warnings and evacuation. P4(2)(e) asks for approved flood warning and evacuation plans where relevant, prepared as a flood warning and evacuation plan.
- No 1 in 20 year outline. Where the SFRA has no modelled 3b, Flood Zone 3 stands in as the functional floodplain unless a site-specific assessment agrees the extent with the Environment Agency, and flood modelling can define it for one site.
- Sewer capacity. Burpham's B-FD 4 and West Horsley's WH13 ask for proof of waste water capacity, set out in a foul drainage strategy.
- Homes that have flooded. Property in the town centre flooded in 2024, and a flood risk assessment for insurance gives an insurer evidence for one address.
Flood and drainage questions from Guildford applicants
What does Guildford Policy P4 require from a planning application?
Policy P4, in the Local Plan: Strategy and Sites adopted in April 2019, permits development in areas at medium or high risk of flooding, including the 'developed' flood zone 3b, "provided that: a) the vulnerability of the proposed use is appropriate for the level of flood risk on the site b) the proposal passes the sequential and exception test (where required) as outlined in the NPPF and Government guidance c) a site–specific flood risk assessment demonstrates that the development, including the access and egress, will be safe for its lifetime, taking into account climate change, without increasing flooding elsewhere, and where possible, will reduce flood risk overall d) the scheme incorporates flood protection, flood resilience and resistance measures appropriate to the character and biodiversity of the area and the specific requirements of the site e) when relevant, appropriate flood warning and evacuation plans are in place and approved and f) site drainage systems are appropriately designed, taking account of storm events and flood risk of up to 1 in 100 year chance with an appropriate allowance for climate change." Clause 5 adds: "All development proposals are required to demonstrate that land drainage will be adequate and that they will not result in an increase in surface water run-off." Its supporting text says: "Proposals for development in areas at, or potentially at, risk of groundwater flooding will also be required to submit an assessment of groundwater flood risk."
Does a Flood Zone 2 site in Guildford borough need a flood risk assessment?
Yes. The council asks for an assessment for every proposal in Flood Zones 2 and 3, and national policy F4 says the same. In Flood Zone 1 one is needed for sites of a hectare or more, land with critical drainage problems, a change to a more vulnerable use, or land the SFRA or the Flood Map for Planning shows at risk from any source.
Is the Guildford validation checklist still in force?
It is still published, but the council says it was last updated and reviewed on 7 July 2021. Because that is more than two years ago, the council cannot insist on the list's local items before registering an application, so they act as guidance. Officers still expect the flood risk and drainage evidence it describes, and the 2015 advice note asks for a Sustainable Drainage Statement on major schemes.
What runoff rate will Guildford and Surrey County Council accept on a brownfield site?
Policy P11 asks for rates and volumes as close as reasonably practicable to greenfield, and never greater than before development. Surrey County Council looks for the lowest achievable rate, limits most sites that add runoff volume to the 1 in 2 year (50% AEP) rate, and allows a brownfield relaxation only in exceptional circumstances.
Can a house be rebuilt in Guildford's functional floodplain?
Policy P4 clause 3 says: "Development proposals in the 'developed' flood zone 3b will also only be approved where the footprint of the proposed building(s) is not greater than that of the existing building(s) and there will be no increase in development vulnerability. Proposals within these areas should facilitate greater floodwater storage." Annex F of the August 2026 NPPF says more and less vulnerable development in Flood Zone 3b should be refused, and Annex A gives a materially inconsistent local policy very limited weight, so raise the scheme with the case officer early.
Who decides Guildford planning applications after April 2027?
Guildford Borough Council decides them until 31 March 2027. From 1 April 2027 West Surrey Council becomes the planning authority for Guildford, Runnymede, Spelthorne, Surrey Heath, Waverley and Woking and also takes over Surrey County Council's services there, including the drainage advice the county gives now.
Applying to Guildford before vesting day?
Tell us the site and the scheme, and we will scope the flood risk and drainage evidence that P4, P11 and Surrey County Council expect. Get a no-obligation, free quote. One of our experienced flood risk consultants will get back to you within 60 minutes.