Medway Council still decides flood risk against saved Policy CF13 of the Medway Local Plan 2003, which refuses development in a tidal flood risk area that would put living or sleeping rooms below the estimated flood level. The replacement Medway Local Plan 2041 was submitted for examination on 18 December 2025, and its Phase 2 hearings run until 27 November 2026. On drainage, the council's 2025 guidance as Lead Local Flood Authority asks for BRE 365 tests and, in many cases, a year of groundwater monitoring before it accepts infiltration.
Every flood risk and drainage requirement on a Medway application comes from one council. Medway is a unitary authority, so Medway Council decides the planning application and also reviews its surface water as the Lead Local Flood Authority; Kent County Council has no flood role in the Medway towns or on the Hoo Peninsula. Strood, Rochester, Chatham and Gillingham line the tidal Medway, and the Hoo Peninsula sits between the Medway and the Thames estuary. The council's Level 1 SFRA counts over 40 km of coastline and records defences along all of it apart from Allhallows-on-Sea.
For applications to Medway Council we prepare the flood risk assessment, the sequential and exception tests and the drainage strategy, each as its own report. Applications to Medway are supported by reports from Unda Consulting Limited, a CIWEM Business Partner, and our consultants are chartered. To talk a site through, call 01293 214444 or email enquiries@unda.co.uk.
Saved Policy CF13 and the other Medway flood policies in force today
A planning application to Medway is decided against the Medway Local Plan 2003, adopted on 14 May 2003. Its policies were kept in force by a Secretary of State direction dated 21 September 2007; those left off the list expired on 27 September 2007. Three saved policies deal with flood risk and water: CF13 on tidal flood risk areas, CF12 on water supply and groundwater, and BNE45 on the undeveloped coast. Two of Medway's three made neighbourhood plans add wording on sustainable drainage, and every one of these is read alongside Chapter 18 of the August 2026 NPPF.
| Policy | Title | What it requires | Your obligation | How Unda meets it | Source and date |
|---|---|---|---|---|---|
| Policy CF13 | Tidal Flood Risk Areas | Refuses development in a tidal flood risk area that harms the defences, gives no means of escape, puts residential living and sleeping accommodation below the estimated flood level, or introduces mobile homes, caravans or new holiday accommodation between October and May | Show the estimated flood level, floor levels, the effect on the defences and the escape route | A flood risk assessment that sources the flood level, sets living and sleeping floors above it on sections, tests the defences and plans the escape | Medway Local Plan 2003, adopted 14 May 2003 |
| Policy CF12 | Water Supply | No harm to the quality or yield of water supply, to aquifer recharge, or to the flora, fauna (including fisheries) and amenity of watercourses and habitats that depend on maintained water levels, and no unacceptable risk to groundwater quality unless appropriate measures protect those resources | Where infiltration or deep works are proposed, show groundwater is protected | A drainage strategy that checks the Source Protection Zone and the aquifer before choosing infiltration | Medway Local Plan 2003, adopted 14 May 2003 |
| Policy BNE45 | Undeveloped Coast | Development on the undeveloped coast only where a coastal location is essential and no suitable alternative site exists on the developed coast, the coast's scenic, heritage or scientific value is kept, and the site will not be at such risk from flooding or erosion that it needs defence works | Show the scheme will not depend on new defences | A flood risk assessment testing tidal risk now and with climate change | Medway Local Plan 2003, adopted 14 May 2003 |
| Policy HOO6 | Design (Hoo St Werburgh and Chattenden Neighbourhood Plan) | Water-permeable hard landscaping; SuDS designed into open space and green infrastructure wherever possible | Show SuDS as part of the landscape layout | A drainage strategy that places above-ground SuDS within the open space plan | Hoo St Werburgh and Chattenden Neighbourhood Plan, referendum 7 November 2024 |
| Policy BNE1 | Public Realm Enhancement (Arches Chatham Neighbourhood Plan) | Supports public realm schemes that use permeable surfaces or other SuDS where possible to cut surface water flood risk | On public realm works, consider permeable surfaces | Permeable surfacing tested in the drainage strategy | Arches Chatham Neighbourhood Plan, adopted 15 May 2024 |
| Draft Policy DM1 (submitted, at examination) | Flood and Water Management | Site-specific assessments, floor levels above the design flood level with freeboard, a 16 m minimum set-back from tidal main rivers, greenfield runoff rates and volumes, no surface water to the foul or combined sewer, and a surface water management strategy with a SuDS proforma for major schemes and for schemes in a Sensitive Drainage Area | Not yet in force; draft policy that officers read with the 2003 plan | Assessments and drainage strategies written to the draft wording now | Medway Local Plan 2041, Regulation 22 submission, December 2025 |
| Draft Policy S1 (submitted, at examination) | Planning for Climate Change | A sequential approach to avoid flood risk areas, natural flood management where possible, and existing flow routes and drainage features kept | Not yet in force; draft policy | Flow routes mapped and kept in the drainage layout | Medway Local Plan 2041, Regulation 22 submission, December 2025 |
Requirements checked November 2026.
Policy CF13 (Tidal Flood Risk Areas): how Medway applies it on the riverside
Policy CF13 lets Medway Council refuse development in a tidal flood risk area on any one of five grounds. The floor-level ground is the one a riverside layout has to be drawn around. The policy reads: "Development will not be permitted within a tidal flood risk area if:- (i) it harms the integrity of the flood defences; or (ii) it fails to provide for a means of escape for people in the event of a flood; or (iii) it introduces residential living and sleeping accommodation below the estimated flood level; or (iv) it introduces mobile homes or caravans; or (v) it introduces new holiday accommodation between October and May" (Medway Local Plan 2003, page 297).
The supporting text names the places it has in mind. Paragraph 9.5.35 lists Halling and Cuxton Marshes, the Hogmarsh Valley, the Rochester and Strood riverside and the riverside area of Gillingham as susceptible to flooding. Paragraph 9.5.34 warns that low-lying land could flood if the defences were breached or overtopped, and asks developers to respond "by not locating habitable rooms at ground floor level". Where the ground has to be raised instead, it says the aim is ideally to limit flood depth to no more than 1.2 metres. Paragraph 9.5.36 adds that the council takes Environment Agency advice on conditions such as slab levels and floodplain storage.
CF13 contains no sequential test, so for a site at risk that test comes from policy F5 of the NPPF, and the Environment Agency advises on tidal levels and the defences. The council's Level 1 SFRA of November 2025 notes that the Environment Agency typically asks for finished floors 300 mm above the design flood level for living space and 600 mm above it for sleeping space.
How we meet it: our flood risk assessment states the estimated flood level for the site and where it comes from, shows ground-floor uses and floor levels against it on sections, describes the escape route, explains how the defences are protected during and after building, and confirms that no caravan, mobile home or October to May holiday use is introduced.
Policy CF12 (Water Supply) and Policy BNE45 (Undeveloped Coast)
Policy CF12 matters wherever a scheme drains to the ground. Its four grounds for refusal include development that "would prevent or reduce replenishment of groundwater aquifers" or that "would represent an unacceptable risk to the quality of groundwater resource, unless appropriate measures are taken to adequately protect those resources" (Medway Local Plan 2003, pages 295 to 296). The council's SFRA asks applicants who propose infiltration to check the Environment Agency's Source Protection Zone maps, and our guide to groundwater source protection zones explains what that check involves.
Policy BNE45 applies on the undeveloped coast shown on the 2003 proposals map. Development there is permitted only if, among other tests, "the development is not likely to be at risk from flooding or coastal erosion to the extent that it would require defence works for its safety and protection" (Medway Local Plan 2003, page 111).
How we meet them: our drainage strategy records the Source Protection Zone and the aquifer before it relies on infiltration, and on coastal land our flood risk assessment tests the tidal risk now and with climate change, so the case that no new defence is needed rests on numbers.
Neighbourhood plan Policy HOO6 (Design) and Arches Policy BNE1 (Public Realm Enhancement)
Medway has three made neighbourhood plans, and two of them contain sustainable drainage wording. The Hoo St Werburgh and Chattenden Neighbourhood Plan 2023-2040, made after its referendum of 7 November 2024, says in Policy HOO6 part 6 that "Hard landscaping materials should take account of the local context and be water permeable", and in part 8 that "A variety of Sustainable Drainage Systems (SuDS) should be sensitively designed to form an integral part of new open spaces and green infrastructure, wherever possible."
The Arches Chatham Neighbourhood Plan, adopted on 15 May 2024, supports public realm improvements that include "Where possible, incorporating permeable surfaces and/or other suitable sustainable drainage systems (SuDS) designs to reduce the risk of surface water flooding and increase local resilience to climate change." The Cliffe and Cliffe Woods plan, adopted on 24 May 2023, has no flood or drainage policy. In Hoo and the Arches area, our drainage strategies show the SuDS inside the landscape and open space layout instead of as pipes and tanks alone.
Draft Policy DM1 (Flood and Water Management) in the submitted Medway Local Plan 2041
The Medway Local Plan 2041 will replace the 2003 plan once adopted, and it is now at examination. The council consulted on it under Regulation 19 from 30 June to 11 August 2025 and submitted it on 18 December 2025. The inspectors held Phase 1 hearings in September 2026, and the Phase 2 hearings on transport, infrastructure and the site allocations run from 17 to 20 and 24 to 27 November 2026, with a further session on Gypsy and Traveller sites set for 4 February 2027. No main modifications have been published for consultation yet.
Draft Policy DM1 in the submitted plan is far more detailed than CF13. It says that "Development should not encroach within a minimum of 16m to tidal main rivers, unless justified by evidence at planning application stage, and agreed in consultation with the Environment Agency". Where development passes the tests, draft DM1 says "finished floor levels should be raised above the design flood level and include the Environment Agency's recommended additional freeboard requirements" (Medway Local Plan 2041, Regulation 22 submission, December 2025).
On drainage, the submitted draft of DM1 says "Development should utilise SuDs and replicate Greenfield runoff rates and volumes" and that "surface water will not be permitted to discharge to the foul or combined sewer network". It would also require a surface water management strategy with an accompanying SuDS proforma for major development and for non-major development in a Sensitive Drainage Area identified by the Level 1 SFRA. On sites in a Source Protection Zone, the draft asks applicants proposing infiltration to show they have consulted the water company responsible.
The sewer wording may change. After the Phase 1 hearings the inspectors asked the council, in action M6.4, to consider modifying draft DM1 so that it would "not allow new surface water connections to the foul network and resist new connections to the combined sewer network" and "encourage the separation of rainwater from wastewater at source". The council sent its schedule of modifications on 9 October 2026 (inspectors' action points, MLP/ED42, 11 November 2026), following its statement of common ground with Southern Water.
Two other submitted policies touch flood risk. Draft Policy S1 (Planning for Climate Change) asks for a sequential approach to avoid flood risk areas and for existing surface water flow routes and drainage features to be kept. Draft Policy SA4 (River Waterfront), heard under Matter 13 of the Phase 2 hearings, says that on the Gillingham waterfront "Flood mitigation and/or a flood defence wall will be required to enable delivery".
How we meet them: until adoption, applications are still decided on the 2003 plan and national policy, with the submitted plan as a material consideration. We write flood risk assessments and drainage strategies to the draft DM1 tests now, showing the 16 m set-back from a tidal main river, freeboard on floor levels, greenfield rates and volumes, and no new surface water connection to the foul sewer. A scheme designed that way should not need reworking if the policy is adopted as drafted or as modified.
Medway Council, the Environment Agency, Southern Water and the marsh board: who decides what
No county council sits above Medway, so three public bodies and the sewerage company shape a decision. The North Kent Marshes board only matters if the site drains to its watercourses or lies near them.
| Body | Role | What it decides or is consulted on |
|---|---|---|
| Medway Council | Local planning authority | Decides the application against CF13, CF12 and BNE45 of the 2003 plan, any made neighbourhood plan and Chapter 18 of the NPPF; checks the submission against its April 2025 validation checklist |
| Medway Council | Lead Local Flood Authority | Statutory consultee on major applications and on applications in areas at high risk of surface water or tidal flooding; land drainage consent for works on ordinary watercourses; Section 19 flood investigations; the Local Flood Risk Management Strategy 2023-2028; also the coast protection authority |
| Environment Agency | Statutory consultee | Tidal and river flood risk on the Medway and the Thames estuary, the defences and the Medway Estuary and Swale strategy; works on or near a main river or a sea defence may also need its flood risk activity permit |
| Southern Water | Sewerage undertaker | Agreement to any new or increased sewer connection; on the submitted plan's allocations with limited network capacity, occupation phased to match network reinforcement (statement of common ground) |
| North Kent Marshes Water Level Management Board | Internal drainage board | Consent under its byelaws, confirmed on 17 June 2026, for water introduced into its watercourses and for works within 9 m of them; a Surface Water Development Charge where a scheme adds runoff to its district |
The two council roles look at different things. A planning officer weighs CF13 and the NPPF, while the LLFA officer checks the drainage calculations against the 2025 guidance, and a scheme can satisfy one and stall on the other. Our explainers on the Lead Local Flood Authority, on how planning authorities handle flood risk and SuDS and on answering an LLFA objection go further. Kent and Medway's reorganisation into new unitary councils is paused, with a government decision expected in early 2027; until then Medway Council remains the planning authority and the flood authority.
Building near the tidal Medway in Strood, Chatham or on the Hoo Peninsula?
Send us the address and the scheme. One of our experienced flood risk consultants will get back to you within 60 minutes with a free, no-obligation, fixed quote for the reports CF13 and the council's drainage guidance call for.
Start a QuoteMedway's 2025 SuDS technical guidance: runoff, storage and groundwater
As Lead Local Flood Authority, Medway Council sets out what it expects on drainage in its Technical Guidance for Planning Applications and Condition Discharge Applications 2025. The guidance says each site is assessed individually, suggests pre-application talks for major schemes and sites in complex areas, and covers outline, full and conversion applications as well as the conditions the LLFA recommends.
- Runoff rates. The guidance says that "For new development the proposed run-off rates should not exceed the Greenfield Runoff rates for the matching return period". Rates are worked out on the whole development site, less large open spaces that will not drain to the SuDS, and "should be restricted to either Greenfield or Brown field depending on the current use, however proximity to outfall will be considered".
- Long-term storage. Where a site does not drain to the ground, the guidance expects long-term storage on top of the attenuation volume, so that discharge does not exceed "the Qbar (1 litres per second per hectare)".
- Climate change. Citing the Environment Agency's May 2022 climate change allowances, the guidance states: "For Medway, our central allowance is 20% for both the 2050 and 2070 epoch however for the upper limit the allowance should be 45% for the 2050 and 40% for the 2070s." Outline submissions show runoff up to the 1 in 100 year event plus 40%.
- Infiltration tests. Where infiltration is considered acceptable, site-specific testing "should be completed in accordance with BRE 365, including geotechnical assessment", at locations representative of the final discharge points. Our BRE 365 infiltration rate calculator shows how the soakage rate is worked out.
- Groundwater monitoring. When infiltration is accepted, the guidance adds: "In many cases, a years' worth of monitoring should be submitted, however we recognise that this is not always possible and therefore we will consider sites on an individual basis." The SFRA also bars infiltration where groundwater sits within 1 m of the base of the system.
- Design storms. Detailed submissions model the critical duration for the 2-year, 30-year and 100-year storms with the latest climate change allowance, and show how exceedance flows are managed on site without significantly increasing flood risk on or off it.
- The 2025 National Standards. Appendix 1 is a compliance checklist against the seven 2025 National Standards for SuDS, and the guidance says "A checklist is included at Appendix 1 and should be submitted with any application." Its overview paragraph still points to the 2015 non-statutory technical standards, so a strategy covers both.
- Conversions. A conversion with no change in footprint or hardstanding needs a drainage statement covering surface water risk, the drainage hierarchy and any SuDS. Where the footprint changes, it also needs calculations up to the 1 in 100 year plus 40% event, and a scheme to meet the greenfield rate or a detailed justification.
- Adoption and conditions. Medway Council "will generally not adopt and/or maintain SuDS" except highway drainage under a Section 38 agreement, so maintenance arrangements must be shown. The standard conditions cover the SuDS scheme, a signed verification report before occupation (or to an agreed schedule) and, for most major schemes, a construction surface water management plan.
How we meet it: our surface water drainage strategy for a Medway site starts with the ground. We arrange BRE 365 tests and agree any groundwater monitoring early, because a year of readings cannot be compressed. If the ground will not take the water, the strategy works down the hierarchy with greenfield rates and long-term storage, then fills in the 2025 Standards checklist and the SuDS proforma. Our page on whether you need infiltration testing and our ground conditions and soakaway map help with the first question.
The November 2025 Medway SFRA: Flood Zone 3b, floor levels and Sensitive Drainage Areas
Medway's newest Strategic Flood Risk Assessment is in two parts, both by EPS: the Level 1 SFRA (Issue 8, November 2025) and the Level 2 SFRA (November 2025), published with a sequential test report in the Local Plan examination library. The council's own flooding guidance page still links the August 2006 SFRA and says a new one is in preparation, so check the examination library for the 2025 versions. Our guide to what an SFRA does gives the background.
- When it wants an assessment. Section 3.3 asks for a site-specific assessment on all development in Flood Zones 2 and 3, and also on sites of a hectare or more in Flood Zone 1, land in the "Flood Zones plus Climate Change" outline, Flood Zone 1 land the Flood Map for Planning shows at risk of surface water flooding, sites in an area known to have critical drainage problems, Flood Zone 1 land the SFRA shows at greater risk in future, and sites that bring a more vulnerable use into an area at risk from other sources. It also asks for one with a prior approval for a change of use.
- No designated critical drainage areas. The SFRA says the Environment Agency has designated no Critical Drainage Areas in Medway, but that the LLFA may still ask for an assessment where local flooding issues are known, for example in a Sensitive Drainage Area.
- Flood Zone 3b. The functional floodplain is drawn from land that floods in a 1 in 30 year (3.3%) event, taken from the Environment Agency's North Kent Coast and River Medway models.
- Floor levels. For sites at risk of tidal or river flooding, the SFRA says the Environment Agency typically asks for floors 300 mm above the design flood level for living accommodation and 600 mm for sleeping accommodation.
- Defences. Standards of protection range from 1 in 20 to 1 in 1,000 years, and the SFRA says the 2011 Medway Flood Defence Strategy found most urban defences below the standard needed for present-day flood levels. With climate change, many areas now protected could flood, so residual risk has to be assessed behind the walls.
- Sensitive Drainage Areas. Appendix A.7 maps Sensitive Drainage Areas built from flood records and surface water plans. A site inside one is recorded on the SuDS proforma, and the LLFA can impose extra restrictions such as flow limits.
- Discharge rules. Discharge should replicate greenfield rates if practicable; a 2 l/s minimum is accepted only when all other options are exhausted, and the runoff volume "should never exceed the greenfield volume for the 1 in 100 year return period rainfall event with a 6 hour duration". Tidal outfalls are designed for tide-locking, with six hours of full blockage as the alternative to joint probability analysis, and the first 5 mm of runoff should ideally be stored on site.
- Level 2 and the allocations. The Level 2 SFRA applies Part B of the exception test to 50 site options, 38 of them wholly or partly in Flood Zone 3, using hazard ratings from the 2024 North Kent Coast modelling study.
Table 5.1 of the Level 1 SFRA sets the drainage paperwork by scale. Major development needs a detailed surface water management strategy and the council's SuDS proforma; a minor scheme within 5 m of an existing watercourse must submit the proforma; and for minor development in a Sensitive Drainage Area the council may recommend either. Our article on SuDS proformas explains how they are filled in.
Item 22 of Medway's April 2025 validation checklist, and when each report is triggered
Medway's National and Local Validation Checklist is dated April 2025. The council says it reviewed the list that month and that "no changes to the local list was necessary", so it is within the two-year review period and its local items apply at registration. Item 22, Flood Risk Assessment / Drainage Strategy, asks for an assessment "In flood zone 2 or 3 including minor development and change of use, more than 1 hectare (ha) in flood zone 1; less than 1 ha in flood zone 1, including a change of use in development type to a more vulnerable class (for example from commercial to residential), where the site could be affected by sources of flooding other than rivers and the sea (for example surface water drains, reservoirs); in an area within flood zone 1 which has critical drainage problems as notified by the Environment Agency".
It adds that "A Drainage Strategy would be required for those developments which fall into the above categories which could be affected by surface water run off or increase surface water runoff", and that where both reports are needed the drainage must meet the LLFA's requirements. The checklist marks the item as potentially required on full, outline, reserved matters, variation-of-condition and approval-of-details applications. Its householder column is blank, although the trigger text covers minor development in Flood Zones 2 and 3 and policy F4 of the NPPF asks for an assessment with any proposal in those zones. Separately, the checklist asks for sections showing finished floor levels wherever new floor space is created in a flood zone.
| Trigger | What Medway expects | Source |
|---|---|---|
| All proposals in Flood Zones 2, 3a and 3b, with householder extensions, minor schemes and changes of use among them | Site-specific flood risk assessment; sections showing finished floor levels for new floor space | NPPF policy F4(1); validation checklist item 22; SFRA section 3.3 |
| Sites of a hectare or more in Flood Zone 1 | Flood risk assessment; drainage strategy where runoff is affected | NPPF policy F4(2)(a); validation checklist item 22 |
| Flood Zone 1 land identified in an SFRA or the Flood Map for Planning as at risk from any source, now or in the future, or land the Environment Agency has identified as having critical drainage problems (none designated in Medway) | Flood risk assessment | NPPF policy F4(2)(b) and (c); SFRA section 3.3 |
| Flood Zone 1, under 1 ha, change to a more vulnerable use where other sources could affect the site; prior approval changes of use | Flood risk assessment | Validation checklist item 22; SFRA section 3.3 |
| Site at risk from any source that is not an allocation tested at plan stage | Sequential test, within an area no greater than the development's anticipated catchment. Not needed for householder development, non-residential extensions under 250 m2, or changes of use other than to a caravan, camping or chalet site or a mobile home or park home site; nor where the assessment shows no built development, access or escape route, land raising or other vulnerable element on land at risk from any source now and in the future; nor where the only risk is surface water and the design keeps occupiers safe for the lifetime of the development without increasing flood risk elsewhere | NPPF policy F5 |
| Flood Zones 2, 3a and 3b, where Annex F table 3 calls for it | Exception test; not needed where the sequential test is not required, and never in Flood Zone 1 | NPPF policy F6 |
| Major development (10 or more homes, 0.5 ha or more where the number of homes is not known, 1,000 m2 of new floor space, or a site of 1 ha or more) | Surface water management strategy, SuDS proforma and the 2025 Standards checklist; LLFA consulted | SFRA table 5.1; LLFA technical guidance 2025 |
| Minor development within 5 m of an existing watercourse | SuDS proforma | SFRA table 5.1 |
| Minor development in a Sensitive Drainage Area | Strategy or proforma may be recommended now; draft DM1 in the submitted plan would require both | SFRA table 5.1; draft DM1 (submitted, at examination) |
| Conversion or refurbishment needing LLFA input | Drainage statement; calculations too where the footprint changes | LLFA technical guidance 2025 |
| Water introduced into a North Kent Marshes board watercourse, or works within 9 m of one | Land drainage consent from the board | Board byelaws confirmed 17 June 2026 |
| Works on any other ordinary watercourse | Land drainage consent from Medway Council | Council land drainage page |
A sequential test for a windfall site in Medway is limited by policy F5 to the anticipated catchment of the development, and the SFRA quotes the national guidance that a non-major housing scheme would not usually search beyond the town or city it sits in, or beyond its village and the villages next to it. Our guides to the sequential and exception tests and to Flood Zone 3b cover the method.
Chapter 18 of the August 2026 NPPF beside a 2003 plan
Because Medway's adopted flood policy dates from 2003, much of the day-to-day test comes from Chapter 18 of the National Planning Policy Framework published on 17 August 2026. Policy F4 asks for a site-specific assessment with all proposals in Flood Zones 2, 3a and 3b, and in Flood Zone 1 for sites of one hectare or more, land identified by the Environment Agency as having critical drainage problems, and "Land identified in a strategic flood risk assessment or the Flood Map for Planning as being at risk of flooding from any source, whether now or in the future".
Policy F5 sets the sequential test and says "The area to which the test is applied should not be greater than the anticipated catchment of the development in terms of its likely occupiers or users." It exempts a site where the assessment shows no built development within the site boundary, "including access or escape routes, land raising or other potentially vulnerable elements", would sit on land at risk from any source now and in the future, and a site at risk of surface water flooding only where occupiers "would remain safe from current and future surface water flood risk for the lifetime of the development without increasing flood risk elsewhere". Policy F6 holds the exception test for Flood Zones 2, 3a and 3b, and policy F7 requires development to be safe for its lifetime. Policy F8 says SuDS should "Be designed in accordance with the National Standards for Sustainable Drainage Systems" and, for major development, take account of the LLFA's advice.
Annex A of the Framework says that development plan policies, or parts of them, that are "materially inconsistent" with its decision-making policies "should be given very limited weight", while other policies "should not be given reduced weight simply because they were adopted prior to the publication of this Framework". CF13's floor-level, escape and caravan tests set conditions the Framework does not spell out, so they sit alongside Chapter 18 instead of against it. The flood risk and coastal change guidance was last updated on 17 September 2025, the National Standards for Sustainable Drainage Systems were published on 19 June 2025, and our summary of the August 2026 NPPF changes and our NPPF guidance service cover the detail. The surface water exemption from the sequential test is explained separately.
Tidal estuary, marshes and surface water: flood risk across Medway
Along the riverside, the tide drives the flood risk. The River Medway is tidal through Strood, Rochester, Chatham and Gillingham, and the Hoo Peninsula fronts the River Thames estuary to the north. The submitted Local Plan says the Environment Agency's Thames Estuary 2100 plan, amended in 2023, and the Medway Estuary and Swale Strategy of 2019 set the long-term approach to the defences, with sea level rise of around a metre possible by 2100. Across its district, which runs from Gravesend to Seasalter and includes the marshes of the Hoo Peninsula, the North Kent Marshes board maintains 206 km of watercourses. Our live river levels map shows the gauges on both estuaries.
Surface water is the other big source. The submitted Local Plan notes that a national assessment counted Medway among 116 communities in England at significant risk of surface water flooding. The council's Local Flood Risk Management Strategy records surface water flooding in January 2021 linked to a high tide, and the council has published Section 19 investigations for the floods of May 2018, September 2023 and November 2023. Flooding can be reported on the council's report flooding page, and our flood risk map shows the flood zones and surface water extents for any postcode. Our piece on Section 19 flood investigations explains what those reports are for.
Two of our area pages go further on parts of the district. Flood risk assessment in Gillingham covers Gillingham, Rainham and Hempstead, and flood risk assessment in Rochester covers Rochester and Strood. Our Kent page explains where Kent County Council takes over as flood authority, and every council we cover is listed on our local authority pages.
Reports for applications to Medway Council, and why each one comes up here
An application to Medway can need up to three separate reports: one on whether the site is safe from flooding, one on whether it should be in that location at all, and one on where the rain goes. Groundwater studies and flood modelling sit inside the first.
- Start with the zone. Item 22 of the April 2025 checklist turns on flood zone, site area and source of flooding, and a short review of all three tells you which reports apply: flood risk assessment.
- Tidal and Flood Zone 2 or 3 sites. CF13 turns on the estimated flood level, floor levels and an escape route, all set out in a flood risk assessment for planning.
- Buying on the riverside. With the SFRA reporting most urban defences below the standard needed for present-day flood levels, a buyer in Strood or Chatham needs to know what a breach would mean: flood risk survey for property purchase.
- Windfall sites at risk. CF13 has no sequential test, so policy F5 supplies one for any unallocated site at risk from any source: sequential and exception test.
- Major schemes. The SFRA asks for a detailed surface water management strategy and the SuDS proforma on every major application: drainage strategy.
- Greenfield rates and long-term storage. The 2025 guidance caps runoff at greenfield rates and long-term storage discharge at Qbar: surface water drainage strategy.
- After permission. The LLFA's standard conditions ask for the SuDS scheme, a verification report before occupation and often a construction surface water plan: discharge of drainage conditions.
- Escape in a tidal flood. CF13 refuses schemes with no means of escape, and policy F7 of the NPPF asks for safe access and escape routes as part of an agreed emergency plan where appropriate: flood warning and evacuation plan.
- Infiltration and the aquifer. The LLFA may want a year of groundwater readings, and CF12 refuses development that "would prevent or reduce replenishment of groundwater aquifers", so the groundwater picture needs settling early: groundwater flood risk assessment.
- Breach and overtopping levels. Where the SFRA mapping does not give a level for a particular plot behind the walls, site-specific modelling may be needed to set the floor level: flood modelling.
- Off-mains sites on the peninsula. Draft DM1 in the submitted plan would ask a non-mains scheme to prove a sewer connection is impracticable and to submit the Environment Agency's FDA1 form: foul drainage strategy.
- National policy questions. Where CF13 and Chapter 18 point in different directions, we set out how the two fit together for the officer: NPPF flood risk guidance.
Questions about Medway Council's flood and drainage requirements
What does Medway Policy CF13 (Tidal Flood Risk Areas) mean for a riverside scheme?
CF13, a saved policy of the Medway Local Plan 2003, refuses development in a tidal flood risk area that harms the integrity of the flood defences, fails to provide a means of escape, introduces residential living and sleeping accommodation below the estimated flood level, introduces mobile homes or caravans, or introduces new holiday accommodation between October and May. In practice a riverside scheme needs a flood risk assessment that sets the estimated flood level and shows living and sleeping floors above it.
Does a small Flood Zone 1 site in Medway need a flood risk assessment?
It can. Medway's April 2025 validation checklist asks for one on Flood Zone 1 sites under a hectare where a change to a more vulnerable use is proposed and other sources of flooding could affect the site. NPPF policy F4 also asks for one on Flood Zone 1 land that an SFRA or the Flood Map for Planning shows at risk from any source, now or in the future. Sites of a hectare or more in Flood Zone 1 always need one.
Does draft Policy DM1 apply before the Medway Local Plan 2041 is adopted?
Not as adopted policy. Draft DM1 is part of the plan submitted on 18 December 2025, which is at examination with Phase 2 hearings from 17 to 27 November 2026. Applications are still decided on the 2003 plan and national policy, with the submitted plan as a material consideration. Designing to draft DM1 now, including its 16 m set-back from tidal main rivers, should avoid a redesign if it is adopted.
How long does Medway's groundwater monitoring take before infiltration is accepted?
The council's 2025 LLFA guidance says that in many cases a year's worth of groundwater monitoring should be submitted where infiltration is considered acceptable, though it considers sites individually when that is not possible. Infiltration also needs BRE 365 tests, and the SFRA rules it out where groundwater sits within 1 m of the base of the system.
Can I prepare my own flood risk assessment for a Medway Council application?
No rule stops an applicant writing one, but it has to meet the national guidance checklist, the Environment Agency's standing advice where that applies and, for drainage, the LLFA's 2025 guidance. For tidal sites it must also set an estimated flood level that satisfies CF13.
Who gives land drainage consent for a ditch on the Hoo Peninsula?
Inside the North Kent Marshes Water Level Management Board's district, the board gives consent under byelaws confirmed on 17 June 2026, including for works within 9 m of its watercourses and for water introduced into them. Elsewhere in Medway, consent for works on an ordinary watercourse comes from Medway Council as Lead Local Flood Authority, and main rivers need the Environment Agency.
Need CF13 floor levels and the LLFA's drainage answers before you submit to Medway?
Get a no-obligation, free quote. We will tell you which reports your site needs under CF13, item 22 and the 2025 drainage guidance, priced at a fixed fee, with a fixed quote within the hour.